Subject Daily Report: Work Permit (WP)
Subject Daily Report: Work Permit (WP)
Date 03/11/2018
1)
EHS Concerns:
2)
Shutdown Progress :
Actual : 12% Vs Expected : 12%
ONGOING ACTIVITIES:
Areas of Concern:
Recommendations:
Tooling is a big issue here waiting for tools and getting them.
1
Stopped the work 16.00PM on removing coupling spool piece Turbine end and Gear –box end as no tools
Completed work
Look Ahead:
Manpower resources #
BHGE FSE Paul Willoughby & Lamberto D’Intino
Foreman
Mechanical Fitter
Mechanical helper 3
E&I helper
E&I
Rigger
…………..