This document contains cost estimates for several construction jobs including:
1) Excavation of 1 cubic meter of normal soil to a depth of 1 meter, costing 89,000 IDR.
2) Backfilling 1 cubic meter of excavated soil, costing 60,000 IDR.
3) Installing 1 meter of 90mm diameter HDPE pipe, costing 20,000 IDR.
4) Testing 1 meter of 90mm diameter HDPE pipe, costing 1,000 IDR.
It also provides cost estimates for two bridge pipe projects using 90mm diameter GI pipe.
This document contains cost estimates for several construction jobs including:
1) Excavation of 1 cubic meter of normal soil to a depth of 1 meter, costing 89,000 IDR.
2) Backfilling 1 cubic meter of excavated soil, costing 60,000 IDR.
3) Installing 1 meter of 90mm diameter HDPE pipe, costing 20,000 IDR.
4) Testing 1 meter of 90mm diameter HDPE pipe, costing 1,000 IDR.
It also provides cost estimates for two bridge pipe projects using 90mm diameter GI pipe.
This document contains cost estimates for several construction jobs including:
1) Excavation of 1 cubic meter of normal soil to a depth of 1 meter, costing 89,000 IDR.
2) Backfilling 1 cubic meter of excavated soil, costing 60,000 IDR.
3) Installing 1 meter of 90mm diameter HDPE pipe, costing 20,000 IDR.
4) Testing 1 meter of 90mm diameter HDPE pipe, costing 1,000 IDR.
It also provides cost estimates for two bridge pipe projects using 90mm diameter GI pipe.
This document contains cost estimates for several construction jobs including:
1) Excavation of 1 cubic meter of normal soil to a depth of 1 meter, costing 89,000 IDR.
2) Backfilling 1 cubic meter of excavated soil, costing 60,000 IDR.
3) Installing 1 meter of 90mm diameter HDPE pipe, costing 20,000 IDR.
4) Testing 1 meter of 90mm diameter HDPE pipe, costing 1,000 IDR.
It also provides cost estimates for two bridge pipe projects using 90mm diameter GI pipe.
No Uraian Kode Satuan Koefisiensi Harga Satuan Jumlah Harga A TENAGA KERJA Pekerja L.01 OH 0,7500 98.200,00 73.650,00 Mandor L.04 OH 0,0250 157.120,00 3.928,00 JUMLAH TENAGA KERJA 77.578,00 B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 77.578,00 E OVER HEAD & PROFIT 15% 11.636,70 F HARGA SATUAN PEKERJAAN (D+E) 89.000,00
A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah
No Uraian Kode Satuan Koefisiensi Harga Satuan Jumlah Harga A TENAGA KERJA Pekerja L.01 OH 0,5000 98.200,00 49.100,00 Mandor L.04 OH 0,0250 157.120,00 3.928,00 JUMLAH TENAGA KERJA 53.028,00 B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 53.028,00 E OVER HEAD & PROFIT 15% 7.954,20 F HARGA SATUAN PEKERJAAN (D+E) 60.000,00
A. 8.4.1.20.b (K3) Pemasangan 1 m Pipa HDPE dia. 90 mm
No Uraian Kode Satuan Koefisiensi Harga Satuan Jumlah Harga A TENAGA KERJA Pekerja L.01 OH 0,0425 98.200,00 4.173,50 Tukang Pipa L.02 OH 0,0215 157.120,00 3.378,08 Mandor L.04 OH 0,0045 157.120,00 707,04 JUMLAH TENAGA KERJA 8.258,62 B BAHAN Pipa HDPE dia 90 mm 1,0000 95.000,00 95.000,00
JUMLAH HARGA BAHAN 95.000,00
C PERALATAN Sewa Tripod / Tacker dan Hari 0,0190 173.000,00 3.287,00
JUMLAH HARGA ALAT 3.287,00
6 M' 106.545,62 D JUMLAH (A+B+C) 1 M' 17.757,60 E OVER HEAD & PROFIT 15% 2.663,64 F HARGA SATUAN PEKERJAAN (D+E) 20.000,00
A. 8.4.5.3.b (K3) Pengetesan 1 m HDPE dia. 90 mm
No Uraian Kode Satuan Koefisiensi Harga Satuan Jumlah Harga A TENAGA KERJA Pekerja L.01 OH 0,0080 98.200,00 785,60 Mandor L.04 OH 0,0008 157.120,00 125,70 JUMLAH TENAGA KERJA 911,30 B BAHAN Air Test (Air Bersih) m3 0,0130 1.000,00 13,00 Bahan Bakar Liter 0,0600 2.000,00 120,00 Oli Liter 0,0020 53.000,00 106,00 JUMLAH HARGA BAHAN 239,00 C PERALATAN -
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 1.150,30 E OVER HEAD & PROFIT 15% 172,54 F HARGA SATUAN PEKERJAAN (D+E) 1.000,00 IX.B.4A Jembatan pipa DIA. 90 ( 3") MM, dengan L = 9,00 m' Pengadaan pipa & Accessories Pengadaan Pipa GI dia. 90 mm m' 12,00 255.500,00 3.066.000,00 Pengadaan Bend 45 0 dia. 90 mm Bh 4,00 439.000,00 1.756.000,00 Pengadaan Losse Flange dia. 90 mm Bh 6,00 137.000,00 822.000,00 Pengadaan Stub End HDPE Dia. 90 mm Bh 2,00 258.000,00 516.000,00 Pengadaan Packing Karet Dia. 90 mm Bh 6,00 41.000,00 246.000,00 Pengadaan Stop Kran Dia. 25 mm Bh 1,00 33.000,00 33.000,00 Pengadaan Double Nipple Dia. 25 mm Bh 1,00 13.000,00 13.000,00 Baut Moer Bh 40,00 1.000,00 40.000,00 Pengukuran dan pemasangan Bowplank m' 6,00 64.000,00 384.000,00 Galian tanah m3 2,00 89.000,00 178.000,00 Urugan tanah dan dipadatkan m3 0,67 60.000,00 40.000,00 Pemasangan Thrust Block Dan Kayu Balok Unit 2,00 1.293.000,00 2.586.000,00 Cerucuk Kayu Galam dia. 10 cm, Pjg = 4 m' Btg 18,00 14.000,00 252.000,00 Pemasangan Air Valve dia. 50 mm Bh 1,00 893.000,00 893.000,00 Perapihan ls 1,00 193.000,00 193.000,00 Jumlah 11.018.000,00 OVER HEAD & PROFIT 15% 1.652.700,00 Dibulatkan 12.670.000,00
IX.B.4B Jembatan pipa DIA. 90 ( 3") MM, dengan L = 15,0 m'
Pengadaan pipa & Accessories Pengadaan Pipa GI dia. 90 mm m' 18,00 255.500,00 4.599.000,00 Pengadaan Bend 45 0 dia. 90 mm Bh 4,00 439.000,00 1.756.000,00 Pengadaan Losse Flange dia. 90 mm Bh 6,00 137.000,00 822.000,00 Pengadaan Stub End HDPE Dia. 90 mm Bh 2,00 258.000,00 516.000,00 Pengadaan Packing Karet Dia. 90 mm Bh 6,00 41.000,00 246.000,00 Pengadaan Stop Kran Dia. 25 mm Bh 1,00 33.000,00 33.000,00 Pengadaan Double Nipple Dia. 25 mm Bh 1,00 13.000,00 13.000,00 Baut Moer Bh 40,00 1.000,00 40.000,00 Pengukuran dan pemasangan Bowplank m' 6,00 64.000,00 384.000,00 Galian tanah m3 2,00 89.000,00 178.000,00 Urugan tanah dan dipadatkan m3 0,67 60.000,00 40.000,00 Pemasangan Thrust Block Dan Kayu Balok Unit 2,00 1.293.000,00 2.586.000,00 Cerucuk Kayu Galam dia. 10 cm, Pjg = 4 m' Btg 18,00 14.000,00 252.000,00 Pemasangan Air Valve dia. 50 mm Bh 1,00 893.000,00 893.000,00 Perapihan ls 1,00 193.000,00 193.000,00 Jumlah 12.551.000,00 OVER HEAD & PROFIT 15% 1.882.650,00 Dibulatkan 14.433.000,00
IX.B.4C Jembatan pipa DIA. 90 ( 3") MM, dengan L = 8,00 m'
Pengadaan pipa & Accessories Pengadaan Pipa GI dia. 90 mm m' 11,00 255.500,00 2.810.500,00 Pengadaan Bend 45 0 dia. 90 mm Bh 4,00 439.000,00 1.756.000,00 Pengadaan Losse Flange dia. 90 mm Bh 6,00 137.000,00 822.000,00 Pengadaan Stub End HDPE Dia. 90 mm Bh 2,00 258.000,00 516.000,00 Pengadaan Packing Karet Dia. 90 mm Bh 6,00 41.000,00 246.000,00 Pengadaan Stop Kran Dia. 25 mm Bh 1,00 33.000,00 33.000,00 Pengadaan Double Nipple Dia. 25 mm Bh 1,00 13.000,00 13.000,00 Baut Moer Bh 40,00 1.000,00 40.000,00 Pengukuran dan pemasangan Bowplank m' 6,00 64.000,00 384.000,00 Galian tanah m3 2,00 89.000,00 178.000,00 Urugan tanah dan dipadatkan m3 0,67 60.000,00 40.000,00 Pemasangan Thrust Block Dan Kayu Balok Unit 2,00 1.293.000,00 2.586.000,00 Cerucuk Kayu Galam dia. 10 cm, Pjg = 4 m' Btg 18,00 14.000,00 252.000,00 Pemasangan Air Valve dia. 50 mm Bh 1,00 893.000,00 893.000,00 Perapihan ls 1,00 193.000,00 193.000,00 Jumlah 10.762.500,00 OVER HEAD & PROFIT 15% 1.614.375,00 Dibulatkan 12.376.000,00 IX.B.4D Jembatan pipa DIA. 90 ( 3") MM, dengan L = 8,50 m' Pengadaan pipa & Accessories Pengadaan Pipa GI dia. 90 mm m' 11,50 255.500,00 2.938.250,00 Pengadaan Bend 45 0 dia. 90 mm Bh 4,00 439.000,00 1.756.000,00 Pengadaan Losse Flange dia. 90 mm Bh 6,00 137.000,00 822.000,00 Pengadaan Stub End HDPE Dia. 90 mm Bh 2,00 258.000,00 516.000,00 Pengadaan Packing Karet Dia. 90 mm Bh 6,00 41.000,00 246.000,00 Pengadaan Stop Kran Dia. 25 mm Bh 1,00 33.000,00 33.000,00 Pengadaan Double Nipple Dia. 25 mm Bh 1,00 13.000,00 13.000,00 Baut Moer Bh 40,00 1.000,00 40.000,00 Pengukuran dan pemasangan Bowplank m' 6,00 64.000,00 384.000,00 Galian tanah m3 2,00 89.000,00 178.000,00 Urugan tanah dan dipadatkan m3 0,67 60.000,00 40.000,00 Pemasangan Thrust Block Dan Kayu Balok Unit 2,00 1.293.000,00 2.586.000,00 Cerucuk Kayu Galam dia. 10 cm, Pjg = 4 m' Btg 18,00 14.000,00 252.000,00 Pemasangan Air Valve dia. 50 mm Bh 1,00 893.000,00 893.000,00 Perapihan ls 1,00 193.000,00 193.000,00 Jumlah 10.890.250,00 OVER HEAD & PROFIT 15% 1.633.537,50 Dibulatkan 12.523.000,00
IX.B.4E Jembatan pipa DIA. 90 ( 3") MM, dengan L = 10,0 m'
Pengadaan pipa & Accessories Pengadaan Pipa GI dia. 90 mm m' 13,00 255.500,00 3.321.500,00 Pengadaan Bend 45 0 dia. 90 mm Bh 4,00 439.000,00 1.756.000,00 Pengadaan Losse Flange dia. 90 mm Bh 6,00 137.000,00 822.000,00 Pengadaan Stub End HDPE Dia. 90 mm Bh 2,00 258.000,00 516.000,00 Pengadaan Packing Karet Dia. 90 mm Bh 6,00 41.000,00 246.000,00 Pengadaan Stop Kran Dia. 25 mm Bh 1,00 33.000,00 33.000,00 Pengadaan Double Nipple Dia. 25 mm Bh 1,00 13.000,00 13.000,00 Baut Moer Bh 40,00 1.000,00 40.000,00 Pengukuran dan pemasangan Bowplank m' 6,00 64.000,00 384.000,00 Galian tanah m3 2,00 89.000,00 178.000,00 Urugan tanah dan dipadatkan m3 0,67 60.000,00 40.000,00 Pemasangan Thrust Block Dan Kayu Balok Unit 2,00 1.293.000,00 2.586.000,00 Cerucuk Kayu Galam dia. 10 cm, Pjg = 4 m' Btg 18,00 14.000,00 252.000,00 Pemasangan Air Valve dia. 50 mm Bh 1,00 893.000,00 893.000,00 Perapihan ls 1,00 193.000,00 193.000,00 Jumlah 11.273.500,00 OVER HEAD & PROFIT 15% 1.691.025,00 Dibulatkan 12.964.000,00
IX.B.4F Jembatan pipa DIA. 90 ( 3") MM, dengan L = 12,0 m'
Pengadaan pipa & Accessories Pengadaan Pipa GI dia. 90 mm m' 15,00 255.500,00 3.832.500,00 Pengadaan Bend 45 0 dia. 90 mm Bh 4,00 439.000,00 1.756.000,00 Pengadaan Losse Flange dia. 90 mm Bh 6,00 137.000,00 822.000,00 Pengadaan Stub End HDPE Dia. 90 mm Bh 2,00 258.000,00 516.000,00 Pengadaan Packing Karet Dia. 90 mm Bh 6,00 41.000,00 246.000,00 Pengadaan Stop Kran Dia. 25 mm Bh 1,00 33.000,00 33.000,00 Pengadaan Double Nipple Dia. 25 mm Bh 1,00 13.000,00 13.000,00 Baut Moer Bh 40,00 1.000,00 40.000,00 Pengukuran dan pemasangan Bowplank m' 6,00 64.000,00 384.000,00 Galian tanah m3 2,00 89.000,00 178.000,00 Urugan tanah dan dipadatkan m3 0,67 60.000,00 40.000,00 Pemasangan Thrust Block Dan Kayu Balok Unit 2,00 1.293.000,00 2.586.000,00 Cerucuk Kayu Galam dia. 10 cm, Pjg = 4 m' Btg 18,00 14.000,00 252.000,00 Pemasangan Air Valve dia. 50 mm Bh 1,00 893.000,00 893.000,00 Perapihan ls 1,00 193.000,00 193.000,00 Jumlah 11.784.500,00 OVER HEAD & PROFIT 15% 1.767.675,00 Dibulatkan 13.552.000,00 IX.B.4G Jembatan pipa DIA. 90 ( 3") MM, dengan L = 18,0 m' Pengadaan pipa & Accessories Pengadaan Pipa GI dia. 90 mm m' 21,00 255.500,00 5.365.500,00 Pengadaan Bend 45 0 dia. 90 mm Bh 4,00 439.000,00 1.756.000,00 Pengadaan Losse Flange dia. 90 mm Bh 6,00 137.000,00 822.000,00 Pengadaan Stub End HDPE Dia. 90 mm Bh 2,00 258.000,00 516.000,00 Pengadaan Packing Karet Dia. 90 mm Bh 6,00 41.000,00 246.000,00 Pengadaan Stop Kran Dia. 25 mm Bh 1,00 33.000,00 33.000,00 Pengadaan Double Nipple Dia. 25 mm Bh 1,00 13.000,00 13.000,00 Baut Moer Bh 40,00 1.000,00 40.000,00 Pengukuran dan pemasangan Bowplank m' 6,00 64.000,00 384.000,00 Galian tanah m3 2,00 89.000,00 178.000,00 Urugan tanah dan dipadatkan m3 0,67 60.000,00 40.000,00 Pemasangan Thrust Block Dan Kayu Balok Unit 2,00 1.293.000,00 2.586.000,00 Cerucuk Kayu Galam dia. 10 cm, Pjg = 4 m' Btg 18,00 14.000,00 252.000,00 Pemasangan Air Valve dia. 50 mm Bh 1,00 893.000,00 893.000,00 Perapihan ls 1,00 193.000,00 193.000,00 Jumlah 13.317.500,00 OVER HEAD & PROFIT 15% 1.997.625,00 Dibulatkan 15.315.000,00
IX.B.4H Jembatan pipa DIA. 90 ( 3") MM, dengan L = 7,0 m'
Pengadaan pipa & Accessories Pengadaan Pipa GI dia. 90 mm m' 10,00 255.500,00 2.555.000,00 Pengadaan Bend 45 0 dia. 90 mm Bh 4,00 439.000,00 1.756.000,00 Pengadaan Losse Flange dia. 90 mm Bh 6,00 137.000,00 822.000,00 Pengadaan Stub End HDPE Dia. 90 mm Bh 2,00 258.000,00 516.000,00 Pengadaan Packing Karet Dia. 90 mm Bh 6,00 41.000,00 246.000,00 Pengadaan Stop Kran Dia. 25 mm Bh 1,00 33.000,00 33.000,00 Pengadaan Double Nipple Dia. 25 mm Bh 1,00 13.000,00 13.000,00 Baut Moer Bh 40,00 1.000,00 40.000,00 Pengukuran dan pemasangan Bowplank m' 6,00 64.000,00 384.000,00 Galian tanah m3 2,00 89.000,00 178.000,00 Urugan tanah dan dipadatkan m3 0,67 60.000,00 40.000,00 Urugan tanah dan dipadatkan Unit 2,00 1.293.000,00 2.586.000,00 Cerucuk Kayu Galam dia. 10 cm, Pjg = 4 m' Btg 18,00 14.000,00 252.000,00 Pemasangan Air Valve dia. 50 mm Bh 1,00 893.000,00 893.000,00 Perapihan ls 1,00 193.000,00 193.000,00 Jumlah 10.507.000,00 OVER HEAD & PROFIT 15% 1.576.050,00 Dibulatkan 12.083.000,00