Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

GMC-ElecEng 2020

Floating PV Solar-Powered Systems: design applied to an


irrigators community in the Valencia Region – Spain
Carlos Vargas-Salgado Irene Mansó Borràs Manuel Alcazar-Ortega Lina Montuori
Departamento de Universitat Politènica de Departamento de Departamento de
Ingeniería Eléctrica València Ingeniería Eléctrica Termodinámica Aplicada
Universitat Politènica de Valencia, Spain Universitat Politènica de Universitat Politècnica de
València irmanbor@etsii.upv.es València València
Valencia, Spain Valencia, Spain Valencia, Spain
carvarsa@upvnet.upv.es malcazar@iie.upv.es lmontuori@upvnet.upv.es

Abstract Introduction

In the present paper, it is carried out the design The floating PV (FPV) is a technology which
of a photovoltaic installation connected to the has been spreading, mainly from 2015, from
utility grid with panels mounted on a floating them which the growth has been almost
structure at an irrigator’s community. The exponential. The main countries with this type
objective is to determine the technical and of facilities are mainly Asian in origins, such as
economic feasibility of a floating photovoltaic China, Japan, Taiwan and South Korea,
installation to partially or totally cover the investment in the United States, France and the
energy demand. Netherlands is also growing. This technology
has increased in the renewable energy market
The floating photovoltaic technology modality since 2016. In December 2018, it reached 1.3
provides better production yields in GW of installed power. [1] [2]
photovoltaic panels since they are kept in
natural refrigeration and at lower temperatures Floating PV plant provides benefits such as a)
than if they were mounted on a roof. Its use for water helps to keep panels at low temperatures,
irrigation facilities is attractive if an irrigator b) the problem of shading is not present in the
pool nearby is available. However, the cost of case of an FPV plant, c) there is a reduction in
installing floating structures is considerably the growth of algae on water, d) no fixed
higher compared to a similar photovoltaic structure is presented in the case of an FPV
installation on a roof. For the design of the plant (installation can be reversible) [1] e)
proposed system, 272 PV panels with a 108 kW evaporation of water is reduced by 80 % as it is
peak installed and a 100 kW inverter are used. covered by floating platforms [3].
The electrical calculations are also carried out
to size all the installation wiring and Several papers assess Floating PV system [4]
incorporate the corresponding protections to [5] [6]. The installation of large-scale PV
guarantee a safe operation. The total cost of the systems has substantial requirements on land
photovoltaic installation is 119,100 €. The usage; approximately 1.6 ha of land per each
photovoltaic generation is 188 MWh/year, MW installed [7]. Also since land resources are
covering 13.6% of the energy demand. scarce their acquisition cost is higher,
impacting the economic viability of projects
Keywords negatively. In this context, FPV emerges as a
solution to mitigate the challenges due to lack
Photovoltaic system, floating, renewable of space, as it will use idle areas, avoiding
energy, self-consumption, compensation. conflicts, for example, with agricultural use [8].

88
Authorized licensed use limited to: ULAKBIM UASL - Osmangazi Universitesi. Downloaded on March 19,2021 at 21:00:53 UTC from IEEE Xplore. Restrictions apply.
GMC-ElecEng 2020

In this paper, Homer and SAM are used to vegetables. At its head station is the pumping
estimate the energy production and to carry out system that distributes the water resource to the
economic analysis. However other tools can be required areas. The water is stored in a reservoir
used. Recent studies show models and methods of 16,640 m3 and it is derived to the fields
for PV systems in which are evidenced more through 3 pumps in parallel, whose operation is
accurate results for simulation models; by governed by a control system that guarantees
the necessary irrigation in all sectors.
considering environmental weather conditions,
PV system architecture, interactions of PV
components with the weather conditions, Irrigation Shifts
manufacturing quality, materials used and
combinations with other sources such a wind
systems. [9] [10] [11] The irrigation is divided into two blocks. The
main and largest one serves to citrus fields
In this paper, the results of the design of an FPV primarily, and the other one to the block of
system are presented. The structure of the vegetable fields. The citrus field block is
manuscript is composed of the methodology, divided into four sub-groups, alternating
energy demand, solar resource, devices used, depending on the schedule. Hence, the system
calculations, scheme of the system and results. is configured in such a way that each field is
irrigated 2 hours per day. On a regular day of
watering, the pumping station is continuously
I. Methodology working for 8 hours. The secondary block is
supplied during 3-4 hours in the afternoon.
The methodology followed to design the PV
system is based on Figure 1. PV system is sized, III. Energy demand
considering the energy demand, the losses due
to energy conversion and the available solar
resource. Then, the inverter is sized, obtaining, The energy demand of the system responds to
therefore, the final design of the system. the irrigation schedule mentioned before. The
frequency of these irrigations depends on the
Losses due to energy season of the year. During summer months it is
conversion and other losses  usually to water six days a week; meanwhile, in
winter the tendency is between 2-3 days a week.
Energy PV Inverter Final The electricity rate contracted with the marketer
demand system sizing design company is the 6.1A (high voltage, six periods).
sizing
250
200
Equivalent sun hours (ESH),
Orientation and Tilt 150
kW

100
50
Figure 1: Methodology to carry out the design.
0
1 3 5 7 9 11 13 15 17 19 21 23
II. Description of the installation TIME
Figure 2: Daily average profile consumption.
The Cooperative of Irrigators, located in the
Valencia Region, supplies 717 hectares of The conditions of this type of rate are
fields dedicated to the cultivation of citrus and determined by the Spanish regulation (Royal

89
Authorized licensed use limited to: ULAKBIM UASL - Osmangazi Universitesi. Downloaded on March 19,2021 at 21:00:53 UTC from IEEE Xplore. Restrictions apply.
GMC-ElecEng 2020

Decree 1164/2001), which establishes tariffs IV. Solar resource


for access to transmission and distribution grid.
Figure 2 shows the average daily profile for Using the PVGIS database, hourly irradiance
August 2019. The consumption that will serve could be obtained for the location of the
as the basis for the present paper is showed in installation. In Figure 4 is shown the daily
Table I. irradiance expected in the location of the
facility, with panel inclination of 5º. [12]
TABLE I. MONTHLY ENERGY CONSUMPTION
Energy consumption MWh As it is shown in Figure 3, consumption is
January 16.70 higher during summer months reaching on
February 18.68
March 26.48 average 200 kW at dawn and early in the
April 22.28 morning. Irradiance values are also higher in
May 38.83
June 51.42
this season as show Figure 4, favouring the
July 60.73 energy production in summer.
August 61.78
September 31.36
October 37.26
November 31.71
December 13.81

New profile consumption


The system was designed to cover afternoon
consumption (Fig. 2). To take more profit of FV
production, the irrigation schedule that was
held during the afternoon will be switched
earlier, during daily hours when irradiation is
higher.
Figure 4: Monthly average solar irradiance.
Figure 3 shows the average daily consumption
of the system distinguishing in winter and
summer, with the afternoon consumption V. Devices
switched to earlier hours.
Floating system

The floating system chosen is composed of a


floating structure with a fixed inclination angle
of 5º. These floats are modular, and each one
holds a panel. The maintenance platforms are
strategically placed with corridors of
maintenance. Floats are made of HDPE (High-
Density Polyethylene) and can hold PV panels
with the following range of dimensions: 1650-
2120 mm length, 980-1060 mm width. [13]
Figure 3. Average daily consumption.

90
Authorized licensed use limited to: ULAKBIM UASL - Osmangazi Universitesi. Downloaded on March 19,2021 at 21:00:53 UTC from IEEE Xplore. Restrictions apply.
GMC-ElecEng 2020

PV panels VI. Calculations


The chosen photovoltaic panel is the model Number of panels
AURORA SPLIT CELL – Monocrystalline
PERC SR-M672400HL [14]. This type of panel The rated power of the PV system is 100 kW.
uses the Half-Cut Cell technology, which To cover the required power, using 400 W
consists of using photovoltaic cells shorter than photovoltaic panels, 250 panels are required
conventional, connected internally in two series according to equation 1.
of strings. This allows to reduce the losses in
the case of shadows, and the production of the 𝑁 (1)
panel is not cancelled. The technical
characteristics of the panel are shown in Table
The number of estimated PV panels is the first
III.
iteration. It must be verified and recalculated.
TABLE III: CHARACTERISTICS OF THE PANEL The final number of panels depends on the
inverter technical characteristics, losses due to
MODEL SR-M672400HL
Peak power (Ppeak) 400 W temperature and its efficiency.
Open circuit voltage (Voc) 49.89 V
Short circuit current (Isc) 10.27 A To achieve the proper size of the PV system, the
Max. power point volt. (Vmpp) 41.73V
Max. power point current (Impp) 9.59A principal values of the panels (Voc, Isc, Pmax)
Efficiency 19.89% must be recalculated, considering the
Dimension (mm) 2008 x 1002 x 40
Weight 22.4 kg temperature factor.
Coeff. of temp Pmax (%) ºC -0.387 %
Coeff. of temp Voc (%) ºC -0.282 % The minimum and maximum temperature of
Coeff. of temp Isc (%) ºC +0.041 %
NOCT 45±2 ºC the panel are calculated according to equation
(2) and (3).
Grid-tied inverter ,
𝑇𝑐𝑒𝑙𝑙 𝑇𝑎𝑚𝑏 𝐺 (2)
The chosen inverter is the INGECON SUN ,
100TL [15]. In Table IV are gathered the main 𝑇𝑐𝑒𝑙𝑙 𝑇𝑎𝑚𝑏 𝐺 (3)
specifications of the inverter.
Now it is possible to calculate Voc, Isc and Pmax
considering the temperature effect.
TABLE IV: CHARACTERISTICS OF THE INVERTER
MODEL INGECON SUN 100TL
The open-circuit voltage (Voc), the short circuit
Rated power DC 101.2 – 145 kW current (Isc) and the peak power are estimated
Imax 240 A
Isc 185 A
according to equation (4), (5) and (6),
Vmax DC 1100 V
Voltage Range MPPT 570 - 850 V 𝑉 𝑉 _ ∙ 1 𝛽𝑉 ∙ 𝑇 _ –𝑇 (4)
Efficiency 98.9 %
Nº of MPPT 1 𝐼 𝐼 ∙ 1 𝛽𝐼 ∙ 𝑇 –𝑇 (5)
Rated power AC 100 kW _ _
Output 50/60 Hz, 400Vac
𝑃 𝑃 ∙ 1 𝛽𝑃 ∙ 𝑇 _ –𝑇 (6)

Finally, the values calculated by correcting the


temperature effect are shown in Table V.

91
Authorized licensed use limited to: ULAKBIM UASL - Osmangazi Universitesi. Downloaded on March 19,2021 at 21:00:53 UTC from IEEE Xplore. Restrictions apply.
GMC-ElecEng 2020

TABLE V: CORRECTED VALUES OF THE PANELS VII. Scheme of the PV system


VOC_max 48.18 V
Isc_max 10.48 A Figure 5 shows the distribution of the floating
PMPP_max 381.04 W system in the irrigation pool and Figure 6 shows
the scheme of the integration of the PV system
into the cooperative internal grid.
PV panels configuration
For a proper array design, it is necessary to
consider the technical specifications of the
inverter and the PV panels. The configuration
of the panels must guarantee the correct ranges
of inverter working. Considering the technical
characteristics of the inverter (Table IV), and
the values calculated in Table V, it is possible
to calculate the configuration of the PV system,
determining the number of panels in series per
string and the number of strings in parallel.

Considering the voltages (Voc and Vmpp), the


maximum quantity of PV panels is estimated,
choosing the maximum value obtained from
equations (7) and (8).
Figure 5. FPV panels distribution on the irrigation
_ pool.
𝑁 _ _ (7)
_
_
𝑁 _ _ (8)
_

Analogously, considering the currents (Isc and


Impp) of the panel, the maximum number of
strings per inverter is estimated choosing the
maximum value obtained from equations (9)
and (10)
_ _
𝑁 _ _ (9)
_
_ _
𝑁 _ _ (10)
_

Finally, according to calculations and arranging


the strings with the same number of panels, the
final configuration is shown in Table VI.

TABLE VI: FINAL PV SYSTEM CONFIGURATION


Panels per string 17
Strings 16
Number of panels 272
Figure 6: Integration of the PV system into the
cooperative grid.

92
Authorized licensed use limited to: ULAKBIM UASL - Osmangazi Universitesi. Downloaded on March 19,2021 at 21:00:53 UTC from IEEE Xplore. Restrictions apply.
GMC-ElecEng 2020

VIII. Results Figure 9 shows the average daily consumption


covered by the floating photovoltaic system
Through the software HOMER, it is concluded designed.
that the best option is a peak power installed of
108 kW (Fig. 7). The photovoltaic field has 272
panels installed and a 100 kW grid-tied inverter.
NPC refers to the Net Present Cost and COE to
the Cost of Energy.

Figure 9: Average daily consumption covered


by the floating photovoltaic system designed.
Figure 7: Results using the software Homer. [16]
The comparison of the energy consumption
from the utility grid (with and without the PV
PV production system) is shown in Table VII. The floating PV
system would cover around 13.55% of the total
The system was finally designed to cover the energy demand.
afternoon consumption, which will now take
place during the time of photovoltaic TABLE VII: UTILITY GRID CONSUMPTION
COMPARISON WITH AND WITHOUT THE PV SYSTEMS
production. Figure 8 shows the estimated
monthly energy production in the floating Without (kWh) With PV (kWh) % Saving
photovoltaic system designed, using the Jan 16,706 14,107 15.56%
software SAM (System Advisor Model). Feb 18,669 15,310 17.99%
Mar 26,472 22,262 15.90%
Apr 22,273 18,288 17.89%
May 38,821 33,097 14.74%
Jun 51,307 45,881 10.58%
Jul 60,360 55,219 8.52%
Aug 61,762 54,194 12.25%
Sep 31,342 25,414 18.91%
Oct 37,465 32,457 13.37%
Nov 31,374 27,814 11.35%
Des 14,440 11,239 22.17%
Anual 410,990 355,283 13.55%

Financial and viability results


The cost of the components is 72,757 € (Fig.
10), and the total cost of the system, including
labour cost, contractual benefits, and VAT is
119,100 €.
Figure 8: Monthly FPV production.

93
Authorized licensed use limited to: ULAKBIM UASL - Osmangazi Universitesi. Downloaded on March 19,2021 at 21:00:53 UTC from IEEE Xplore. Restrictions apply.
GMC-ElecEng 2020

The payback period is 15 years (Equation 12).


The total profit at the end of the life of the
installation would be 71,328 €.


𝑃𝑎𝑦𝑏𝑎𝑐𝑘 € (12)

IX. Conclusions

According to the initial aim of the feasibility


study of the photovoltaic installation with
floating panels, it has been determined that it is
Figure 10: Cost of the components. technically viable to install a photovoltaic plant
on the irrigation pool at the Cooperative under
The economic savings would be possible thanks study. It is concluded that the final design of the
to the reduction of energy consumption from
photovoltaic system has 272 panels (108 kW),
the utility grid. But also due to the savings that
would be generated thanks to the regulation and one inverter of 100 kW.
established in the RD 244/2019. This regulation Regarding the economic profitability, the
forces the marketer company to compensate payback period is 15 years, generating a profit
economically the custom, due to the excess of of 71,327 € at year 25. This payback is not on
energy injected to the utility grid.
the average for PV systems in Spain, as it is
usually expected to obtain a return at 7-10
In this project, the annual saving would be
around 7,800 €. It is also considered a yearly years. However, the extra cost due to the
saving of 353 € due to the savings by avoiding floating structure has increased the final budget.
80% of the evaporation of the water surface Following the aim of energy saving, there is a
covered by the floating structure [3].
reduction of the grid consumption of 55,707
Additionally, according to the Valencian
kWh/year, equivalent to 13.55% of the total
regulation (DOGV 25/5/2020), a bonus of
8,573 € will be obtained at year 10. The annual consumption. The saving could be improved if
maintenance cost has been estimated in 1,200 €. the demand were redistributed to the
The replacement of the inverter between the 15- photovoltaic production times by increasing
20 years is also considered. this energy-saving consumed from the utility
grid.
The annual inflation is estimated at 1%. It is
obtained an Internal Rate of Return of 4%
annually for 25 years from equation (Equation
11), where NPC is the Net Present Cost and C0
is the initial cost of the FPV system.  

𝑁𝑃𝐶 𝐶 ∑ 0 (11)

94
Authorized licensed use limited to: ULAKBIM UASL - Osmangazi Universitesi. Downloaded on March 19,2021 at 21:00:53 UTC from IEEE Xplore. Restrictions apply.
GMC-ElecEng 2020

Bibliography [11] F. Mohamad, J. The and H. Abunima, "Multi


Objective Optimization of Solar/Wind Penetration
in Power Generation Systems," IEEE Access, 2019.
[1] S. S. Gurfude and P. Kulkarni, "Energy Yield of
Tracking Type Floating Solar PV Plant," in Plant," [12] E. Commission, "PHOTOVOLTAIC
2019 National Power Electronics Conference GEOGRAPHICAL INFORMATION SYSTEM
(NPEC), 2019. PVGIS," [Online]. Available
https://re.jrc.ec.europa.eu/pvg_tools/en/tools.html#
[2] "Ecoinventos," 26 June 2019. [Online]. Available: PVP. [Accessed 5 July 2020].
https://ecoinventos.com/fotovoltaica-flotante/.
[Accessed 12 July 2020]. [13] Isifloating, [Online]. Available
https://www.isifloating.com/mediateca/. [Accessed
[3] M. M. Hassan and W. L. Peyrson, "Evaporation 25 June 2020].
mitigation by floating modular devices," in 7th
International Symposium on Gas Transfer at Water [14] TECHNOSUN, [Online]. Available
Surfaces, Washington, USA, 2016. https://b2b.technosun.com/pt_PT/shop/product/sol0
226-panel-solar-400w-monocristalino-perc-sr-
[4] P. Elia Campana, L. Wästhage, W. Nookuea, Y. m672400hl-2008x1002x40mm-aurora-red-solar-
Tan and J. Yan, "Optimization and assessment of 14472. [Accessed 25 JUNE 2020].
floating and floating-tracking PV systems," Solar
Energy, vol. 177, pp. 782-795, 2019. [15] INGETEAM, [Online]. Available
https://www.ingeteam.com/es-es/sectores/energia-
[5] S. Oliveira-Pinto and J. Stokkermans, "Assessment fotovoltaica/p15_24_624_450/ingecon-sun-
of the potential of different floating solar 100tl.aspx. [Accessed 8 June 2020].
technologies - Overview and analysis of different
case studies," Energy Conversion and [16] HOMER ENERGY, “Hybrid Optimization o
Management, vol. 211, 2020. Multiple Energy Resources,” 2012.

[6] A. Sahu, N. Yada and K. Sudhakar, "Floating


photovoltaicpowerplant:Areview,"
RenewableandSustainableEnergyReviews, vol. 66,
pp. 815-824, 2016.

[7] E. Kabir, P. Kumar, S. Kumar, A. Adelodun and K.-


H. Kim, "Solar energy: potential and future
prospects," Renewable and Sustainable Energy
Reviews, vol. 82, pp. 894-900, 2018.

[8] H. Liu, V. Krishna, J. Lun Leung, T. Reindl and L.


Zhao, "Field experience and performance analysis
of floating PV technologies in the tropics,"
Progress in Photovoltaics Research and
Applications, vol. 26, pp. 957-967, 2018.

[9] H. Abunima and J. Teh, "Reliability Modeling of


PV Systems Based on Time-Varying Failure
Rates," IEEE Access, vol. 8, pp. 14367-14376,
2020.

[10] H. Abunima, J. Teh and H. Jabir, "A new solar


radiation model for a power system reliability
study," IEEE Access, p. 1, 2019.

95
Authorized licensed use limited to: ULAKBIM UASL - Osmangazi Universitesi. Downloaded on March 19,2021 at 21:00:53 UTC from IEEE Xplore. Restrictions apply.

You might also like