Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 2

SCHEDULE PELAKSANAAN PEKERJAAN FIRE SUPPRESSION JAKARTA INTERNATIONAL STADIUM

BULAN 1 BULAN 2 BULAN 3


No KETERANGAN Minggu -1 Minggu -2 Minggu -3 Minggu -4 Minggu -5 Minggu -6 Minggu -7 Minggu -8 Minggu -9 Minggu -10 Minggu -11 Minggu -12
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

1 Penerimaan PO
2 Material Approval & Detail Drawing
2.1 Shop Drawing Approval
2.2 Equipment & Instalasi Approval
2.3 As Built Drawing
3 Procurement
3.1 Pengadaan Material Instalasi
3.2 Pengadaan Main Equipment
4 Mobilisasi & Demobilisasi (Man Power)
5 Delivery Material
5.1 Material Instalasi
5.2 Material Equipment Fire Alarm
5.3 Material Equipment Fire Suppression
6 Instalasi Elektrik:
6.1 Smoke Detector
6.2 Manual Release
6.3 Abort Switch
6.4 Alarm Bell dan Horn
6.5 Evacuate dan Gas Discharge
6.6 Low pressure Switch
6.7 Electric Solenoid
6.8 Power 220Vac
6.9 Instalasi Shutdown AC
7 Instalasi Mekanik
7.1 Fabrikasi Support
7.2 Fabrikasi Pipa
7.3 Pemasangan Instalasi Pipa
8 Pemasangan Material Equipment
8.1 Material Elektrik
8.2 Material Mekanik
9 Internal Test & Trouble Shooting
10 Testing & Commisioning ,Training
SCHEDULE PELAKSANAAN PEKERJAAN FIRE SUPPRESSION JAKARTA INTERNATIONAL STADIUM

BULAN 4 BULAN 5 BULAN 6


No KETERANGAN Minggu -13 Minggu -14 Minggu -15 Minggu -16 Minggu -17 Minggu -18 Minggu -19 Minggu -20 Minggu -21 Minggu -22 Minggu -23 Minggu -24
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

1 Penerimaan PO
2 Material Approval & Detail Drawing
2.1 Shop Drawing Approval
2.2 Equipment & Instalasi Approval
2.3 As Built Drawing
3 Procurement
3.1 Pengadaan Material Instalasi
3.2 Pengadaan Main Equipment
4 Mobilisasi & Demobilisasi (Man Power)
5 Delivery Material
5.1 Material Instalasi
5.2 Material Equipment Fire Alarm
5.3 Material Equipment Fire Suppression
6 Instalasi Elektrik:
6.1 Smoke Detector
6.2 Manual Release
6.3 Abort Switch
6.4 Alarm Bell dan Horn
6.5 Evacuate dan Gas Discharge
6.6 Low pressure Switch
6.7 Electric Solenoid
6.8 Power 220Vac
6.9 Instalasi Shutdown AC
7 Instalasi Mekanik
7.1 Fabrikasi Support
7.2 Fabrikasi Pipa
7.3 Pemasangan Instalasi Pipa
8 Pemasangan Material Equipment
8.1 Material Elektrik
8.2 Material Mekanik
9 Internal Test & Trouble Shooting
10 Testing & Commisioning ,Training

Dibuat Oleh,
PT MAHAWIRA PUTRA TEKNIK

You might also like