Professional Documents
Culture Documents
Pom Module 3
Pom Module 3
Pom Module 3
Functions
The functions of production
The intermediate objectives are: department are grouped into two:
Machinery and Equipments The activity which convert the
Materials available capital into physical
Manpower resource required for
Supporting Service production
The activities which convert the
physical resources to saleable
goods
Characteristics
Advantages
High variety of products and low volume
Use of general purpose machines and Variety of products can be
facilities produced
Highly skilled operators due to uniqueness Operator becomes skilled and
in job competent that each job gives
Process type layout for arrangement of
them learning opportunity
facilities
Movement of material is long and Utilization of full potential of
interrupted operator
Relative imbalance in workloads at various Opportunity to use innovative
departments
ideas and creative methods
Advantages Disadvantages
Better utilization of plant and Material handling is complex because
of longer and irregular flows
machinery
Production planning and control is
Promote functional specialization complex
Cost per unit is lower Work in progress inventory is higher
compared to continuous production
Lower investment in plant and
Longer production times
machinery
Higher setup cost due to frequent
Flexibility to accommodate and changes in setup.
process number of products
Characteristics
Mass Production
Standardization of product and process
sequence and hence line layout is
Manufacturing of discrete parts or
recommended
assemblies using a continuous
Dedicated, special purpose machines
process are called mass production
having higher production capabilities
or repetitive production. and output rates
Products are standardized Larger volumes of production
Large volume can be produced Shorter cycle time of production
Lower in process inventory
Perfectly balanced production lines
Advantages
Higher rate of production with reduced cycle time Process Industry
Higher capability balancing due to line balancing
Less skilled operators can make the process
Low in process inventory
It is the production process that includes
Production cost per unit is less mixing, separating and or performing chemical
reaction.
Disadvantages It is usually carried out in continuous mode
Break down of one machine will stop entire
production line It usually produces non discrete products in
Line layout needs adjustments with the changes in large volume
product design
High investment in production facilities
Supervision is general rather than specific
The cycle time is determined by the slowest
operation
Importance of PERT/CPM
By using PERT and CPM analysis you will be able to answer questions such as:
1. When will the entire project be completed? NETWORK TECHNIQUES
2. What are the critical activities or tasks in the project, that is, the
ones that will delay the entire project if they are late? PERT CPM
3. Which are the noncritical activities, that is, the ones that can run
-Program Evaluation and Critical Path Method
late without delaying the whole completion time? Review Technique Developed by El Dupont
4. What is the probability that the project will be completed by a - developed by the US for Chemical Plant
specific date? Navy with Booz Shutdown Project- about
Hamilton Lockheed same time as PERT
5. At any particular date, is the project on schedule, behind schedule, - on the Polaris
or a head of the schedule? Missile/Submarine
6. On any given date, is the money spent equal to, less than, or greater program 1958
than the budgeted amount?
7. Are there enough resources available to finish the project on time? Both use same calculations, almost similar
Main difference is probabilistic and deterministic in time estimation
8. If the project is to be finished in a shorter amount of time, what is Gantt Chart also used in scheduling
the best way to accomplish this at the least cost? (crash analysis) 70
71
72
Example of Network DEFINITION OF TERMS IN A NETWORK
More Complex Activity : any portions of project (tasks) which required
by project, uses up resource and consumes
time may involve labor, paper work,
contractual negotiations, machinery operations
Activity on Arrow (AOA) showed as arrow, AON
Activity on Node
Event : beginning or ending points of one or more
activities, instantaneous point in time, also
PRECEEDING SUCCESSOR
ACTIVITY
EVENT
74
73
PERT/CPM
Emphasis on Logic in Network Construction
Two conventions
Construction of network should be based on logical or technical
nodes for events and arcs for activities (our convention) dependencies among activities
Example -
WRONG !!!
CORRECT
75
76
79 80
Activity Immediate
Activity Immediate predecessors
predecessors A -
A -
B -
B -
C B
C B
D A, C
D A, C
E C
E C
F C
F C
81 G D,E,F 82
G D,E,F
WRONG
RIGHT
!!!
RIGHT
83 84
Network with LS & LF time
Latest start & latest finish time
D[5,8] 5
2 3[7,10]
To find the critical path we need a backward pass
calculation.
7
4
Starting at the completion point (node 7) and using a latest 1 6
finish time (LF) of 26 for activity I, we trace back through
the network computing a latest start (LS) and latest finish
time for each activity
3
IMPORTANT QUESTIONS
Importance of Float (Slack) and Critical Path
What is the total time to complete the project?
1. Slack or Float shows how much allowance each activity has,
26 weeks if the individual activities are completed on schedule.
i.e how long it can be delayed without affecting completion
date of project
What are the scheduled start and completion times for each activity?
ES, EF, LS, LF are given for each activity.
2. Critical path is a sequence of activities from start to finish
with zero slack. Critical activities are activities on the
What activities are critical and must be completed as scheduled in order to critical path.
keep the project on time?
Critical path activities: A, E, F, G, and I.
3. Critical path identifies the minimum time to complete
project
How long can non-critical activities be delayed before they cause a delay in
Slack time available for all activities are given. 4. If any activity on the critical path is shortened or extended,
project time will be shortened or extended accordingly
95 96
Importance of Float (Slack) and Critical Path PERT For Dealing With Uncertainty
5. So, a lot of effort should be put in trying to control So far, times can be estimated with relative certainty,
activities along this path, so that project can meet due date. confidence
If any activity is lengthened, be aware that project will not
For many situations this is not possible, e.g Research,
meet deadline and some action needs to be taken.
development, new products and projects etc.
8. If resources can be saved by lengthening some activities, do Expected Value (te) = (to+4tm +tp) /6
so for non-critical activities, up to limit of float. Variance (V) = ( (tp-to)/ 6 ) 2
Std Deviation (S) = SQRT (V) ie (tp-to)/ 6
9. Total Float belongs to the path 97 98
99 100
a - 10 22 22 20 4 2
b - 20 20 20 20 0 0
c - 4 10 16 10 4 2
d a 2 14 32 15 25 5
e b,c 8 8 20 10 4 2
f b,c 8 14 20 14 4 2
g b,c 4 4 4 4 0 0
h c 2 12 16 11 5.4 2.32
I g,h 6 16 38 18 28.4 5.33
j d,e 2 8 14 8 4 2
101 102
Figure 8-13 The complete Network
The complete network
EF=20 35
d d
2 6 2 6
(15,25) a (15,25) j
j (20,4) (8,4)
(8,4) b e
a 20 43
(20,0) (10,4)
(20,4) e CRIT. TIME = 43
f 7
(10,4)
1 3
(14,4)
1 f 7
3 g
b (14,4)
c (4,0)
(20,0) i
(10,4)
g (18,28.4)
c h
(4,0) 4 5
(10,4) i (11,5.4)
(18,28.4) 10 24
h 5
4
(11,5.4)
103 104
Critical Path Analysis (PERT) Assume, PM promised to complete the project in the fifty days.
What are the chances of meeting that deadline?
Activity LS ES Slacks Critical ? Calculate Z, where
a 0 0 0 Yes
Z = (D-S) / V
b 1 0 1
Example,
c 4 0 4 D = 50; S(Scheduled date) = 20+15+8 =43; V = (4+25+4) =33
Z = (50 43) / 5.745
d 20 20 0 Yes
= 1.22 standard deviations.
e 25 20 5
The probability value of Z = 1.22, is 0.888
f 29 20 9
g 21 20 1
h 14 10 4
i 25 24 1 1.22
j 35 35 0 Yes
106
105
Thus, there is a 95 percent chance of finishing the project by 52.45 days. 3 Used where times can be estimated Used where times cannot be estimated
with confidence, familiar activities with confidence.
Unfamiliar or new activities
107
108
BENEFITS OF CPM / PERT NETWORK BENEFITS OFCPM / PERT NETWORK (cont.)
Consistent framework for planning, scheduling, Identified activities with slacks that can be delayed for specified
monitoring, and controlling project. periods without penalty, or from which resources may be
temporarily borrowed
Shows interdependence of all tasks, work packages,
and work units. Determines the dates on which tasks may be started or must be
started if the project is to stay in schedule.
Helps proper communications between
departments and functions. Shows which tasks must be coordinated to avoid resource or
timing conflicts.
Determines expected project completion date. Shows which tasks may run in parallel to meet project
completion date
Identifies so-called critical activities, which can
delay the project completion time.
109 110
Pon
A*'u,tQ
-_
D:o tZ U)"",4-) 1
l-z "5
2-3 6
"3-5 5
z-4 4
" 3
"1 --S
/+
5-6
@ Dw,?'L'o/,
ryL& D--bAt
"
l-z 3 4-s 6
t-4 z -f-b {
t-? I 6-q 4t,',
2-3 L5
4-s +,
3-L 2 *-q b
:
4-5 ,4
'@.,. .ir.+ir;Ei
Pr"lrrro.* g#)l ,
-- A 3 "ji.
::r
.
-_'.;
B"
.."-,r
4r . ,:,;
e 3
/
,9 Z
'ro
e b;L {
C
I D;V- 3
, ,/.
.n .,- L
I
fi
AB
n B
iir-*: ,
'::'i'+ltj.
b
3 A 3:
(- e"
DA v ':tl
i2-
fn
.> D {
ha)
,<
IJ
4 E
rrlZ t /, I
rc
u,
5 .r) -Fr
L/
J
2
q ....
h,e1 I
'''2.
'"f 4- tJ
F,4
D
-
L
i
.i:
E tF)l-l
i
d I ? rl
b_.n 2-
i.,. :
::
;,J
l
@ P,o-orz^^A)-
WW)
A z
I
E
c a 3
D
A I
A
r 2_
a 4
E
q c ?
,t+ q I
2 b *
J btE)F,)4 €
V
II
u
khl,Q (i;,uo EsT EFT L9'i LtrJ Ft"*!.
? l2 b 1Z I 20 I
q Zo o LO 0 ?b o
p g 36
.B
L2 o 29
lz 2g 1o 3bi 4s 8
T z8 zo 48 LO: 4e o
U lz 4s 6o 1A, 6o o
V
8' 4o 4Q 5z 6ou ': . ,12-
N I a
6o be bo 6s
t,'
l
e
I
I
l
PsE : t-z-3-s-b -, <420
| -z - 4-5-L plb
A^l[r : l- 2'6 :) I
r- z:?:b :> @
t-2-3-9'6 z? 19
t-3-b => 1o>
t- Z*s-b *2 a
| - 4 - g-b -2 tB
Fa,[3 i ,-2-3-b-q:) lz
t-4- 5 -A-1 =2 @
t-1 g-1 =) 13
t-7 e-q =) lo
?^,1t,,. n-ts-D-tr*.)t2
A"e-E-F*r@
A''e-tr-l:z) 14
Pqlb' : A-D-i t3
4 -E-r =2
q
B.F. T ,7 lo
C-Ct-h-1 =, @
e-t
f)."-lho c A-e- E-T =+ @
A-1- F- lJ ='l + ls
,t4
A-D-q-h-I:>
F
4
c-4-tt-f =) tz