Pom Module 3

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 25

Production management is the process of Objectives of Production

planning, organising, directing and controlling Management


the activities of the production function The objective is to produce goods or
Production Management mainly deals with: services of right quality and quantity at the
Decision making related to production predetermined time and pre established
cost
process
So the objectives are:
Producing goods or service according to
standard specification Right quality
Producing good at minimum cost Right quantity
Producing goods at scheduled time Predetermined time
Pre established cost (Manufacturing
Cost)

Functions
The functions of production
The intermediate objectives are: department are grouped into two:
Machinery and Equipments The activity which convert the
Materials available capital into physical
Manpower resource required for
Supporting Service production
The activities which convert the
physical resources to saleable
goods

The functions of production personnel are:


Forecasting of demand
Use the forecast to determine the factors
While carrying out the functions the
of production
production department has to take care
of following things Arranging procurement of required
factors of production
Production of goods at right quantity
and quality Arranging services such as maintenance,
material handling, inspection quality
Production of goods at right time control etc
Production of goods at minimum Effective and optimum utilization of
possible cost facilities available for production
SCOPE OF PRODUCTION MANAGEMENT Strategic level decision
The strategic level decision are mainly
The objective of production involved with the design of product and
management is aimed at satisfying production system.
These decisions have long term implications.
the need of customer
The scope of production The strategic level decisions are:
management can be considered 1. New product identification and design
from the point of view of both 2. Process Design and Planning
3. Facilities Location and Layout Planning
Strategic level decision 4. Design of material handling system
5. Capacity planning
Operation level decision

1. New product identification and


2. Process Design and Planning
design
The product should have good It involves appropriate
market acceptability so that technology to convert raw
demand should be high material to products
The product design should meet The technology depends on
customer expectation
demand, investment capability,
The tools like value analysis should labour availability, degree of
be done to avoid unexpected cost
automation etc.
build up

3. Facilities Location and Layout


4. Design of material handling system
Planning
Material handling should be kept at
Due consideration should be
minimum.
given in location selection
The material flow and handling
Once located will not be altered equipment should be based on factors
in near future such as:
Distance between work stations
Intensity of flow traffic and size
Shape and nature of material to be
handled
5. Capacity planning Operational level decision

It mainly deals with Are short term decisions


procurement of fixed asset Mainly concerned with planning and
controlling of production activities
like plant and machineries It includes:
It decides the size of plant, Production planning
output etc. Production control
The other activities
It is a function of demand

Production planning Production control

It determines future course of It aims to ensure that activities


action regarding production to are carried out as per plan
achieve organisation objectives It take corrective action if there is
deviation between actual and
standard

The other activities TYPES OF PRODUCTION

The other activities include: The production system is mainly


classified into three:
Inventory control
Make to Stock Production System
Maintenance and replacement . Make to Order Production System
Cost reduction and Cost control Assemble to Order Production
etc. System
Make to Stock Production System Situation for make to stock production
In this system, the manufacturer stocks the
finished goods in inventory for immediate Fairly constant and predictable
shipment demand
This ensures the immediate delivery of good Products are few and are
quality, reasonably priced, standard
products standardized
Here the customer will not accept the delay Shorter delivery time expected by
in delivery and the management is required the customer
to maintain adequate stock
E.g. Ready to wear garments, nuts and bolts,
Products having higher shelf life
motors, television

Information needed Make to Order Production


Forecasted demand In this case the firm will manufacture
Opening inventory level product only after the receipt of order from
Desired ending inventory level customer
Any previous orders (Back Orders) The production activities is initiated only
after confirmation of order from customer
Hence the lead time is long
Total Production = Forecasted Demand +
Back Orders + Ending Inventory There is always direct interaction with
Opening Inventory customer during all stages
The production schedules changes with
changes in customer needs

Situation for make to order production Assemble to Order Production


Here the manufacturer will produce and stock all
the standard component parts required to
Products are manufactured according to produce goods or products.
customer specification Here the products are manufactured from
available components/parts according to the
Customer can wait still the order is being needs and specification of customer
processed i.e. the customer can choose the components for
the product
Product is non standard and expensive to Here the products are customized and variety of
store product can be produced
The only the time to assemble is needed before
When there are several product options delivering products
E.g. Computers, automobiles
CLASSIFICATION OF PRODUCTION Job Shop Production
SYSTEM This type is characterized by one or few
According to volume of production and quantity of products
product standardization
INTERMITTENT PRODUCTION It is designed and produced as per the
Job shop production specification of customer within prefixed
Batch production time and cost
Project industries It consist of general purpose machines
CONTINUOUS PRODUCTION arranged into departments.
Mass or flow production
The main feature is low volume and high
Process industries
variety of production
ASSEMBLY LINES
CELLULAR PRODUCTION It includes manufacturing of space craft,
aircraft special purpose machine tool etc.

Characteristics
Advantages
High variety of products and low volume
Use of general purpose machines and Variety of products can be
facilities produced
Highly skilled operators due to uniqueness Operator becomes skilled and
in job competent that each job gives
Process type layout for arrangement of
them learning opportunity
facilities
Movement of material is long and Utilization of full potential of
interrupted operator
Relative imbalance in workloads at various Opportunity to use innovative
departments
ideas and creative methods

Disadvantages Project Industries


Higher setup and tooling up cost In this type the materials, tools,
due to frequent set up changes equipment's and personnel's are brought
to the location where the product is to be
High inventory level of raw fabricated
material and hence high cost
The aim is to achieve specific objective
Production planning is within prescribed time and cost limitations
complicated Project is of ONE-OFF JOB which may
Skilled manpower is required not repeat exactly in the same manner
It has a definite start and finish. It is
Product cost comes high
executed in a time bound schedule
Batch Production The plant produces a batch of
product and kept in stock for sale
It is characterized by the manufacture Then it changes to another
of limited number of products product
produced at regular intervals in batches
or lots and stocked awaiting sales
When first product get depleted,
the production of first batch is
Different batches can be produced
repeated.
simultaneously through different
routing So alternately or intermittently
The system can also be used for the products can be changed
producing different products

Advantages Disadvantages
Better utilization of plant and Material handling is complex because
of longer and irregular flows
machinery
Production planning and control is
Promote functional specialization complex
Cost per unit is lower Work in progress inventory is higher
compared to continuous production
Lower investment in plant and
Longer production times
machinery
Higher setup cost due to frequent
Flexibility to accommodate and changes in setup.
process number of products

Characteristics
Mass Production
Standardization of product and process
sequence and hence line layout is
Manufacturing of discrete parts or
recommended
assemblies using a continuous
Dedicated, special purpose machines
process are called mass production
having higher production capabilities
or repetitive production. and output rates
Products are standardized Larger volumes of production
Large volume can be produced Shorter cycle time of production
Lower in process inventory
Perfectly balanced production lines
Advantages
Higher rate of production with reduced cycle time Process Industry
Higher capability balancing due to line balancing
Less skilled operators can make the process
Low in process inventory
It is the production process that includes
Production cost per unit is less mixing, separating and or performing chemical
reaction.
Disadvantages It is usually carried out in continuous mode
Break down of one machine will stop entire
production line It usually produces non discrete products in
Line layout needs adjustments with the changes in large volume
product design
High investment in production facilities
Supervision is general rather than specific
The cycle time is determined by the slowest
operation

CELLULAR PRODUCTION ASSEMBLY LINES


In this case the parts having similar processing Here the parts are added to a product in a
requirement are classified into part families. sequential manner to produce finished
Then a cell is created which includes all product.
equipment's, facilities and human skills It is first developed for the assembly of
required to produce a part family automobiles

PRODUCT DESIGN PROCESS


It includes
Conception
Acceptance
Execution
Translation
Pre-production
Acceptance Execution

FRAME WORK OF PRODUCTION


It mainly includes five s
The Product
The Plant
The Process
The Programme
The People

The Product The Plant


Product is the link between production and The plant should match the needs of
marketing products, the market, the people and the
The main aspects to be considered about a organisation.
product are: It includes:
Performance Design and layout of buildings
Quality and Reliability Reliability, perfection and maintenance of
Aesthetics and Ergonomics equipments
Quantity and Selling price Safety of operations
Delivery schedule The financial constraint
Growth Maturity (Saturation)
Sales start increasing during this stage due to Sales rate reaches a point above which it will
acceptability of product not grow
Growth rate will be high if there is limited or The sale will be maintained for some period
no competition

Decline Production Procedure


New product will come to the market with Sales forecast phase
better product features, advanced technology
and reduced price. Production planning activity phase
It create threat to the product and sales start Production Phase
declining
If proper care such as design changes, new
Dispatching Phase
features etc. are not incorporated, the
products are to be taken back from the
market

Sales forecast phase Production planning activity phase


Sales forcast is made by sales department Production budget- finance department
Manufacturing cycle triggered by Prepare drawing , specifications or
Customer orders check and modify existing ones- Engineering
Forecast of customer demand Product availability Dept.
good ware house
The marketing or sales department Management reviews the sales forecast and the
Thorough analysis budget to fix the quantities to be produced
Market research Production planning activity-schedule of
To know acceptability of the product by production
customers Inventory level procurement of material
Consumers reaction to new modifications Make or buy decision
and designs
INTRODUCTION
Schedule converts action plan into
operating time table
PERT &CPM Basis for monitoring and controlling
project
Scheduling more important in projects
than in production, because unique
nature
A project is any task which has
definable beginning and definable end 68

Importance of PERT/CPM
By using PERT and CPM analysis you will be able to answer questions such as:
1. When will the entire project be completed? NETWORK TECHNIQUES
2. What are the critical activities or tasks in the project, that is, the
ones that will delay the entire project if they are late? PERT CPM
3. Which are the noncritical activities, that is, the ones that can run
-Program Evaluation and Critical Path Method
late without delaying the whole completion time? Review Technique Developed by El Dupont
4. What is the probability that the project will be completed by a - developed by the US for Chemical Plant
specific date? Navy with Booz Shutdown Project- about
Hamilton Lockheed same time as PERT
5. At any particular date, is the project on schedule, behind schedule, - on the Polaris
or a head of the schedule? Missile/Submarine
6. On any given date, is the money spent equal to, less than, or greater program 1958
than the budgeted amount?
7. Are there enough resources available to finish the project on time? Both use same calculations, almost similar
Main difference is probabilistic and deterministic in time estimation
8. If the project is to be finished in a shorter amount of time, what is Gantt Chart also used in scheduling
the best way to accomplish this at the least cost? (crash analysis) 70

NETWORK Example of Simple Network


Survey
Graphical portrayal of activities and event
Shows dependency relationships between
tasks/activities in a project
Clearly shows tasks that must precede
(precedence) or follow (succeeding) other
tasks in a logical manner
Clear representation of plan a powerful tool
for planning and controlling project

71
72
Example of Network DEFINITION OF TERMS IN A NETWORK
More Complex Activity : any portions of project (tasks) which required
by project, uses up resource and consumes
time may involve labor, paper work,
contractual negotiations, machinery operations
Activity on Arrow (AOA) showed as arrow, AON
Activity on Node
Event : beginning or ending points of one or more
activities, instantaneous point in time, also

Network : Combination of all project activities and the events

PRECEEDING SUCCESSOR
ACTIVITY

EVENT
74

73

PERT/CPM
Emphasis on Logic in Network Construction
Two conventions
Construction of network should be based on logical or technical
nodes for events and arcs for activities (our convention) dependencies among activities
Example -

i j Common error build network on the basis of time logic (a


feeling for proper sequence ) see example below

arcs for events and nodes for activities

WRONG !!!
CORRECT
75
76

Example 1- A simple network Sequence of activities


Consider the list of four activities for making a
simple product: Can start work on activities A and B anytime,
since neither of these activities depends upon the
completion of prior activities.
Activity C cannot be started until activity B has
been completed
Activity D cannot be started until both activities
A and C have been completed.
Immediate predecessors for a particular activity are the
The graphical representation (next slide) is
activities that, when completed, enable the start of the
referred to as the PERT/CPM network
activity in question. 77 78
Network of Four Activities
Example 2
Develop the network for a project with following activities
and immediate predecessors:
Activity Immediate
predecessors
A -
B -
C B
D A, C
E C
F C
G D,E,F

Try to do for the first five (A,B,C,D,E) activities

79 80

Network of first five activities Network of Seven Activities


1 A 3 D 4 G
7
dummy E
B
C 5
F
2 6

Activity Immediate
Activity Immediate predecessors
predecessors A -
A -
B -
B -
C B
C B
D A, C
D A, C
E C
E C
F C
F C
81 G D,E,F 82
G D,E,F

EXAMPLES OF THE USE OF DUMMYACTIVITY


Network concurrent activities
a
a 2
Note how the network correctly identifies D, E, and F as 1 2 1 Dummy
the immediate predecessors for activity G. b
b 3
WRONG!!! RIGHT
Dummy activities is used to identify precedence
relationships correctly and to eliminate possible confusion
of two or more activities having the same starting and Activity c not WRONG !
required for e
ending nodes a
a e
d
Dummy activities have no resources (time, labor, b 1 b
1
e
machinery, etc) purpose is to PRESERVE LOGIC of the c
d
network c
2

WRONG
RIGHT
!!!
RIGHT

83 84
Network with LS & LF time
Latest start & latest finish time
D[5,8] 5
2 3[7,10]
To find the critical path we need a backward pass
calculation.
7
4
Starting at the completion point (node 7) and using a latest 1 6
finish time (LF) of 26 for activity I, we trace back through
the network computing a latest start (LS) and latest finish
time for each activity
3

The expression LS = LF t can be used to calculate latest


start time for each activity. For example, for activity I, LF =
26 and t= 2, thus the latest start time for activity I is Latest finish time rule:
LS = 26 2 = 24 The latest finish time for an activity entering a
particular node is equal to the smallest of the latest
91 start times for all activities leaving the node. 92

Slack or Free Time or Float Activity schedule for our example


Activity Earliest Latest Earliest Latest Slack Critical
Slack is the length of time an activity can be delayed without affecting the start (ES) start (LS) finish (EF) finish (LF) (LS-ES) path
completion date for the entire project.
For example, slack for C = 3 weeks, i.e Activity C can be delayed up to 3
A 0 0 5 5 0 Yes
weeks B 0 6 6 12 6
3
(start anywhere between weeks 5 and 8).
2
C 5 8 9 12 3
ES LS EF EF D 5 7 8 10 2
5 8 9 12
E 5 5 6 6 0 Yes
LF-EF = 12 9 =3
F 6 6 10 10 0 Yes
LS-ES = 8 5=3
G 10 10 24 24 0 Yes
H 9 12 21 24 3
LF-ES-t = 12-5-4 = 3
I 24 24 26 26 0 Yes
93
94

IMPORTANT QUESTIONS
Importance of Float (Slack) and Critical Path
What is the total time to complete the project?
1. Slack or Float shows how much allowance each activity has,
26 weeks if the individual activities are completed on schedule.
i.e how long it can be delayed without affecting completion
date of project
What are the scheduled start and completion times for each activity?
ES, EF, LS, LF are given for each activity.
2. Critical path is a sequence of activities from start to finish
with zero slack. Critical activities are activities on the
What activities are critical and must be completed as scheduled in order to critical path.
keep the project on time?
Critical path activities: A, E, F, G, and I.
3. Critical path identifies the minimum time to complete
project
How long can non-critical activities be delayed before they cause a delay in

Slack time available for all activities are given. 4. If any activity on the critical path is shortened or extended,
project time will be shortened or extended accordingly
95 96
Importance of Float (Slack) and Critical Path PERT For Dealing With Uncertainty
5. So, a lot of effort should be put in trying to control So far, times can be estimated with relative certainty,
activities along this path, so that project can meet due date. confidence
If any activity is lengthened, be aware that project will not
For many situations this is not possible, e.g Research,
meet deadline and some action needs to be taken.
development, new products and projects etc.

6. If can spend resources to speed up some activity, do so


Use 3 time estimates
only for critical activities.
tm= most likely time estimate, mode.
to = optimistic time estimate,
7. waste resources on non-critical activity, it will not
shorten the project time. tp = pessimistic time estimate, and

8. If resources can be saved by lengthening some activities, do Expected Value (te) = (to+4tm +tp) /6
so for non-critical activities, up to limit of float. Variance (V) = ( (tp-to)/ 6 ) 2
Std Deviation (S) = SQRT (V) ie (tp-to)/ 6
9. Total Float belongs to the path 97 98

99 100

Precedences And Project Activity Times


Immediate Optimistic Most Likely Pessimistic Var S.Dev
Activity Predecessor Time Time Time te V

a - 10 22 22 20 4 2
b - 20 20 20 20 0 0
c - 4 10 16 10 4 2
d a 2 14 32 15 25 5
e b,c 8 8 20 10 4 2
f b,c 8 14 20 14 4 2
g b,c 4 4 4 4 0 0
h c 2 12 16 11 5.4 2.32
I g,h 6 16 38 18 28.4 5.33
j d,e 2 8 14 8 4 2

101 102
Figure 8-13 The complete Network
The complete network

EF=20 35
d d
2 6 2 6
(15,25) a (15,25) j
j (20,4) (8,4)
(8,4) b e
a 20 43
(20,0) (10,4)
(20,4) e CRIT. TIME = 43
f 7
(10,4)
1 3
(14,4)
1 f 7
3 g
b (14,4)
c (4,0)
(20,0) i
(10,4)
g (18,28.4)
c h
(4,0) 4 5
(10,4) i (11,5.4)
(18,28.4) 10 24
h 5
4
(11,5.4)

103 104

Critical Path Analysis (PERT) Assume, PM promised to complete the project in the fifty days.
What are the chances of meeting that deadline?
Activity LS ES Slacks Critical ? Calculate Z, where
a 0 0 0 Yes
Z = (D-S) / V
b 1 0 1
Example,
c 4 0 4 D = 50; S(Scheduled date) = 20+15+8 =43; V = (4+25+4) =33
Z = (50 43) / 5.745
d 20 20 0 Yes
= 1.22 standard deviations.
e 25 20 5
The probability value of Z = 1.22, is 0.888
f 29 20 9

g 21 20 1

h 14 10 4

i 25 24 1 1.22
j 35 35 0 Yes

106
105

What deadline are you 95% sure of meeting


Comparison Between CPM and PERT
Z value associated with 0.95 is 1.645 CPM PERT
1 Uses network, calculate float or slack,
identify critical path and activities, Same as CPM
D = S + 5.745 (1.645) guides to monitor and controlling
= 43 + 9.45 project
= 52.45 days 2 Uses one value of activity time Requires 3 estimates of activity time
Calculates mean and variance of time

Thus, there is a 95 percent chance of finishing the project by 52.45 days. 3 Used where times can be estimated Used where times cannot be estimated
with confidence, familiar activities with confidence.
Unfamiliar or new activities

4 Minimizing cost is more important Meeting time target or estimating


percent completion is more important

5 Example: construction projects, Example: Involving new activities or


building one off machines, ships, etc products, research and development
etc

107
108
BENEFITS OF CPM / PERT NETWORK BENEFITS OFCPM / PERT NETWORK (cont.)
Consistent framework for planning, scheduling, Identified activities with slacks that can be delayed for specified
monitoring, and controlling project. periods without penalty, or from which resources may be
temporarily borrowed
Shows interdependence of all tasks, work packages,
and work units. Determines the dates on which tasks may be started or must be
started if the project is to stay in schedule.
Helps proper communications between
departments and functions. Shows which tasks must be coordinated to avoid resource or
timing conflicts.

Determines expected project completion date. Shows which tasks may run in parallel to meet project
completion date
Identifies so-called critical activities, which can
delay the project completion time.
109 110
Pon

A*'u,tQ
-_
D:o tZ U)"",4-) 1

l-z "5
2-3 6
"3-5 5
z-4 4
" 3
"1 --S
/+
5-6

M;u, b^-^L;(g ""p)


lsZ 3 I
I
l-3 I
t+ I
l-4
lo
L*3
-{
2*b
4
3-5
4.
3-L
'1 -E 3
t+ I

@ Dw,?'L'o/,
ryL& D--bAt
"
l-z 3 4-s 6
t-4 z -f-b {
t-? I 6-q 4t,',

2-3 L5
4-s +,
3-L 2 *-q b
:

4-5 ,4
'@.,. .ir.+ir;Ei

Pr"lrrro.* g#)l ,

-- A 3 "ji.
::r

.
-_'.;
B"
.."-,r
4r . ,:,;

e 3
/
,9 Z
'ro
e b;L {
C
I D;V- 3

A"*".Zi lr,).utNcr-t Ac,H",'E&


*--?

, ,/.

.n .,- L
I
fi
AB
n B
iir-*: ,
'::'i'+ltj.
b
3 A 3:
(- e"

DA v ':tl
i2-
fn
.> D {
ha)
,<
IJ
4 E
rrlZ t /, I

rc
u,
5 .r) -Fr
L/
J
2
q ....
h,e1 I
'''2.
'"f 4- tJ
F,4
D
-
L

i
.i:

E tF)l-l
i

d I ? rl
b_.n 2-

i.,. :
::
;,J
l
@ P,o-orz^^A)-
WW)
A z
I
E
c a 3
D
A I
A
r 2_

a 4
E
q c ?
,t+ q I
2 b *
J btE)F,)4 €

P*XLr-r-sarr ft-^ I t"""" )


4 tz ? t ?-i - t) - t/,t =)
P l\s. 6a
2-O
@ 6,_f-U_ td _) @
K zt ?- g- u-b/ , 64
-g R tL ?-g-t/-tzr) =) SL
f P,A z-*
d (f,3 I,Z
V s *
N q,l I

V
II
u
khl,Q (i;,uo EsT EFT L9'i LtrJ Ft"*!.
? l2 b 1Z I 20 I
q Zo o LO 0 ?b o
p g 36
.B
L2 o 29
lz 2g 1o 3bi 4s 8
T z8 zo 48 LO: 4e o
U lz 4s 6o 1A, 6o o
V
8' 4o 4Q 5z 6ou ': . ,12-
N I a
6o be bo 6s

t,'
l

e
I

I
l
PsE : t-z-3-s-b -, <420
| -z - 4-5-L plb

A^l[r : l- 2'6 :) I
r- z:?:b :> @
t-2-3-9'6 z? 19
t-3-b => 1o>

t- Z*s-b *2 a
| - 4 - g-b -2 tB

Fa,[3 i ,-2-3-b-q:) lz
t-4- 5 -A-1 =2 @
t-1 g-1 =) 13
t-7 e-q =) lo

w A -p-* E- H -T'L :2 2+4'ls+st l.lq+g =


A-s-c-P-L-k- t- =72+4+s+z+zl++E = 24
21

4 - e- c-.q -I -k- L- =7z +4?s+3'+2t4+g =@


A-B-D-h-!*lc-.L =)zt4+ s43) zf ++-9 = 23
L
,
ry

?^,1t,,. n-ts-D-tr*.)t2
A"e-E-F*r@
A''e-tr-l:z) 14

Pqlb' : A-D-i t3
4 -E-r =2
q
B.F. T ,7 lo
C-Ct-h-1 =, @

e-t
f)."-lho c A-e- E-T =+ @
A-1- F- lJ ='l + ls
,t4
A-D-q-h-I:>

F
4

?^W t A* D"'! '=) t3


A- D- ,f. =2
t+
A-r -A --) ?
B - F -{ =) to t"

c-4-tt-f =) tz

You might also like