The Employer : The Engineer : The Contractor : Sub-Contractor :

Build of Fit out and Museography at Qatar Olympic and Sports


Museum, Doha, QATAR

OPERATIONS & MAINTENANCE MANUAL


SYSTEM : GIBCA’s STEEL CUBICLES

Document Number: UCCAPD754-GIB-O&M-A-0012 Rev.00


Name Title Signature Date

Prepared by: Rithesh Kumar Shetty QA/QC Engineer 25.01.2021

Reviewed by: Walid Briekaa Technical Manager 25.01.2021

Approved by: Mohamed K Kamal Sr. Project Manager 25.01.2021

Endorsed By Aitor Tarrega Project Director 25.01.2021


Copyright ©: This document is the property of UCCAPD JV and all rights are reserved in respect of it. This document may not be reproduced or disclosed
in any manner, in whole or in part without the prior written consent of UCCAPD JV Management. UCCAPD JV expressly disclaims any responsibility for or
liability arising from the use of this document by third party. Unless specifically stated otherwise; all printed copies are uncontrolled and not subject to
revision control.

Table of contents
Operations & Maintenance Manual
System : GIBCA’s STEEL CUBICLES.
Build of Fit out and museography at Qatar Olympic Rev. Page
and Sports Museum 00 32

S. No Description File

1.0 Contractual Contact Details

2.0 Definitions & Abbreviations

3.0 System Description

4.0 Equipment Schedule.

5.0 Spare part List/Recommended Spare Parts List

6.0 Factory Test Certificates/Testing and Commissioning Reports

7.0 Operating Instructions & Procedure.

8.0 Maintenance Procedure & Schedule-Disposal Instructions.

9.0 Manufacturer Contact Details.

10.0 Manufacturers Literature & Manuals

11.0 As Built Drawings.

12.0 Guarantee and Warranties ( Draft copy)

1.0 Contractual Contact Details.


Operations & Maintenance Manual
System : GIBCA’s STEEL CUBICLES.
Build of Fit out and museography at Qatar Olympic Rev. Page
and Sports Museum 00 32

Main Contractor: UCCAPD JV

UCC- Urbacon Trading and Contracting


Address: 4th Floor, COM 39 Tower , Lusail City
P.O Box: 201184
Phone: +974 44292920
Fax: +974 4429 2244
Email: info@urbacon-intl.com.

APD- ACCIONA Producciones y Diseño


Address: 1st floor, Ghanim Bin Saad Al Saad & Sons Group holding building
Salwa Road Street , Al Rayaan.
Phone: +974 44991826
Fax: +974 4499 1879

Subcontractor: GIBCA Ltd Co. (FZC) LLC


Address: P.O Box 312,
Postal code 322, Sohar, Sultanate of Oman.
Phone: +968 26850261
Fax: +968 26850258
Email Address: info@gibcaoman.com
Website: www.gibcaoman.com

Flat No 1702,renco Tower, Media City, Dubai, UAE. PO BOX 48


2.0 Definitions & Abbreviations.
Operations & Maintenance Manual
System : GIBCA’s STEEL CUBICLES.
Build of Fit out and museography at Qatar Olympic Rev. Page
and Sports Museum 00 32

UCCPAD JV- Urbacon trading & Contracting & Acciona Producciones y Diseño- Main Contractor
(JV)
GIB– GIBCA Ltd Co. (FZC) LLC.
HSE- Health Safety and Environment
QCS -Qatar Construction Specifications 2014
O & M – Operation & Maintenance.

3.0 General System Description

GIBCA'S STEEL CUBICLE (STEELO GS)

CONSTRUCTION: Complete Cubicle consisting of Front Posts, Divider Panel and Door made of
stainless Steel in
1mm thickness with polypropylene Honey Comb Core. The edges are in solid grade compact
laminate.
Door & Post: 30mm thick. Divider: 25mm thick.
HARDWARE: STAINLESS STEEL
ACCESSORIES INCLUDE: Doorknob, Privacy thumb turn with red & white indicator, Coat hook
cum door
stopper, S.S Hinges, S.S. Adjustable foot and S.S Top rail.

LAYOUT DETAILS:
SECOND FLOOR
MALE DRESSING / REST ROOMS SECOND FLOOR MUSEUM BUILDING:
TOILET CUBICLES -6 Nos, SHOWER CUBICLES -5 Nos & CHAINGING ROOM CUBICLES - 4Nos =
15 Nos
FEMALE DRESSING / REST ROOMS SECOND FLOOR MUSEUM BUILDING:
TOILET CUBICLES -8 Nos, SHOWER CUBICLES -5 Nos & CHAINGING ROOM CUBICLES - 7Nos =
20 Nos

THIRD FLOOR
MALE & FEMALE STAFF REST ROOMS THIRD FLOOR MUSEUM BUILDING: MOCKUP
TOILET CUBICLES -4 Nos
MALE REST ROOMS THIRD FLOOR MUSEUM BUILDING:
TOILET CUBICLES -4 Nos
FEMALE REST ROOMS THIRD FLOOR MUSEUM BUILDING:
TOILET CUBICLES -6 Nos
Total Qty of Cubicles = 49 Nos

SAFETY PROCEDURE
Operations & Maintenance Manual
System : GIBCA’s STEEL CUBICLES.
Build of Fit out and museography at Qatar Olympic Rev. Page
and Sports Museum 00 32

General
Before commencing any task, give careful consideration to what is or may be involved; the
extent of the plant/equipment requiring attention; how your intended activities may affect
others working in the vicinity.
Should an accident occur details must be entered in the Clients Accident Report Book and
submitted immediately to the Client it is the Client responsibility to provide a system for the
Reporting of Injuries, Diseases and Dangerous Occurrences.
Copies of a suitable occurrence repot form must be freely available for use. (Refer to the
British “Essentials of Health and Safety at Work” HMSO document ISBN 0118839772 for
guidance and local Government Regulations).
It is recommended that a Permit to Work system be adopted to assure the safety of all
operatives and occupants.

Before commencing work on any items of mechanical and/or electrical equipment a Permit to
Work docket signed by an appropriate authority should be obtained. On completion of the
work it should be returned for logging in the master maintenance system records.

The Permit to work system should cover the following aspect;


 To give authority to maintenance staff to commence inspection or work on plant.
 To explain in outline the approach required to carry out the work in a way that no personnel
or plant hazard to the working environment is crested.
 To co-ordinate staff requirements in relation to the maintenance procedures and operations
thus eliminating exposure of the work face to any hazard.
The system should be devised so that maintenance may be carried out safely and that no
starting or running of plant presents an environment hazard.
Correct shutting down of systems must be observed where removal of guards or housing has
taken place and no electrical work on equipment must be undertaken without satisfactory
clearance that the plant is now safe for work to proceed.

Members of the maintenance staff must carry out work within the scope of their particular
discipline and job descriptions.
Where it is necessary to provide staging, scaffolding tower and ladders to examine or carry out
the replacement of components then these must comply in all respects with the latest
legislation.

4.0 Equipment Schedule


GIBCA'S STEEL CUBICLE (STEELO GS)
Operations & Maintenance Manual
System : GIBCA’s STEEL CUBICLES.
Build of Fit out and museography at Qatar Olympic Rev. Page
and Sports Museum 00 32

CONSTRUCTION: Complete Cubicle consisting of Front Posts, Divider Panel and Door made of
stainless Steel in
1mm thickness with polypropylene Honey Comb Core. The edges are in solid grade compact
laminate.
Door & Post: 30mm thick. Divider: 25mm thick.
HARDWARE: STAINLESS STEEL
ACCESSORIES INCLUDE: ACCESSORIES INCLUDE: Doorknob, Privacy thumb turn with red &
white indicator, Coat
hook cum door
stopper, S.S Hinges, S.S. Adjustable foot and S.S Top rail.
Electrically Operated Machinery (Power Tools)
1. Router Machine
2. Drilling Machines
3. Hammering Drill
4. Jigsaw
5. Tighter Machine
Basic Hand Tools
6. Hammer
7. Hand saws, (wood/metal)
8. Screw drivers
9. Ladders /step ladders
10. Spirit Level
11. Trowels
12. Multi Socket Extensions
13. Miscellaneous hand tools

5.0 Recommended Spare Parts List


GIBCA'S STEEL CUBICLE (STEELO GS)
Hardware Stainless Steel (Normbau)
1. Stainless Steel Privacy Thumb turn with Red/White Indicator
2. Stainless Steel Hinges
3. Stainless Steel Doorknob
4. Stainless Steel Hinge Cover
5. Stainless Steel Coat Hook/Door Stopper
6. S.S. Adjustable foot
7. Stainless Steel Top rail

MANUFACTURING & SHIPPING TIME REQUIRED FOR IMPORTED SPARE PART:


Stockpiling of spare parts for Toilet Cubicles is not being recommended by the manufacturer.
However, in case of any requirement for components they are readily available at GIBCA Ltd
Co. (FZC)
LLC with address at P.O. Box 312, Postal Code322, Sohar, Sultanate of Oman, contact details:
Tel +968
2685 0261, Fax- +968 2685 0258, Email- info@gibcaoman.com and website
Operations & Maintenance Manual
System : GIBCA’s STEEL CUBICLES.
Build of Fit out and museography at Qatar Olympic Rev. Page
and Sports Museum 00 32

www.gibcaoman.com.

6.0 Factory Test Certificates/Testing and Commissioning Reports


N/A

7.0 Operating Instructions & Procedures


The GIBCA'S STEEL CUBICLE (STEELO SS) Complete Cubicle consisting of Front Posts,
Divider Panel and Door made of stainless Steel in 1mm thickness with polypropylene Honey
Comb Core. The edges are in solid grade compact laminate.

Door & Post: 30mm thick. Divider: 25mm thick, suitable for wet areas. which is a phenolic
resin material with sanitary grade melamine surface.

The hardware includes Hinges, Doorknob, Adjustable Foot, Coat Hook and Privacy thumb turn
locking device are of stainless steel construction. One hinge on the door is spring loaded which
will hold the door in close or open position, if the cubicle is occupied the indicator on door face
will show red color.

The thumb turn locking device is operated manually by rotating the arm in a clockwise
direction and opened by rotating anti-clockwise. In an emergency, the door may be unlocked
from outside by inserting a coin in the slot in the center of the thumb turn and rotating
clockwise.

8.0 Maintenance Procedure & Schedule-Disposal Instructions.

The cleaning of all components of the Gibca's Steel Cubicle (Steelo GS) requires only a mild
soap
solution in warm water, harsh scouring agents or any detergent containing bleach should not
be used.

The only maintenance required is an occasional lubrication of the hinges with light oil.

Spare parts are available from GIBCA Ltd Co. (FZC) LLC with address at P.O. Box 312, Postal
Code322, Sohar, Sultanate of Oman, contact details: Tel +968 2685 0261, Fax- +968 2685
0258, Emailinfo@gibcaoman.com and website www.gibcaoman.com.

MAINTENANCE CYCLE:
Operations & Maintenance Manual
System : GIBCA’s STEEL CUBICLES.
Build of Fit out and museography at Qatar Olympic Rev. Page
and Sports Museum 00 32

RECOMMENDED MAINTENANCE SCHEDULES AND FAULTFINDING TABLE.


Operations & Maintenance Manual
System : GIBCA’s STEEL CUBICLES.
Build of Fit out and museography at Qatar Olympic Rev. Page
and Sports Museum 00 32
Operations & Maintenance Manual
System : GIBCA’s STEEL CUBICLES.
Build of Fit out and museography at Qatar Olympic Rev. Page
and Sports Museum 00 32

1. Modification information
The GIBCA'S STEEL CUBICLE (STEELO GS) installed on the project has been selected
specifically to suit the projects requirements and there is no facility for modification

2. Disposal instruction
Fire behaviour of the HPL Panels is excellent. HPL panels don’t melt, drip or explode and
retains its stability for a long time. Furnished with high chemical resistance and not
adversely affected by moisture. Panel waste can be disposed off or used just like normal
building or demolition waste. If it burned in industrial furnaces, no hazardous corrosive
gases are released.
For further advice contact:
DEPARTMENT OF ENVIRONMENTAL PROTECTION

9. Manufacturer Contact Detail.


: GIBCA'S STEEL CUBICLE (STEELO
Names of Item
GS)
Name of the Manufacturer : GIBCA Ltd Co. (FZC) LLC
: GIBCA Ltd Co. (FZC) LLC
Name of Supplier
: P.O. Box 312, Postal Code322, Sohar,
Address
Sultanate of Oman.
Telephone Number
: +968 2685 0261
Fax Number
: +968 2685 0258
Email Address
: info@gibcaoman.com
Website : www.gibcaoman.com.

: Eng. Sheeraz Haider Naqvi.


Contact Person
: +968 2685 0261
Telephone Number
:+968 98081686 /Qatar +974 55052657
Mobile Number :
Email Address : Sheeraz.Haider@gibcaoman.com
Operations & Maintenance Manual
System : GIBCA’s STEEL CUBICLES.
Build of Fit out and museography at Qatar Olympic Rev. Page
and Sports Museum 00 32

10.Manufacturer Literature and Manuals


Operations & Maintenance Manual
System : GIBCA’s STEEL CUBICLES.
Build of Fit out and museography at Qatar Olympic Rev. Page
and Sports Museum 00 32

11. As Built Drawings


As-Built drawings submitted separately.
Operations & Maintenance Manual
System : GIBCA’s STEEL CUBICLES.
Build of Fit out and museography at Qatar Olympic Rev. Page
and Sports Museum 00 32

12. Guaranty/ Warranty Certificate:

You might also like