Subject Daily Report

FSE Name Paul Willoughby


Machine Type GT Frm 5001 –
Unit Customer Tag MT001C / GE NP# G06744

Date 03/11/2018

Work Permit (WP) WP Issuing WP Expiring


# 17131 Work order NO
03-11-2018 - Time: 07.00am 04-11-2018 - Time: 18.30
3664913 GT C

1)
EHS Concerns:
2)

Shutdown Progress :
Actual : 12% Vs Expected : 12%

ONGOING ACTIVITIES:

1. Permits received 07.30am


2. Remove coupling guards and spools piece on gear-box & load gear-box for rotor alignment
checks to be carried out ON GOING
3. Open inlet plenum door for Six-point check to commence on R.O
4. Cleaning all parts for rebuild

Areas of Concern:

Not enough Technicians to support the outage.


Please provide 3 additional Experienced Mech Technicians.
No one turned up today

Recommendations:

Shortages (materials & tools):

Tooling is a big issue here waiting for tools and getting them.

1
Stopped the work 16.00PM on removing coupling spool piece Turbine end and Gear –box end as no tools

Completed work

Aux Compartment scaffolding removed


Load gear –box Turbine Shaft removed

Look Ahead:

Unbolt gas turbine compartment Ventilation ducts


Remove instrumentation wiring and conduit in turbine Compartment and on roof
Remove Roof
Remove Combustion instrumentation Spark plugs flame Scanners 
Remove turbine compartment piping cooling & sealing and gas piping
Please prepare all new parts for combustion inspection

Manpower resources #
BHGE FSE Paul Willoughby & Lamberto D’Intino
Foreman
Mechanical Fitter
Mechanical helper 3
E&I helper
E&I