Professional Documents
Culture Documents
OTC 21066 New 9-7/8-In. HPHT Permanent Packer With New Back-Up System Provides North Sea Operator With An Effective Solution For Worn Casing
OTC 21066 New 9-7/8-In. HPHT Permanent Packer With New Back-Up System Provides North Sea Operator With An Effective Solution For Worn Casing
OTC 21066 New 9-7/8-In. HPHT Permanent Packer With New Back-Up System Provides North Sea Operator With An Effective Solution For Worn Casing
New 9-7/8-in. HPHT Permanent Packer with New Back-Up System Provides
North Sea Operator with an Effective Solution for Worn Casing
Richard Innes and Michael Eddy, Total E&P UK Ltd; John Ligertwood, NRD, Limited; Thomas Robb and Ernie
Valentine, Halliburton
Copyright 2010, Offshore Technology Conference
This paper was prepared for presentation at the 2010 Offshore Technology Conference held in Houston, Texas, USA, 3–6.
This paper was selected for presentation by an OTC program committee following review of information contained in an abstract submitted by the author(s). Contents of the paper have not been
reviewed by the Offshore Technology Conference and are subject to correction by the author(s). The material does not necessarily reflect any position of the Offshore Technology Conference, its
officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written consent of the Offshore Technology Conference is prohibited. Permission to
reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of OTC copyright.
Abstract
A major operator in the North Sea had experienced a problem with worn casing at the packer setting depth of an existing
HPHT well, causing a leak into the production annulus. This problem required a workover, and a calliper survey was
conducted after retrieving the tubing. Two large grooves along the longitudinal axis of the casing at 120° to each other were
found.
Since the worn casing was the problem, a new permanent packer was required, and this paper will discuss the process
required to successfully qualify and install an HPHT permanent packer that would satisfactorily address the needs for worn
casing.
Permanent packers are qualified by ISO 14310 V0 in a test fixture to meet the API 5CT internal casing dimensions;
however, they do not account for any wear or damage in the casing. A test program was developed to test the packer for both
HPHT well conditions and worn casing. The test program consisted of the following:
1. Install the packer in 9-7/8-in casing and flow test to 3 bpm at 180°F to verify that the circulation around the packer
would not damage the Aflas® element.
2. Perform an application test using synthetic oil to mimic packer loading until failure, including setting, production,
and hot/cold shut in.; apply 9,000 psi annulus pressure to
support the casing during testing. In this case, the
maximum temperature was 343°F or above for over 200
hours.
3. Perform a modified ISO 14310 V0 test at 450°F with
15,000 psi differential pressure and 400,000 lbf tension
and compression.
The packer passed all tests with no extrusion of the three-piece
multi-durometer Aflas® element, and no leaks were detected at any
of the load points in the application (liquid) test or modified ISO
V0 gas test.
The discussion will include information on the packer design,
HPHT tests in worn casing, and casing acceptance criteria. This
test was the first packer test performed in worn casing that
demonstrated the capability of a compliant back-up system to
support the entire element in worn casing and at the HPHT
conditions.
Introduction
The Elgin Franklin fields were discovered in 1991 and 1986
respectively and are the largest and highest pressured HPHT gas
fields to be developed in the UK. The fields lie approximately 140
miles East of Aberdeen in the Central Graben region of the North
Sea (Fig 1). The primary reservoir is the Fulmar sands, which is
Fig 1: Location
2 R. INNES, M. EDDY, J. LIGERTWOOD, T. ROBB, and E. VALENTINE OTC-21066
located at an approximate depth of 19,000- ft TVD SS. Reservoir fluids within the Fulmar are gas condensate with a
bottomhole pressure of 16,000 psi and a static temperature of 375º F. The Fulmar reservoir is underlain by the Pentland
reservoir with bottomhole conditions of 16,500 psi and 392º F.
Production commenced in 2001 with an infrastructure that was comprised of a fixed wellhead platform for the Elgin and
Franklin reservoirs plus a production, utilities and quarters (PUQ) jack-up platform adjacent to the Elgin wellhead platform.
The PUQ is linked to the Elgin wellhead platform by a 300-ft-long bridge and to the Franklin wellhead platform by a subsea
pipeline bundle. Both Elgin and Franklin wellhead platforms normally are unmanned and are operated remotely from the
PUQ. Drilling and completion of the wells was carried out by two heavy-duty jack-ups in cantilever mode over the wellhead
jackets. Fig 2 shows the Elgin Franklin infrastructure.
Fig. 5—Packer
Envelope.
Design Review
Prior to any testing, a detailed design review on the 9-7/8-in. HPHT permanent packer was completed. This review included
the packer design, drawings, metallic materials, elastomers, element material, quality plans, and ISO 14310 test. The brief
technical specifications for the packer are detailed below:
• Casing: 9-7/8-in., 62.8–68 lb/ft and 9-5/8-in., 47–53.5 lb/ft
• Maximum OD: 8.31 in.
• Minimum ID: 3.961 in.
• Differential Pressure rating: 15,000 psi
• Temperature rating: 212–450°F
• Connections: 5-in., 23.2-lb/ft Vam Top HC x 5-½-in., 26-lb/ft Vam Top
Qualification Testing
The packer was already qualified for 9-7/8-in., 62.8–68-lb/ft and 9-5/8-in., 47–53.5-lb/ft casing and previously had been
tested to ISO 14310 V0 in a 9-5/8-in., 47-lb maximum-ID casing fixture of 8.821 inches. The packer was qualified, therefore,
from a minimum ID of 8.390-in. to a maximum ID of 8.821-in.
The purpose of the new test was to qualify the packer for the customer-supplied worn casing (9-7/8 in., 66.9 lb Q125) and
to the HPHT well conditions. The test was performed in three parts:
• A flow test with water at 3 bbl/min and 180°F.
• An application test with synthetic oil at the maximum temperature of 423°F and the minimum temperature of 343°F.
• A modified V0 test with nitrogen at the maximum temperature of 450°F and the minimum temperature of 212°F.
OTC-21066 NEW 9-7/8-IN. HPHT PERMANENT PACKER WITH NEW BACK-UP SYSTEM PROVIDES NORTH SEA 5
OPERATORS WITH AN EFFECTIVE SOLUTION FOR WORN CASING
The testing was conducted at the High Temperature Test Facility (HTTF) in Dallas, Texas. The customer-supplied 9-7/8-
in. casing was shipped to Dallas, and the grooves were machined into the ID to mimic the casing-wear grooves that had been
experienced in the actual well.
Test Casing
The well was completed with 9 7/8-in. 66.9-lb Q125 casing. The longitudinal casing grooves measured in the well at the
packer setting depth included the following dimensions: one was 1 mm (0.040 in.) x 70 mm (2.7-in.) and the other 0.7 mm
(0.028-in.) x 120 mm (4.7-in.). The grooves were spaced 120° apart.
For the test casing, the grooves were machined, and the wall thickness was measured (ultrasonically), as shown in Fig 7.
Note:
The yellow line represents the minimum depth of the groove required by the customer.
The magenta curve represents the actual 2.70 width groove inside the casing.
Fig. 7 − 2.7-in. Test Casing Grooves Machined into the Test Casing.
The 2.7-in. wide groove depth was measured at 0.070–0.085-in. at the element area. Although this depth is slightly deeper
than the requirements of 0.040-in. for the 2.7-in. groove, it was within the maximum ID of the standard ISO test previously
qualified, and subsequently, provided a worst-case scenario. The 4.7-in. groove was measured at 0.025–0.045-in. at the
element area.
The casing was inspected dimensionally, both before and after the test. The OD and wall thickness were recorded. All
tests (flow, application, and modified ISO) were conducted in the actual casing.
To support the casing during the application and modified ISO tests, an external pressure of 9,000 psi was maintained
throughout the tests to support the casing and represent the reservoir pore pressure without cement.
Flow Test
The purpose of this test was to install the packer inside the 9-7/8-in., 66.9-lb (Q125) casing and to verify that circulation
around the packer would not damage or pack off the Aflas® element. This test would replicate running the packer and
circulating prior to setting the packer. Flow was in the direction from the bottom of the packer up around the annulus area
between the packer and the casing and out through a perforated pup joint. The flow rate was increased in 0.5-bpm increments
up to a maximum of 3 bpm and held for 7 hours. The fluid used during the flow test was water heated to 180°F.
This test arrangement is shown in Fig. 8. After the flow test, the packer was removed from the casing and was fully
inspected. No damage was noted, and the element, back-up shoes, and slips were found to be in good condition.
The packer was set hydraulically with the minimum setting pressure of 6,800 psi. To help support the casing, an external
pressure of 9,000 psi was maintained throughout the test. The test medium for the application test was oil, and the test
temperature was between 343°F and 423°F. A hydraulic jack was connected directly to the top of the packer and provided the
compressive and tensile loads.
The application test was conducted using test pressures and applied axial loads based on the customer program, as shown
in Table 1. This test was used to mimic the critical well conditions experienced in the well and covered setting the packer,
tubing tests, annulus tests, hot shut-in, and cold shut-in. The duration of the tests varied from 2 hours to a maximum of 72
hours for the cold shut-in. No leaks were detected at any of the load points during the application load test.
The test casing assembly was removed from the test fixture and was examined for any signs of damage. The casing OD
dimensions were verified. The packer was inspected, and no signs of Aflas® extrusion were found in the test fluid.
Table 1: Application
These loads were not the maximum tensile/compressive loads for the packer; however, they were the required maximum
to capture all load points for the well conditions. The ISO 14310 V0 test was conducted to ensure no Aflas® extrusion would
occur at the maximum predicted loads for the packer envelope. Table 2 shows the load points around the envelope and the
temperature cycle from 450°F down to 212°F. No leaks were detected during the test at any of the envelope load points.
The test casing assembly was removed from the test fixture. The casing was milled longtitudinally, and the packer was
removed and found to be in excellent condition, with no signs of Aflas® extrusion. All of the packer’s critical components
were dimensionally verified.
8 R. INNES, M. EDDY, J. LIGERTWOOD, T. ROBB, and E. VALENTINE OTC-21066
As shown in Fig. 11, the element package showed no signs of extrusion. The element and back-up shoes were in excellent
condition. A groove track was visable where the element package had set into the machined grooves in the casing. The
grooves in the casing were also inspected and verified.
Qualification
The results of the casing-wear tests demonstrated that the new compliant back-up system prevented extrusion of the Aflas®
element at HPHT conditions. Wear grooves are acceptable as long as the circle formed from the casing centerline to the
maximum groove depth does not exceed a diameter of 8.821-in. This diameter was the maximum ID to which the packer was
qualified in the original casing test fixture (i.e., 9-5/8-in., 47-lb/ft casing).
The two machined grooves in the test casing were within this maximum ID. The actual casing ID was 8.64-in., and the
2.7-in. wide groove was 0.085-in. deep. Conservatively, the operator limited the maximum ID to 8.7-in., including the
deepest groove.
OTC-21066 NEW 9-7/8-IN. HPHT PERMANENT PACKER WITH NEW BACK-UP SYSTEM PROVIDES NORTH SEA 9
OPERATORS WITH AN EFFECTIVE SOLUTION FOR WORN CASING
Conclusion
From the successful test program, the following can be concluded:
1. The packer successfully passed the test program, which consisted of the flow test, application test (liquid), and the
modified ISO 14310 V0 (gas) test. All pressure holds were normal with no returns.
2. At the conclusion of the test, the packer was removed from the test fixture. There were no measurable dimensional
changes for the critical components of the packer.
3. The packer’s fully-compliant back-up system prevented any external or internal extrusion with the worn casing and
fully supported the element at the HPHT conditions.
4. The packer was qualified for a specific level of casing wear and the HPHT conditions of 15000 psi and 450° F.
The packer has been successfully installed in a North Sea HPHT well.
Acknowledgements
The authors wish to thank Total E & P UK Limited and Halliburton for their encouragement and permission to publish this
paper.
References
Hillis, D; Eddy, M; Cassagne T; Ligertwood, J: “Investigation of Production Tubing Coupling Failures from a Suspended HPHT Well,”
Paper 123892, Offshore Europe, Aberdeen, Sept 2009.
Humphreys, A.: “Completion of Large-Bore High Pressure/High Temperature Wells: Design and Experience,” Paper 12120, Offshore
Technology Conference, Houston, May 2000.
Ray, T: “High Pressure/High Temperature (HP/HT) Seals for Oil and Gas Production,” Paper 39573 presented at Oil and Gas Conference
and Exhibition, New Delhi, February 1998.
Robb, T. and Valentine, E.: “New 9-7/8-in. HPHT Permanent Packer with New Back-Up System Provides North Sea Operator with
Effective Solution for Damaged or Worn Casing,” Paper SPE 132176 presented at the SPE Deep Gas Conference and Exhibition held
in Manama, Bahrain, 24-26 January 2010.