Fair Mutasa
The Borrowdale Race Course Office Park Construction Site Stanford Mawedze
Tavonga Dhlembeu
(Ques 1a) Obert Femayi
EXECUTIVE SUMMARY Hazel Kunaka
Old Mutual undertook to construct an upmarket office park at the Borrowdale Race
Course area. The office park ranked the best in the country designed with fine, modern
and intriguing architecture occupies an area of 67 hectares . Old Mutual engaged John
Sisk to execute this momentous project as the main contractor, with about twenty other
companies sub contracted to carry out specific work in their respective areas of
specializations. The project started in 2005 and was temporarily suspended during the
2008-2010 hyperinflation era only to commence mid 2011 with an improved design.
Earthworks Front end loader
The construction of the office park involved considerable earthworks from the onset.
The state of the art office park was to incorporate a basement, underground storage
tanks and tunnels, and a road loop around the structure with car parking slots for tenants
of up to 600 vehicles parking capacity. Earthworks for road construction was being done The Road loop being constructed covers an area of 3436m²
by Bitcon. Roadbed and subgrade material (natural gravel) of 1780m³ from a
Road loop borrow pit at Mt Hampden 23km from site were to be compacted to
Road loop 93% ModAASHTO.
Construction of 540m³ subbase to 95% ModAASHTO. Subbase
material comprising of 19mm stones and dust was obtained from
Pomona Stone Crushers.
The Structures
Road loop
Granite.
EXCAVATION
Road loop
COMPACTION
Bobycat
Manual Excavation
Trench for drainage detail (Ques 4)
width = 1m 1m
invert level = 0.45m
gradient = 1: 40
68000mm
Calculations:
Trench longitudinal section = 88.4m²
width of trench = 1m
Total volume excavated = 88.4m³
Number of laborers = 8 plus 1 supervisor
Excavation per laborer per day = 2.5m³
per hour = 2.5m³ ÷ 9 working hours
= 0.28m³ per hour
Time for excavation = (88.4m³ ÷ 0.28m³) per hr
= 315.7hrs per laborer
Time for excavation for the
eight laborers = 315.7hrs ÷ 8
= 39.46hours
Wages (NEC grade 1) = $1.57 per hour
Overhead costs = 10% Stabilising material
C le a r s it e o f r u b b is h , g r a s s , t r e e s e t c
(Ques 3)
E x c a va tio n G a n g G .B & 1 0 2 4 4 .9 8 p day / 250m 2 per day
L 0 .9 8
0 .9 8
Exc a v o v e r s it e a v e . 1 5 0 m m f o r v e g e t a b le s o il a n d d e p o s it o n s it e n o t e xc e e d in g 1 0 0 m
Swell factors
Clay = 30%
E x c a va tio n G a n g ( G .B & 1 0 ) ( b u lkin g ) 2 4 4 .9 8 p day / 200 sq m per day 1 .2 2
E x c a va tio n G a n g ( G .B & 1 0 ) ( d e p o s it) - p day / 250 sq m per day -
1 .2 2 sand = 5%
L 1 .2 2
Exc a v a t e o v e r s it e t o r e m o v e v e g e t a b le s o il a n d c a r t a w a y
L 1 .2 2
gravel = 5%
Exc a v a t e in p ic ka b le m a t .t o r e d u c e d le v e ls n .e 2 m d e e p
E x c a va tio n G a n g G .B & 1 0 2 4 4 .9 8 p day / 22 cu m p day 1 1 .1 4
REFERENCES:
Old Mutual Properties department
L 1 1 .1 4
Ministry of Transport Materials Reference Manual.
Rates Build Up Schedule by Bitcon Quantity Surveyor
Garry Woolsen & Nemhara (Jonh Sisk Site Engineers)
Exc a v a t e in p ic ka b le m a t . f o r t r e n c h e s e xc e e d in g 2 0 0 0 n .e . 4 0 0 0 m m d e e p . Mr. S. Shumba (lecturer Civil Engineering)
E x c a va tio n G a n g G .B & 1 0 2 4 4 .9 8 p day / 12 cu m p day 2 0 .4 2 Field Manual (FM 5-434 USA army)
L 2 0 .4 2 National Employmet Council (NEC) informative
circular no: 002/2012.