Professional Documents
Culture Documents
Session 5 Dealing With Risk and Uncertainties
Session 5 Dealing With Risk and Uncertainties
Risk neutral
Risk seeker
0 NPV
Example Dealing with Uncertainty
Table 7.18 Sensitivity Results: Change in NPV and EIRR, Switching Values
NPV Switching Assumed
Change ($ million) EIRR (%) Value Value
Base case 66.96 17.3
Capital cost 54% 100%
10% 54.58 16.0
20% 42.20 14.9
Fuel 29% 100%
-20% 47.86 15.8
-10% 57.39 16.6
10% 76.56 17.9
20% 86.19 18.6
Income growth 1.027 1.06
1.02 -9.84 10.90
1.10 217.90 23.8
Price elasticlty 0.6326 -0.5
-0.90 109.31 20.1
-0.10 36.37 15.0
Adjusted half 57.72 16.6
VOC savings
EIRR = economic internal rate of return, NPV = net present value.
Source: ADB (2007).
Table 7.19 Risk Analysis: Parameter Variation Figure 7.3 Risk Analysis: Probability Distribution of NPV
Parameter Range (Base Case) NPV NPV
GDP growth, annual 2% to 10% (6%) -25 242 -25 242
5.0% 5.0%
Price elasticity −0.9 to −0.1 (−0.5) 0.006 1.0
The resulting expected value, that is, the probability weighted NPV is 0.000 0.0
• The key result is the probability of project failure,
-200
0
200
400
600
800
1000
1200
1400
1600
-200
0
200
400
600
800
1000
1200
1400
1600
$83.2 million, approximately 24% higher than the base case (Figure 7.3).
defined
The key bythea probability
result is negative of NPV. This
project probability
failure, defined byisa negative
NPV NPV
about 10%
Minimum -95.4331
While
•Figure there is no unique cut-off rate for
7.3 Risk Analysis: Probability Distribution of NPV Maximum
Mean
1,564.9006
83.1918
acceptable
-25 242
risk
NPV levels (although 25% isNPV
-25 242
sometimes Std Dev
Values
86.7300
10,000
used as a rule
0.006
5.0%of thumb), the project appears
1.0
5.0% to NPV = net present value, Std Dev = Standard deviation.
be low risk.
0.005 0.8
Source: ADB (2007).
0.004
0.6
0.003
0.4
0.002
0.001 0.2
0.000 0.0
-200
0
200
400
600
800
1000
1200
1400
1600
-200
0
200
400
600
800
1000
1200
1400
1600
NPV NPV
Techniques in Handling Risk and Uncertainty
3. Raising the discount rate
• Another method for allowing for risk is by ‘loading’ or raising the discount rate
• The strategy of loading the discount rate is often used to counter a systematic over-
optimism in net benefit forecasts, especially when late-occurring benefits may be too
high
• The method fails if it is late-occurring costs that are the source of the uncertainty
(produce adverse effect), therefore reduce the discount rate is more appropriate.
• A risk loading is appropriate where there is a constant (exponentially increasing)
probability of a project failing
• Loading the discount rate is not recommended as a general practice for publicly
funded projects.
However, such circumstances are rare. Generally, a project is more likely to fail during its
set-up period or at the end of its life – for example, as capital equipment becomes obsolete.
Accordingly, loading the discount rate is not recommended as a general practice for publicly
funded projects.