Professional Documents
Culture Documents
Session 4 Present Value and Decision Rule
Session 4 Present Value and Decision Rule
represented in equation (3). Substituting equations (6) and (7) into equation (3) gives
the following useful expression:
NPV = a a
n Bt n Ct
t
- (8)
t=0 (1 + i) t=0 (1 + i)t
Benefits 85,558
($) 76,290
81,630
87,344
93,458
PV (B ) = 424,280 20,000
100,000 100,000 100,000 100,000 100,000
Time
0 1 2 3 4 5 (years)
FIGURE 4 Time Line of the Benefits and Costs of the Library Information
System
Decision Rule Involving Present Value
• Benefit Cost Ratio (BCR): a ratio between PVB over PVC
𝐵!
∑$!"#
𝐵! = (1 + 𝑟)! 𝑃𝑉𝐵
𝐶 =
$ 𝐶! 𝑃𝑉𝐶
∑!"# !
(1 + 𝑟)
• Decision rule:
• If %⁄& > 1, then GO
• If %⁄& ≤ 1, then NO GO
• Pro:
• Another way to say that benefits are larger than costs
• Cons:
• BCR are in percentage value, they should not be used to select one project from a group of
projects that differ in size
Sensitivity Analysis in Discounting
• Previous section assumes that interest/discount rate is known when
we are calculating the PVB and PVC
• Because the discount rate and the horizon value often determine the
sign of the NPV, therefore analysts frequently conduct sensitivity
analyses with respect to these two parameters (r and NPV).
• Internal Rate of Return (IRR) is the discount rate at which the NPV is
zero
Internal Rate of Return as Decision Rule
• The IRR may be used for selecting projects when there is only one alternative to
the status quo.
• The decision rule:
• If 𝐼𝑅𝑅 > 𝑆𝐷𝑅 𝑜𝑟 𝑂𝐶𝐶, then GO
• If 𝐼𝑅𝑅 < 𝑆𝐷𝑅 𝑜𝑟 𝑂𝐶𝐶, then NO GO
• Pro:
• if IRR is unique, it conveys useful information to decision makers who want to know how
sensitive the results are to the discount rate.
• Cons:
• IRR may not be unique, there may be more than one discount rate at which the NPV is zero
(when annual net benefit change more than once from positive to negative)
• IRRs are in percentage value, they should not be used to select one project from a group of
projects that differ in size
Discounting and dynamic efficiency
• Assume three time periods: now, 40 years and 100 years
• Path A produces flow of NB: $500 billion, $1000 billion, $100 billion
• Path C produces flow of NB: $500 billion, $800 billion, $1000 billion
• Discount rate = 3%
• PV = Vt / (1+r)t