P543 - REF615 Gajah Tunggal - Pasar Kemis Baru

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Doc. No.

UITJBB/01/04/2021/023
UNIT INDUK TRANSMISI JAWA BAGIAN BARAT
Cinere 16514 – Jakarta Selatan Valid. Januari 2021
DAFTAR SETELAN RELE PROTEKSI GI 150 KV GAJAH TUNGGAL

1. Proteksi : Penghantar 150 KV arah Pasar Kemis II #1


Jenis relai : Line Current Differential Relay (with Distance Relay)
Merek/Tipe relai : ALSTHOM / MICOM P543
LOKASI : GI Gajah Tunggal
PROTEKSI : Bay Pasar Kemis II 1
L1, L2 : 2.58+1.21+2.81 km , 3.5 Km
L3, L4 : 3.5 km , 2.5 Km
Penghantar : CAB-150kV-XLPE PRSYMIAN-2x1000mm + OHL-150kV-ACSR AS 2x450mm +
OHL-150kV-ZEBRA AS 2x484.5mm
CCC : 1513 A +1856 A + 1620 A
Z0 : 0.134 +j 0.513 /km
Z1 : 0.04 +j 0.203 /km
Z2 : 0.039 +j 0.281 /km
Z3 : 0.039 +j 0.281 /km
Z4 : 0.0642 +j 0.205 /km
CT : 2000 A/ 1 A
PT : 150 KV / 100 Volt
SCHEME : POTT

Address Name Value Address Name Value


CB CONTROL
07.0C Single Pole A/R Enabled 07.11 CB Status Input 52B 1 pole
07.0D Three Pole A/R Disabled
Enabled
CONFIGURATION
09.03 Active Settings Group 1 09.21 Supervision Enabled
09.07 Setting Group 1 Enabled 09.23 System Checks Enabled
09.0B Distance Enabled 09.24 Auto-Reclose Enabled
09.0F Phase Diff Disabled 09.2B Measure't Setup Visible
09.12 Broken Conductor Enabled 09.2E Setting Values Secondary
09.18 PowerSwing Block Enabled
CT AND VT RATIOS
0A.01 Main VT Primary 150.0 kV 0A.07 Phase CT Primary 2000 A
0A.02 Main VT Sec'y 100.0 V 0A.08 Phase CT Sec'y 1.000 A
0A.03 CS VT Primary 150.0 kV 0A.0F CS Input BN
0A.04 CS VT Secondary 100.0 V 0A.10 Main VT Location Line
MEASURE'T SETUP
0D.01 Default Display Power 0D.09 Distance Unit Kilometres
0D.02 Local Values Primary 0D.0A Fault Location Distance
0D.03 Remote Values Primary
PROT COMMS/ IM64
20.01 Scheme Setup 2 Terminal 20.18 Comm Fail Timer 10.00 s
20.03 Address 1-A *as site needed 20.1A GPS Sync GPS Disabled
20.10 Comms Mode Standard 20.1B Char Mod Time 500.0 ms
20.11 Baud Rate Ch1 64kbits/s 20.1F Alarm Level 25.00 %
20.13 Clock Source Ch1 Internal 20.20 Prop Delay Stats Enabled
20.17 Comm Delay Tol 350.0 us 20.21 MaxCh1 PropDelay 15.00 ms
OPTO CONFIG
11.01 Global Nominal V 110/125V 11.80 Characteristic Standard 60%-80%
1/5 Daftar Setelan Rele Proteksi Dibuat : AMD Diperiksa : HIK Disetujui : AJI
Rev. 00 GI 150 KV GAJAH TUNGGAL Tgl : 21/01/21 Tgl: 22/01/21 Tgl: 22/01/21
Doc. No. UITJBB/01/04/2021/023
UNIT INDUK TRANSMISI JAWA BAGIAN BARAT
Cinere 16514 – Jakarta Selatan Valid. Januari 2021
DAFTAR SETELAN RELE PROTEKSI GI 150 KV GAJAH TUNGGAL

GROUP 1 LINE PARAMETERS


30.01 Line Length 6.6 km 30.07 Mutual Comp Disabled
30.03 Line Impedance 1.82 Ohm 30.0B Phase Sequence Standard ABC
30.04 Line Angle 78 deg 30.0C Tripping Mode 3 Pole
30.05 kZN Res Comp 0.53 30.10 Line Charging Y 2.000 mS
30.06 kZN Res Angle -5.6 deg
GROUP 1 DISTANCE SETUP
31.0C Setting Mode Advanced 31.B0 Zone P Gnd Stat. Disabled
31.10 PHASE DISTANCE 31.C0 Zone 4 Gnd Stat. Disabled
31.11 Phase Chars. Mho 31.D0 Digital Filter Standard
31.20 Zone 1 Ph Status Enabled Ch Fail 31.D1 CVT Filters Disabled
31.30 Zone 2 Ph Status Enabled 31.D3 Load Blinders Enabled
31.40 Zone 3 Ph Status Enabled 31.D4 Z< Blinder Imp 33.708 Ohm
31.70 GROUND DISTANCE 31.D5 Load/B Angle 45.00 deg
31.71 Ground Chars. Quad 31.D6 Load Blinder V< 15.00 V
31.80 Zone 1 Gnd Stat. Enabled Ch Fail 31.D7 Dist. Polarizing 1.000
31.90 Zone 2 Gnd Stat. Enabled 31.E0 DELTADIRECTIONAL
31.A0 Zone 3 Gnd Stat. Enabled 31.E1 Dir. Status Disabled
31.A2 Zone3 Gnd Offset Disabled
GROUP 1 DIST. ELEMENTS
32.01 PHASE DISTANCE
32.02 Z1 Ph. Reach 1.456 Ohm 32.60 Z2 Gnd. Reach 2.301 Ohm
32.03 Z1 Ph. Angle 78 deg 32.61 Z2 Gnd. Angle 78 deg
32.09 Z1 Sensit. Iph>1 50.00 mA 32.63 Z2 Dynamic Tilt Disabled
32.10 Z2 Ph. Reach 2.301 Ohm 32.65 kZN2 Res. Comp. 0.53
32.11 Z2 Ph. Angle 78 deg 32.66 kZN2 Res. Angle -5.6 deg
32.17 Z2 Sensit. Iph>2 50.00 mA 32.69 R2 Gnd Resistive 26.71 Ohm
32.20 Z3 Ph. Reach 3.769 Ohm 32.6B Z2 Sensit Ignd>2 50.00 mA
32.21 Z3 Ph. Angle 78 deg 32.70 Z3 Gnd. Reach 3.769 Ohm
32.28 Z3 Sensit. Iph>3 50.00 mA 32.71 Z3 Gnd. Angle 78 deg
32.40 Z4 Ph. Reach 0.161 Ohm 32.73 Z3 Dynamic Tilt Disabled
32.41 Z4 Ph. Angle 78 deg 32.75 kZN3 Res. Comp. 0.53
32.46 Z4 Sensit. Iph>3 50.00 mA 32.76 kZN3 Res. Angle -5.6 deg
32.50 GROUND DISTANCE 32.79 R3 Gnd. Res. Fwd 38.16 Ohm
32.51 Z1 Gnd. Reach 1.456 Ohm 32.7C Z3 Sensit Ignd>3 50.00 mA
32.52 Z1 Gnd. Angle 78 deg 32.90 Z4 Gnd. Reach 0.161 Ohm
32.53 Z1 Dynamic Tilt Disabled 32.91 Z4 Gnd. Angle 78 deg
32.55 kZN1 Res. Comp. 0.53 32.95 kZN4 Res. Comp. 0.53
32.56 kZN1 Res. Angle -5.6 deg 32.96 kZN4 Res. Angle -5.6 deg
32.59 R1 Gnd Resistive 18.7 Ohm 32.9C Z4 Sensit Ignd>3 50.00 mA
32.5B Z1 Sensit Ignd>1 50.00 mA
GROUP 1 PHASE DIFF
33.01 Phase Diff Enabled 33.0B Phase Time Delay 0 sms
20
33.06 Phase Is1 0.2 x In = 0.2 A 33.0E PIT Time 25.0 ms
33.07 Phase Is2 2.0 x In = 2 A 33.0F Ph CT Corr'tion 1 *as site needed
33.08 Phase k1 30.00 % 33.10 Compensation None
33.09 Phase k2 150.0 % 33.17 PIT I selection Remote

2/5 Daftar Setelan Rele Proteksi Dibuat : AMD Diperiksa : HIK Disetujui : AJI
Rev. 00 GI 150 KV GAJAH TUNGGAL Tgl : 21/01/21 Tgl: 22/01/21 Tgl: 22/01/21
Doc. No. UITJBB/01/04/2021/023
UNIT INDUK TRANSMISI JAWA BAGIAN BARAT
Cinere 16514 – Jakarta Selatan Valid. Januari 2021
DAFTAR SETELAN RELE PROTEKSI GI 150 KV GAJAH TUNGGAL

33.0A Phase Char DT


GROUP 1 BROKEN CONDUCTOR *alarm only
37.01 Broken Conductor Enabled 37.03 I2/I1 Time Delay 60.00 s
37.02 I2/I1 Setting 0.2
GROUP 1 SCHEME LOGIC
34.01 BASIC SCHEME 34.80 Trip On Close
34.08 Zone1 Tripping Phase And Ground 34.81 SOTF Status Enabled PoleDead
34.09 tZ1 Ph. Delay 0s 34.82 SOTF Delay 30.00 s
34.0A tZ1 Gnd. Delay 0s 34.83 SOTF Tripping 000011 (Z1 Z2)
34.10 Zone2 Tripping Phase And Ground 34.84 TOR Status Enabled
34.11 tZ2 Ph. Delay 0.4 s 34.85 TOR Tripping 000011 (Z1 Z2)
34.12 tZ2 Gnd. Delay 0.4 s 34.86 TOC Reset Delay 100.0 ms
34.18 Zone3 Tripping Phase And Ground 34.88 TOC Delay 200.0 ms
34.19 tZ3 Ph. Delay 1.6 s 34.B0 Z1 Extension
34.1A tZ3 Gnd. Delay 1.6 s 34.B1 Z1 Ext Scheme Disabled
34.28 Zone4 Tripping Phase And Ground 34.C0 Loss of Load
34.29 tZ4 Ph. Delay 0s 34.C1 LOL Scheme Disabled
34.2A tZ4 Gnd. Delay 0s
34.40 AIDED SCHEME 1
34.41 Aid. 1 Selection POR
34.43 Aid.1 Dist. Dly 0s
34.42 Aid 1 Distance Phase and Ground
34.4A Trev Guard 100 ms
34.60 AIDED SCHEME 2
34.61 Aid. 2 Selection Disabled
GROUP 1 POWER SWING BLK.
3D.01 PSB Status Blocking 3D.15 Zone 4 Gnd. PSB Blocking
3D.03 Zone 1 Ph. PSB Blocking 3D.20 PSB Unblocking Disabled
3D.05 Zone 2 Ph. PSB Blocking 3D.22 PSB Reset Delay 200.0 ms
3D.07 Zone 3 Ph. PSB Blocking 3D.23 OST Mode OST Disabled
3D.09 Zone P Ph. PSB Blocking 3D.24 Z5 3.64 Ohm
3D.0B Zone 4 Ph. PSB Blocking 3D.26 Z5' -3.64 Ohm
3D.0D Zone 1 Gnd. PSB Blocking 3D.28 R5 28.652 Ohm
3D.0F Zone 2 Gnd. PSB Blocking 3D.2A R5' -28.652 Ohm
3D.11 Zone 3 Gnd. PSB Blocking 3D.2C Blinder Angle 80.00 deg
3D.13 Zone P Gnd. PSB Blocking
GROUP 1 SUPERVISION
46.01 VTS Mode Measured + MCB 46.0E Inrush Detection Enabled
46.02 VTS Status Blocking 46.0F I>2nd Harmonic 20.00 %
46.03 VTS Reset Mode Auto 46.10 WEAK INFEED BLK
46.04 VTS Time Delay 5.000 s 46.11 WI Inhibit Disabled
46.05 VTS I> Inhibit 2.00 A 46.30 CT SUPERVISION
46.06 VTS I2> Inhibit 200.00 mA 46.31 CTS Mode Disabled
GROUP 1 SYSTEM CHECKS
48.14 VOLTAGE MONITORS 48.1D CS2 Status Disabled
48.15 Live Voltage 52.00 V 48.22 CS Undervoltage 52.00 V
48.16 Dead Voltage 11.50 V 48.23 CS Overvoltage 64.0 V

3/5 Daftar Setelan Rele Proteksi Dibuat : AMD Diperiksa : HIK Disetujui : AJI
Rev. 00 GI 150 KV GAJAH TUNGGAL Tgl : 21/01/21 Tgl: 22/01/21 Tgl: 22/01/21
Doc. No. UITJBB/01/04/2021/023
UNIT INDUK TRANSMISI JAWA BAGIAN BARAT
Cinere 16514 – Jakarta Selatan Valid. Januari 2021
DAFTAR SETELAN RELE PROTEKSI GI 150 KV GAJAH TUNGGAL

48.17 CHECK SYNC. 48.24 CS Diff Voltage 6.000 V


48.18 CS1 Status Enabled 48.25 CS Voltage Block V<
48.19 CS1 Phase Angle 15.00 deg 48.26 SYSTEM SPLIT
48.1A CS1 Slip Control Frequency 48.27 SS Status Disabled
48.1B CS1 Slip Freq 0.167 Hz
GROUP 1 AUTORECLOSE *AR Mode: 1/3P
49.05 Single Pole Shot 1 49.08 Dead Time 1 3.000 s *for TPAR
49.06 Three Pole Shot 1 49.0F Reclaim Time 40.00 s
49.07 1 Pole Dead Time 1.000 s *for SPAR 49.3A Dead Time Start Protection Op

Note:
Agar pihak kontraktor:
 Mendesain fungsi Z1 akan akitf saat terjadi kegagalan komunikasi/line diff blocked.
 Menyiapkan slot signal (digital/virtual input) pada rekaman relay, antara lain:
Status CB R-S-T, Fault Phase R, Fault Phase S, Fault Phase T, Trip R, Trip S, Trip T, Z1 Start, Z2 Start, Z3 Start, SOTF
Trip, Initiate AR, Sending, Receive, PowerSwing Detected, dan CT/VT Fail
 Mendesign oscillography merekam saat terjadi gangguan internal, eksternal, opening/closing PMT, dan
blackout.
 Mengkonfigurasi fungsi CT Failure dan CCT-Fail sebagai fungsi ALARM
 Mengkonfigurasi fungsi dan binary input-output Auto Reclose Internal

Logic yang diterapkan :

4/5 Daftar Setelan Rele Proteksi Dibuat : AMD Diperiksa : HIK Disetujui : AJI
Rev. 00 GI 150 KV GAJAH TUNGGAL Tgl : 21/01/21 Tgl: 22/01/21 Tgl: 22/01/21
Doc. No. UITJBB/01/04/2021/023
UNIT INDUK TRANSMISI JAWA BAGIAN BARAT
Cinere 16514 – Jakarta Selatan Valid. Januari 2021
DAFTAR SETELAN RELE PROTEKSI GI 150 KV GAJAH TUNGGAL

2. Proteksi Cadangan: Penghantar 150 kV arah Pasar Kemis 1


Jenis relai : Over Current Relay
Merek/Tipe relai : ABB REF 615
Arus Nominal : 1A
LOKASI : GI Gajah Tunggal
PROTEKSI : Line Pasar Kemis 150 kV 1
Penghantar : CAB-150kV-XLPE PRSYMIAN-2x1000mm + OHL-150kV-ACSR AS 2x450mm + OHL-
150kV-ZEBRA AS 2x484.5mm
CCC : 1513 A +1856 A + 1620 A
CT : 2000 / 1 Ampere
PT : 150 kV / 100 Volt

Current and Time Setting


PARAMETER OCR ITEM APPROVE
1 150kV CT Ratio : CT Ratio 2000/1
2 Start current of stage I> as a multiple of the : I>/In 0.91
energizing input used
3 Curve Type : Curve IDMT (Inverse definite minimum time)
Normal Inverse
4 Time multiplier setting of stage I> : k 0.38
5 Overcurrent stage 2 : I>> Not used
PARAMETER GFR ITEM APPROVE
1 Start current of stage Io> as a multiple of : Io>/In 0.15
the energizing input used
2 Curve Type : Curve IDMT (Inverse definite minimum time)
Normal Inverse
3 Time multiplier setting of stage Io> : ko 0.65
4 Earthfault stage 2 : Io>> Not used

5/5 Daftar Setelan Rele Proteksi Dibuat : AMD Diperiksa : HIK Disetujui : AJI
Rev. 00 GI 150 KV GAJAH TUNGGAL Tgl : 21/01/21 Tgl: 22/01/21 Tgl: 22/01/21