Professional Documents
Culture Documents
Cost Analysis For Cement Production
Cost Analysis For Cement Production
On
for
By
“AKHILESHWAR KUMAR”
Submitted to
“University of Pune”
Through
Pune-48.
BRACT’s
info@vim.ac.in, www.vim.ac.in
Certificate
This is to certify that Mr. AKHILESHWAR KUMAR has completed the Summer
Project Titled “COST ANALYSIS FOR CEMENT PRODUCTION” to my
satisfaction and as per the requirements of the two year full-time MBA programme.
Date:
ACC Limited
Chaibasa Cement Works
P.O. Jhinkpani
July 17, 2008 Singhbhum (W) - 833215
Jharkhand, India
Phone: +91-6589-235224
Fax : +91-6589-235250
www.acclimited.com
CERTIFICATE
During the training period, his performance, conduct etc were found very
good. We wish him ever success in his career.
Mr. P. K. MOHANTY
Manager-Finance
Chaibasa Cement Works
Registered Office: Cement House, 121, Maharshi Karve Road, Mumbai 400020,India.
ACKNOWLEDGEMENT
programme.
and Dr. Smita Sovani, Finance faculty of VIM for their guidance and Support
esteemed organization. He has been benevolent enough to lend help and spare his
valuable time throughout this project. He has been immensely contributive with his
ideas, constructive criticism and motivation which were the guiding light during the
Finally I also extend my heartiest thanks to Mr. B.PAN (Costing) and other
without the support of whom, this project would not have been successful.
AKHILESHWAR KUMAR
LIST OF TABLES
INDEX
CHAPTER
1. EXECUTIVE SUMMARY 1-2
INDIA
INTRODUCTION
ACC VISION
HISTORY
CORPORATE GOVERNANCE
IT INFRASTRUCTURE
PRODUCT : CEMENT
PRODUCT QUALITY
PIONEERING EFFORTS
INTERNATIONAL
RECOGNITION
RESEARCH AND
DEVELOPMENT
PRIORITY TO POLLUTION
CONTROL
STRATEGIC PERPECTIVE
WORKS
HISTORY
CONTRIBUTION TO SOCIO-
ECONOMICAL ASPECTS
IT-INFRASTRUCTURAL
INFRASTRUCTURAL FACILITY
3. OBJECTIVES OF STUDY 31-32
4. RESEARCH METHODOLOGY 33
5. DATA ANALYSIS 34-80
ANALYSIS OF COST
6. FINDINGS 81
7. SUGGESTIONS AND CONCLUSIONS 82-83
8. LIMITATIONS 84
9. BIBLIOGRAPHY 85
CHAPTER-I
EXECUTIVE SUMMARY
This project includes cost analysis of cement production in ACC Limited, Chaibasa
and concrete. ACC's operations are spread throughout the country with 14 modern
cement factories, more than 30 Ready mix concrete plants, 20 sales offices, and
several zonal offices. Duration of project was 21 st May to 17th July. Procedure of
carrying out the project: - In first week I was observing various works carried out in
the factory and become familiar with all the functions carried out in the plant.
In current economic scenario and cutthroat competition, it is very important for any
business to manage and utilize its resources to the best. Resources can be man,
Material, machinery, money and market. Finance is one of the most important areas of
ways is an integral part of the job of managers who are involved in planning,
begin the report, the introduction and detailed discussions about the Cement
Manufacturing Industry, basic concept of costing through three cost centre such as
main cost centre, auxiliary cost centre and pre-process cost centre, the main study
issue:-
“Cost Analysis for Cement Production” of ACC Limited Chaibasa Cement Works”
developed.
The project explores the different constituent element of variable cash cost and its
1. Cost sheet will be useful for price restructuring. Head office has been decided
profit margin and thereby decides the selling price. It is observed that
maintenance cost of plant is increasing. This analysis will help the finance
CHAPTER-II
COMPANY PROFILE
INTRODUCTION
modern world because of its intrinsic performance characteristics, its versatile uses in
constructions and its ability to create pleasing aesthetic structures. Cement industries
Cement is one of the key infrastructures for industries. India is the second largest
cement producer in the world, with an installed capacity of 160 million tonnes.
Cement industry has undergone rapid technological up- gradation and vibrant growth
during the last two decades, and some of the plants can be compared in every aspect
Indian cement industry is a mixture of mini and large capacity cement plants, and
majority of the production of cement in the country (94%) is by large plants, which
are defined as plants having capacity of more than 600 TPD(tonne per day). The
installed capacity is distributed over across approximately 129 large cement plants
Indian cement industry is one of the key industries amongst various old economy
industries, which have witnessed up and down cycles along with the general
economic trend in the past. However, the Indian economy has gathered its momentum
in the last couple of the years the fortunes of this industry have also swung from being
As an emerging market India has substantial potential. The growth outlook for the
Indian economy over the coming year is positive. The country’s dynamic expansion
of India’s infrastructure at 125 kilograms per capita per year, cement consumption is
currently among the lowest in Asia. Cement consumption of 139 million tonnes in
Indian cement industry has turned the corner. Currently, the demand supply situation
Housing sector, which accounts for 50% of the demand, is see to grow at 15%
years.
Cement being one of the key construction material has witnessed a robust growth of
more than 8.5 percent in volume terms during the third quarter of current financial
year and about 10 percent rise in dispatches in the first nine months of the year mainly
The structure of the industry is fragmented, although, the concentration at the top is
increasing. The fragmented structure is a result of the low entry barriers in the post
decontrol period and the ready availability of technology. However, cement plants are
capital intensive and require a capital investment of over Rs.3500 per ton of cement,
which translates into an investment of Rs.3500 million for a 1 mtpa green field plant.
TABLE A
COMPANY INSTALLED CAPACITY %
(MILLION TONES)
ACC Ltd 19.4 12
Ultra Tech Cement Ltd 17.0 11
Gujarat Ambuja Group 14.9 9
Grasim Industries 14.1 9
India Cements 8.8 5
J. K. Group 6.7 4
Century Textiles 6.3 4
Jaypee Cement Ltd 6.1 4
Others 67.0 42
Total 160.3 100
INTRODUCTION
ACC (ACC Limited) is India's foremost manufacturer of cement and concrete. ACC's
operations are spread throughout the country with 14 modern cement factories, more
than 30 Ready mix concrete plants, 20 sales offices, and several zonal offices. It has a
9,000 dealers. ACC's research and development facility has a unique track record of
its inception in 1936, the company has been a trendsetter and important benchmark
for the cement industry in respect of its production, marketing and personnel
programmes have won it acclaim as a responsible corporate citizen. ACC has made
significant contributions to the nation building process by way of quality products,
In the 70 years of its existence, ACC has been a pioneer in the manufacture of cement
and concrete and a trendsetter in many areas of cement and concrete technology
ACC’s brand name is synonymous with cement and enjoys a high level of equity in
the Indian market. It is the only cement company that figures in the list of Consumer
The company's various businesses are supported by a powerful, in-house research and
technology backup facility - the only one of its kind in the Indian cement industry.
This ensures not just consistency in product quality but also continuous improvements
ACC has rich experience in mining, being the largest user of limestone, and it is also
one of the principal users of coal. As the largest cement producer in India, it is one of
the biggest customers of the Indian Railways, and the foremost user of the road
transport network services for inward and outward movement of materials and
products.
ACC has also extended its services overseas to the Middle East, Africa, and South
consumers, and also helps in the operation and maintenance of cement plants abroad.
ACC is among the first companies in India to include commitment to environmental
protection as one of its corporate objectives, long before pollution control laws came
into existence. The company installed pollution control equipment and high efficiency
sophisticated electrostatic precipitators for cement kilns, raw mills, coal mills, power
plants and coolers as far back as 1966. Every factory has state-of-the art pollution
ACC demonstrates the practices of being a good corporate citizen undertaking a wide
ACC VISION
Safety of employee.
HISTORY
ACC was formed in 1936 when ten existing cement companies came together under
one umbrella in a historic merger – the country’s first notable merger at a time when
the term mergers and acquisitions was not even coined. The history of ACC spans a
wide canvas beginning with the lonely struggle of its pioneer F E Dinshaw and other
Indian entrepreneurs like him who founded the Indian cement industry. Their efforts
to face competition for survival in a small but aggressive market mingled with the
stirring of a country’s nationalist pride that touched all walks of life – including trade,
The first success came in a move towards cooperation in the country’s young cement
industry and culminated in the historic merger of ten companies to form a cement
giant. These companies belonged to four prominent business groups – Tatas, Khataus,
Killick Nixon and F E Dinshaw groups. ACC was formally established on August 1,
1936. Sadly, F E Dinshaw, the man recognized as the founder of ACC, died in
ACC stands out as the most unique and successful merger in Indian business history,
in which the distinct identities of the constituent companies were melded into a new
cohesive organization – one that has survived and retained its position of leadership in
industry. In a sense, the formation of ACC represents a quest for the synergy of good
business practices, values and shared objectives. The use of the plural in ACC’s full
name, The Associated Cement Companies Limited, itself indicates the company’s
origins from a merger. Many years later, some stockbrokers in the country’s leading
A strategic alliance
The house of Tata was intimately associated with the heritage and history of ACC,
right from its formation in 1936 upto 2000. Between the years 1999 and 2000, the
Tata group sold all 14.45 per cent of its shareholding in ACC in three stages to
subsidiary companies of Gujarat Ambuja Cements Ltd (GACL), who are now the
largest single shareholder in ACC. This has enabled ACC to enter into a strategic
alliance with GACL; a company reputed for its brand image and cost leadership in the
cement industry.
A new association was forged between ACC and the Holcim group of Switzerland in
2005. In January 2005, Holcim announced its plans to enter into a long-term strategic
alliance with the Ambuja Group by acquiring a majority stake in Ambuja Cements
India Ltd. (ACIL), which at the time held 13.8 per cent of the total equity shares in
ACC. Holcim simultaneously announced its bid to make an open offer to ACC
shareholders, through Holcim Cement Pvt Limited and ACIL, to acquire a majority
shareholding in ACC. An open offer was made by Holcim Cement Pvt. Limited along
with Ambuja Cements India Ltd. (ACIL), following which the shareholding of ACIL
increased to 34.69 per cent of the Equity share capital of ACC. Consequently, ACIL
has filed declarations indicating their shareholding and declaring itself as a Promoter
of ACC.
Holcim is the world leader in cement as well as being large suppliers of concrete,
in information technology and research and development. The group has its
CORPORATE GOVERNANCE
The importance of Corporate Governance has always been recognised in ACC. Much
before Corporate Governance guidelines became applicable and mandatory for listed
companies; ACC had systems in place for effective strategic planning and processes,
risk management, human resources development and succession planning. The Audit
Investors Grievance Committee was formed way back in 1962 and the Compensation
Committee was convened since 1993. The Company’s core values are based on
integrity, respect for the law and strict compliance thereof, emphasis on product
quality and a caring spirit. Corporate Governance therefore in ACC is a way of life.
IT INFRASTRUCTURE
ACC was among the first Indian companies to adopt automation of information
It has traveled a long way from its early days when it was using simple keypunching
infrastructure since then - from Batch processing to on-line systems, from IBM 1401
and Data General system to the latest Linux/UNIX and Windows 2003 based
machines. It has made timely transitions determined by available technologies and
business requirements.
In February 2007 the company made a quantum jump from in-house developed
systems using Oracle 9i and Developer 6i to an ERP (SAP) based solution. This
decision was based solely on our strategic objectives and the business benefits that it
expects to derive from implementing such a solution. With this move it also aligned
and R&D centers, it has invested in the creation of a comprehensive infrastructure that
allows free flow of information across the organization. This enables almost instant
connects each of our 275 plus locations. A judicious mix of VSAT and VPN links
Patni Computer Systems installed India’s first Data General computer in ACC in 1978
and deployed a team of their best employees to manage it. The team comprised the
legendary Narayanamurthy, then among the earliest employees of PCS. They were
given an office in Cement House. Later when he and others from PCS established
Infosys Technologies in Bangalore 1981, ACC was among their first customers.
3. Lucky Minmat
District Bargarh
Orissa -768038
Fax: 91-6646-46430
Chaibasa Chaibasa Cement Works 0.87
District Singhbhum
Jharkhand
Phone: 91-6589-35224
Fax: 91-6589-35250
Chanda Chanda Cement Works 1.00
P.O. Cementnagar
Dist Chandrapur
Maharashtra
Phone: 91-7172-275026
Fax: 91-7172-275165
Damodhar Damodar Cement Works 0.53
Madhukunda
District Purulia
West Bengal
Phone: 91-341-230671/672
Fax: 91-341-230671
Gagal Gagal Cement Works 4.40
District Bilaspur
Himachal Pradesh
Phone: 91-1978-244041/31
Fax: 91-1978-244067
Jamul Jamul Cement Works 1.58
District Durg
Chhattisgarh
Tel:00-91-788-383 082/84
Fax:00-91-788-382 585/643
Kymore Kymore Cement Works 2.20
P.O. Kymore
Dist. Katni
Madhya Pradesh
Phone: 91-7626-272301
Fax: 91-7626-272303
Lakheri Lakheri Cement Works 1.50
P.O. Lakheri
Dist Bundi
Rajasthan
Phone: 91-7438-261642/54
P.O. Madukkarai
District Coimbatore
Tamil Nadu
Phone: 91-422-822282/449
Fax: 91-422-822286
Sindri Sindri Cement Works 0.91
District Dhanbad
Jharkhand
P.O. Wadi
Karnataka
Phone: 91-08476-302406/302239
Fax: 91-08476-302190
New Wadi Wadi Cement Works 2.60
Karnataka
Plant
ACC Limited
Uttar Pradesh
Phone: 91-5368-44279
Fax: 91-5368-44479
PRODUCT: CEMENT
ACC Cement is the most commonly used cement in all constructions including plain
and reinforced cement concrete, brick and stone masonry, floors and plastering. It is
also used in the finishing of all types of buildings, bridges, culverts, roads, water
What is more, it surpasses BIS Specifications (IS 8112-1989 for 43 grade OPC) on
This is an Ordinary Portland Cement which surpasses the requirements of IS: 12269-
53 Grade. It is produced from high quality clinker ground with high purity gypsum.
ACC 53 Grade OPC provides high strength and durability to structures because of its
optimum particle size distribution, superior crystalline structure and balanced phase
composition.
BLENDED CEMENTS
Portland Cement clinker with high quality processed fly ash - based on norms set by
the company's R&D division. This unique, value-added product has hydraulic binding
ACC Fly-ash based PPC is made by intergrinding high strength clinker with specially
processed fly ash. This imparts a greater degree of fineness to ACC Fly-ash based
PPC cement, improved workability properties while mixing, and makes concrete more
corrosion resistant and impermeable. All of this makes for better long-term strength
and improved corrosion resistance and therefore, greater life for your constructions.
In concrete made from ordinary cements, moisture reacts with calcium hydroxide in
concrete to form calcium bicarbonate, which leaches out of the concrete, leaving
pores that reduce its strength. ACC Fly-ash based PPC has ingredients which react
with calcium hydroxide to form CSH gel, to provide additional strength, which
actually makes the concrete grow in strength over the years. It also produces less heat
of hydration and offers greater resistance to the attack of aggressive waters than
ACC Fly-ash based PPC can be used for all jobs in construction:-
ACC Fly-ash based PPC easily replaces OPC and provides additional advantages for
recommended for mass concreting work, and where soil conditions and the prevailing
Due to its inherent characteristics, ACC Fly-ash based PPC makes very corrosion
resistant concrete that is superior to concrete made with OPC. It is more impermeable
to oxygen, CO2, chlorides, etc. Leaching of alkalis is reduced and the alkaline
This is a slag-based blended cement that imparts strength and durability to all
reaction.
Increased serviceability with less deflection of members and micro cracks and
All these factors make for a strong, durable, and longer lasting construction. ACC
PSC benefits the structure, protects the environment by reducing CO2 emissions and
type of blended cement containing ground granulated blast furnace slag. Concrete
made with ACC PSC has a higher density than concrete made with OPC, and hence it
It can, therefore, be used for all purposes where OPC or PPC is used.
PRODUCT QUALITY
Product Development has always been an important activity at ACC, arising out of a
focus on quality and process improvement. It has been a constant partner, driving
Central Research Station (CRS) was established in Thane. The research complex now
renamed as ACC Thane Complex, spread over an area of 8000 sq m has modern labs
with the latest equipment and manned by highly qualified scientists and technologists
who carry out product development work in cement and allied fields.
ACC has effectively pledged its reputation as the market leader in the quality of
cement. Maintaining this lead calls for harnessing the resources and expertise of the
company - from applied research and production to marketing. Accordingly, all ACC
associated quality control and testing laboratories. Trained engineers, chemists and
technicians man these. The Central Laboratory at ACC Thane Complex is used as a
As a result of this focus on quality, ACC cement specifications exceed those set by
BIS by a wide margin. Today, all ACC cement plants have the ISO 9001 Quality
PIONEERING EFFORTS
ACC Ltd has pioneered the manufacturing of Portland cement in India. Portland Slag
cement, Portland Pozzolana cement, Oil well cement, Sulfate resistant cement etc. has
been by ACC. It has introduced the use of industrial wastes as raw material and fuel.
It is the only company to exploit low grade limestone for cement manufacture by
beneficiating it using the forth flotation process. By utilizing low grade limestone it
has contributed to the conservation of the mineral wealth of the country. A distinction
no other cement company has achieved. This can also be said, as it has its own large
ACC was the first company in India to put up one million tones
per annum capacity cement plants using indigenous technology. It was first time in
India that one of the Wet process cement plants of ACC was converted to semi wet
INTERNATIONAL RECOGNITION
The company in the operation of cement plant has gained international recognition
when it was called upon to operate a cement plant in Saudi Arabia and two plants in
Iraq under operation and management contracts. Due to the gulf war the contract with
Iraqi companies ceased to operate. The contract for the operation of the plant in Saudi
Arabia which has added one more modern high capacity production line recently has
been in force for nearly 25 years. Currently it is partnering one of the major
international consultants, the Blue Circle industries of UK in the total project
cement project of 2.5 million tones per annum capacity in Saudi Arabia. The geologist
of the company had undertaken geological survey and investigation assignments for
cement companies abroad. ACC has a joint venture with M/S. FKCC.(Fars and
The services are availed by many clients in India and abroad by a laboratory set up in
Thane near Bombay in the early 60’s which has grown into a premier industrial R&D
Institution. The total support is given by this institution to the operating units of the
company in the areas of processes, products and quality control. It has highly and
equipped and expertly manned laboratories and pilot plant facilities. The R&D
Division has also been active in product and process development in non cement areas
such as refractory, chemicals and advanced electronic materials. It has played a big
The company has played a significant part in making Indian Cement industry a
substantially pollution free industry. It has spent a large amount of money in installing
pollution control systems even in its not so economic production units such as its wet
process cement plants. The companies’ activities have always taken into consideration
the societal concerns in regard to protection of the environment. Its modern cement
plants incorporate state of the art pollution control equipment. The company’s
technical collaboration with Hamon Research Cottrell of United states for the
stress as much on pollution control as on reducing costs and maximizing outputs. The
norms set are better than statutory requirements and are comparable to the norms in
western countries. A special cell in the operations division focuses on all pollution
blast furnace slag and fly ash, the waste by – product of then steel and power
recycled in production processes. The project under study in this report also envisages
use of fly ash, a waste product from Thermal Power Stations, in the manufacture of
transporting cement over long distances. ACC has pioneered the carrying of bulk
cement in specially designed rail bulkers in India and is the only company to utilize
this mode of transport from its plant at Wadi to Kalamboloi near Mumbai in India.
ACC has tied up with M/S. Unozowa of Japan for the design and Technology transfer
of bulker tanks in order to supply environmentally friendly bulkers for road transport.
STRATEGIC PERSPECTIVE
ACC has decided to utilize the available funds to consolidate its present operation
with new energy efficient technologies in order to reduce costs and to enhance the
productive capacity of existing assets. Keeping in mind the state of the cement
industry ACC has came up with this strategy. The project and engineering division of
and commissioned a large number of plants for ACC and other clients in India and
abroad.
HISTORY
about 20 kms away from Chaibasa town. It was formally inaugurated on Nov.5, 1946,
by Sir Huge Dow, the then Governor of Bihar. Chaibasa Cement Works, an ISO-9001
and ISO-14001 certified unit of The Associated Cement Companies Ltd. The factory
District. At Jhinkpani the silence lies unbroken by the raucous cries of humanity, only
the rolling hills and verdant glades dotted with tiny huts listen to the hustle and bustle
of A.C.C. factory. It seems as through the primeval and modern were trying to
commune. The works has its own colony, hospital, sports club, small shopping
complex, schools, banks, post office. It is well connected with the world through
telephone and Internet. To cater to the need of nearby villagers such as health
services, skill development i.e. carpentry, stitching/embroidery for women for self-
manufactured by ACC at its own workshop and it was in January 1947 that the first
ton of cement was put out for sale. This is the first plant of its kind indigenously
designed by ACC, for manufacturing of Portland Slag Cement using the waste
product i.e. granulated slag of TISCO, Jamshedpur. Right from the inception of the
• Right from the inception of the factory this plant is producing Slag based Cement
The main causes for the establishment of the industry in this particular location were:-
1. Availability of Raw Material such as – Limestone from own mines, Slag from
2. There were only few industries in this region at that time. They were –
Tata Group – TISCO (Now Tata Steel) & TELCO (Now Tata Motors).
predominantly Tribal.
villages.
farm.
Agricultural implements like sprayers, dusters & paddy thresher are provided
surrounding villages.
These are the benefits provided by the Chaibasa cement plant to the society
and economy.
IT- INFRASTRUCTURE
ACC Limited Chaibasa Cement Works is working on SAP platform, means System
a. FICO
b. MM (Material Management)
d. PP (Production Planning)
e. PM (Planned Maintenance)
f. PS (Project System)
INFRASTRUCTURAL FACILITIES
LOCATION
The plant is located about 150 km from Ranchi airport and 2.2 km from Jhinkpani
railway station. The Paradeep seaport is 332 km from plant. Plant gets coal from
MCL, ECL, SECL (washery coal) and coal fines from steel industry. The national
highway NH-75E an inter state road is within 1 km from the plant. The general terrain
of the area is gently hilly. Chaibasa has a population of 1.5 lakh. The school up to 12 th
standard and dispensary is within the premises of the plant. There is college facility
available 16-18 km away from plant. The altitude is 270.345 meters above mean sea
level.
CLIMATE
and in winter, it goes as low as 4-5 c. The summer period is April & May and rainy
season is from June to September (traces in January, February, April, and November).
The annual rainfall is 1500-1700 mm. The maximum relative humidity is 70% and
minimum is 60%. There is no history of earthquake and flood. The soil consists of
WATER
The source of water is river, reservoir created in Gunmala and abandoned quarry. The
water is pumped from these sources to the plant. The water required clinker plant
excluding colony will be 925 m3 / day. Water is required for filter wash, crusher
dryer/ball mill bearing cooling and there will be loss of 15% moisture in cake with
flue gases. In present semi – wet process plant, 36% slurry is fed to kiln and water lost
with flue gas is 805 m3 / day. Water requirement for 20 mw power plant is
approximately 2800 m3 / day. There are 635 quarters in colony. Taking average 4
persons per house and 200 liters/day/person, water required is 510 m3 / day.
POWER
Present power consumption is 15-16 Mw. The source of power is sub station 30 km
away from plant at Kendposhi which receives 132 KV away from JSEB and steps it
down to 33 kV. Power is drawn from existing 15 Mw captive power plants and 6 Mw
captive power plant act as stand by. Presently cost of power is Rs. 2.49 /kWh
TRANSPORT
Limestone is transported from quarry through 2.5 KM long pipe conveyer. Here 1000
mm width conveyer belt is folded in shape of pipe with the help of idlers; it is then
pulled by heavy motors. The cement transport is by rail. The coal transport is by rail
only. Plant owns one rail loco. There is broad gage railway track (2.2 km) from rail
station to the existing plan. The track from station to factory yard is 2.2 km. The
railway track inside the plant is 800m long. There is no. of tracks in the plant area.
The roads within the plant are in good condition. Public transport is well established.
FUEL
Plant uses coal from Mahanadi Coalfields Limited (MCL), Brijrajnagar /Eastern
Washery Present coal consumption is 23.5% semi wet, and 76.5% dry combined
process with heat consumption of 750 kcal/kg cl, coal consumption will be 18.5%
OBJECTIVE OF PROJECT
NEED OF STUDY:
During my first week of visit in different department of plant I have collected many
information about different problems which are plant was facing and other one
increasing cost of production per ton of cement. Finally I have decided to select “Cost
PRIMARY OBJECTIVES:
SECONDARY OBJECTIVE:
1. To analyse data of different element of variable cost of plant with the help of
This project has helped the finance manager and cost accountant of plant to know the
plant level.
CHAPTER-IV
RESEARCH METHODOLOGY
1. Cost sheet will be useful for price restructuring. Head office has been
decided profit margin and thereby decides the selling price. It is observed
that maintenance cost of plant is increasing. This analysis will help the
2. This cost analysis will help the plant manager to understand expenditure in
3. Some data provided by the Finance Manager form his data base.
company.
CHAPTER-V
DATA ANALYSIS
Objectives of HARP
HARP Principals
Understandability
Reliability
Comparability
COST CENTER:
The activities and costs incurred in the process of making cement are collected in
This lesson has been explained to me the cost centers are specified for clinker and
cement production so that one will be able to identify to which center the cost of
plant. These are generally not directly involved in the production process (e.g.
1) Primary cost
2) Secondary costs
Cost Center Structure
Cement Grinding
1) Primary costs
2) Secondary costs
process)
Main cost center:
Main cost centers reflect the main production, distribution and cost flows of a
plant following the main component of a product from the beginning to the
finished product.
included in auxiliary cost centers forms the infrastructure of a plant and is not
The individual types of cost are included in the respective auxiliary cost
centers. The sum of these individual costs is thereafter allocated as a total into
thereafter allocated as a total into two types of costs in the respective main
cost centers:
main cost centers even after allocation of auxiliary cost centers and the
production process.
Pre-process cost centers flow into the respective main cost centers as follows:
Allocation
to all
receiving
cost centers
Pre-process cost centers are with the exception of power generation- directly
linked to one main cost center mainly consuming the respective products.
The costs from pre-process cost center are not allocated, aggregated on a
single line to the respective main cost center; they are allocated to each
The exception: the cost of the power generation pre-process cost center ( for
own power generation plants only) are allocated directly through the type of
Allocation
to all
receiving
cost centers
cost center by equipment and by employees, the costs can be allocated to the
cost center where the activity mainly takes place e.g. grinding coal and raw
cement grinding.
Grinding plant allocate the auxiliary cost centers 100 % to ‘cement grinding’
Note: If an auxiliary activity is assigned only to one main cost center than these costs
the cost of supervisors (for confidentiality reasons) which have to be charged first to
auxiliary cost center and are thereafter allocated using the 70 % / 30 % rule.
All equipment for transport and feed of material into storage, as well as the storage
All equipment for reclaiming and extraction from the storage belong to the next cost
center.
At a plant, the costs related to the storage of inventories belong to the cost center that
produces the inventory as output. The physical location of the stockpile is irrelevant.
Raw Material Extraction' versus 'Raw Material Preparation
All the activities related to extracting and moving the raw material (e.g. limestone)
from the quarry until the bin of the crusher belong to the main cost center 'Raw
Material Extraction'. Subsequent activities belong to the main cost center 'Raw
Material Preparation'.
All the activities related to moving the prepared raw material (e.g. limestone after
crushing) to the related storage in the crushing area, including all the expenditures
related to the storage thereof, belong to the 'Raw Material Preparation' main cost
center.
All the activities related to moving the prepared raw material from the stockpile or
intermediate storage to the mill area and the mill feed system belong to the 'Raw Meal
All the activities related to moving the raw meal to the related storage in the
homogenization and storage thereof, belong to the 'Raw Meal Preparation' main cost
center.
All the activities related to extracting the raw meal from the homogenizing silo or
slurry tanks and moving it to the kiln feed system belong to the 'Clinker Production'
All the activities related to moving the clinker to the clinker storage including all the
costs related to the storage belong to the 'Clinker Production' main cost center.
All the activities related to extracting the clinker from the clinker storage and moving
it to the cement mill feed system belong to the 'Cement Grinding' main cost center.
The quantity of raw material mined/extracted and transported from the quarry to raw
Calculation:
Raw material produced in the raw material preparation process, for example crushing
and homogenizing.
Calculation:
Measured with: Weigh feeders or similar devices, truck load count or front
Raw meal produced in the raw meal preparation process, for example grinding mills
of all production units in operation. The quantity calculated contains all raw meal
types.
Calculation:
For all processes (e.g. dry, semi dry, semi wet, wet) the water content of the
The raw meal produced is determined by raw material fed to the system
Actual quantity of clinker production process, for instance kilns of all operating
production units. The quantity accounted comprises all clinker types and the quantity
clinker ratio, then this factor has to be verified periodically by comparing the
inventories of the raw meal and the clinker volume feed to the clinker storage.
This indicator corresponds to the quantity of cement produced with grinding mills and
Mixer / Blender Vol. added (if applicable) + Cement Grinding Volume (for mill 1) (t)
Cement Grinding Volume (for mill 1) (t) = Clinker input dry (t) + Set regulator (e.g.
gypsum) (dry) (t) + Minor additional constituents (e.g., cement kiln dust) (t) +
The auxiliary cost centers provide the organizational body and infrastructure
equipment for the clinker and cement production process. They are not directly
Note that the respective auxiliary personnel should be charged to the appropriate
The types of auxiliary cost centers may differ from one company to another; however,
at least one auxiliary cost center must be identified for each Group company.
Pre-Process Cost Centers:
process; and
All Group company cement plants are required to have the following minimum set of
a. Power Generation
Costs incurred in generating electrical power, for companies with own power
plant only.
Note that where a Group company has constructed a power plant but it is owned by
the state authorities / third parties, and the Group Company has to pay for power
usage, this cost of usage does not belong to this pre-process cost center, but has to be
Revenue from selling electrical energy to third parties is included in this pre-process
for consumption in the raw mill as part of raw material preparation and usually are in
the form of an industry by-product (e.g. contaminated soil, dry sludge, etc.)
At cement plant this includes the activities of unloading, internal transporting, sorting,
Materials that correct the chemical composition of raw materials to make the
Correctives include iron oxide, iron ore, sand, silica, high-grade limestone
(when used as a corrective), kaolin, bauxite, magnetite and pyrite ash, etc.
Correctives do NOT include the main siliceous and arcillaceous materials (limestone,
sorting, feeding to the burner pipe) of traditional fuels for consumption in the
production of clinker.
Examples of traditional fuels are coal, pet coke, liquid fuels (heavy oils, light
Costs incurred in the preparation and handling of fuels used to replace the
traditional fuels for consumption in the production of clinker. Alternative fuels are
normally:
At cement plant this cost center includes the activities of unloading, internal
transporting, sorting, shredding and feeding to the burner pipe. At AFR unit, this
Gypsum and additives are materials fed into the cement grinding and pre-
the plant) are charged through inventory consumption directly to the finished
product. This procedure is necessary because the costs of the 'Cement Grinding' main
cost center are allocated to the different cement types by kWh and this key would not
clinker.
These include fly ash, pozzolane, ground granulated blast furnace slag
(GGBFS), granulated blast furnace slag (GBFS), air cooled blast furnace slag
Note that the components of the cost relating to the material itself (including the costs
to transport it to the plant) are charged directly through inventory consumption to the
finished product. This procedure is necessary because the costs of the 'Cement
Grinding' main cost center is allocated to the different cement types by kWh and this
Cash costs mainly disclose the actual flows (cash) in and flows (cash) out of a
cost center. Cash cost is the sum of fixed and variable costs at cost center
level.
Fixed versus variable costs:
Maintenance expenses include all the expenditures incurred in the activities of:
distribution processes
A. CLINKER PRODUCTION
Total Quantity of
(in tonnes)(X)
2006 1052447 - -
2007 1100026 47579 4.52
1200000 1100026 5
1052447
4.52 4.5
1000000
Percentage Increases
4
800000 3.5
3 X
Tonnes
600000 2.5 Y
2 Z
400000 1.5
200000 1
47579 0.5
0 0
2006 2007
Year
FINDINGS:
1. Total quantity of clinker production is growing in year 2007 w.r.t. year 2006.
2006.
B. CEMENT PRODUCTION
Total Quantity of % Increase
Year Difference (Y)
Production(Tonnes) (X) (Z)
2006 673357 - -
2007 719457 46100 6.85
800000 719457 8
673357
700000 6.85 7
Percentage Increases
600000 6
500000 5 X
Tonnes
400000 4 Y
300000 3 Z
200000 2
100000 46100 1
0 0
2006 2007
Year
FINDINGS:
1. Total quantity of cement production is growing in year 2007 w.r.t. year 2006.
C. CEMENT DESPATCHES
Total Quantity of Cement % Increase
Year Difference (Y)
Despatches (Tonnes) (X) (Z)
2006 666473 - -
2007 716349 49876 7.48
800000 716349 8
666473 7.48
700000 7
Percentage Increases
600000 6
500000 5 X
Tonnes
400000 4 Y
300000 3 Z
200000 2
100000 49876 1
0 0
2006 2007
Year
FINDINGS:
2006.
1. RAW MATERIALS
(X)
2006 299.97 - -
2007 315.34 15.37 5.12
350 315.34 6
299.97
300 5.12 5
Percentage Increases
250
4
X
200
Rs
3 Y
150
Z
2
100
50 1
15.37
0 0
2006 2007
Year
FINDINGS:
a. Cost per tonne of cement in year 2007 increases w.r.t. year 2006.
b. Percentage increase in cost per tonne of cement is 5.12 in year 2007 w.r.t. year
2006.
REASON:
Rate per tonne of Bauxite, Iron Ore, and Imported Gypsum in year 2007 is higher
(X)
2006 258.25 - -
2007 264.63 6.38 2.47
300 3
258.25 264.63
250 2.47 2.5
Percentage Increases
200 2
X
Rs
150 1.5 Y
Z
100 1
50 0.5
6.38
0 0
2006 2007
Year
FINDINGS:
1. Cost per tonne of cement increases in year 2007 w.r.t. year 2006.
2. Percentage increase of cost per tonne in year 2007 is 2.47 w.r.t. year 2006.
REASON:
Rate per tonne of Indian Coal and Imported Coal in year 2007 is higher than
year 2006.
1.75 1.8
150 1.6
Percentage Decreases
1.4
100 1.2 X
Rs
1 Y
50 0.8 Z
0.6
0 0.4
2006 2007-3.24 0.2
-50 0
Year
FINDINGS:
1. Power cost per tonne of cement is decreasing in year 2007 w.r.t. year 2006.
2. Percentage decrease of Power cost per tonne of cement is 1.75 in year 2007
REASON:
Power cost per tonne of cement is decreasing due to change in usage of power
by 1.19 % in Clinker and 4.74 % in Grinding and also reduction in average power
cost.
4. WEAR PARTS
Cost per tonne –
(X)
2006 15.69 - -
2007 45.29 29.6 188.66
50 200
45.29 188.66
45 180
40 160
Percentage Increases
35 140
29.6
30 120 X
Rs
25 100 Y
20 15.69 80 Z
15 60
10 40
5 20
0 0
2006 2007
Year
FINDINGS:
1. Bar chart of wear parts cost per tonne of cement is increasing in year 2007
2. Percentage increase of wear parts cost per tonne of cement is 188.66 in year
35 14
29.26 12.63
30 12
25.98
Percentage Increases
25 10
20 8 X
Rs
Y
15 6 Z
10 4
5 3.28 2
0 0
2006 2007
Year
FINDINGS:
1. Cost per tonne of cement is increasing in year 2007 w.r.t. year 2006.
2. Percentage increase of cost per tonne of cement is 12.63 in year 2007 w.r.t.
year 2006.
50 9
43.21
39.89 8
40 7.68
7
Percentage Decreases
30 6
5 X
Rs
20 Y
4
Z
10 3
2
0
2006 2007 1
-3.32
-10 0
Year
FINDINGS:
1. Cost per tonne of cement is decreasing in year 2007 w.r.t. year 2006.
2. Percentage decrease of cost per tonne of cement is 7.68 in year 2007 w.r.t.
year 2006.
1000 927.2 12
900 835.97 10.91
10
800
Percentage Increases
700
8
600 X
Rs
500 6 Y
400 Z
4
300
200
91.23 2
100
0 0
2006 2007
Year
FINDINGS:
1. Cost per tonne of cement is increasing in year 2007 w.r.t. year 2006.
2. Percentage increase of cost per tonne of cement is 10.91 in year 2007 w.r.t.
year 2006.
340 1000
320 950
900
300 850
280 800
260 750
240 700
Percentage change
650
220 600
200 550
180 500
Rs
450
160 400
140 350
120 300
250
100 200
80 150
60 100
40 50
0
20 -50
0 -100
A B C D E F
All element of Variable cash cost
A – Raw Materials
D – Wear Parts
FINDINGS:
Total variable cash cost per tonne of cement increases in year 2007 w.r.t. year
2006 due to increase in cost per tonne of cement of Raw Materials, Fuels/Thermal
5000 4.5
4327.84
4500 4150.56 4.1 4
4000
3.5
3500
Percentage Decreases
3
3000
2500 2.5 X
Lakhs
Y
2000 2 Z
1500
1.5
1000
1
500
0 0.5
2006 2007
-177.28
-500 0
Year
FINDINGS:
2. Percentage decrease of fixed cost in year 2007 is 4.1 w.r.t. year 2006.
2100 1000
1950 950
1800 900
1650 850
1500 800
750
1350
700
1200 650
1050
Percentage change
600
900 550
Rs Lakhs
750 500
600 450
450 400
300 350
150 300
0 250
200
-150 A B C D E F G H I J K 150
-300 100
-450 50
-600 0
-750 -50
-900 -100
All element of Fixed cost
I - Maintenance Material –M
Total Fixed cash cost decreases in year 2007 w.r.t year 2006 due to decrease of cost in
350 320.82 14
150 8 X
Rs
Y
100 6 Z
50
4
0
2006 2007 2
-50
-40.4
-100 0
Year
FINDINGS:
1. Cost per tonne of cement decreases in year 2007 w.r.t. year 2006.
2. Percentage decrease of cost per tonne of cement in year 2007 is 12.59 w.r.t.
year 2006.
CASH COST = VARIABLE CASH COST + FIXED CASH COST
CASH COST
(X)
2006 1156.80 - -
2007 1207.62 50.82 4.39
1400 5
1207.62 4.5
1156.8 4.39
1200
4
Percentage Increases
1000 3.5
3 X
800
Rs
2.5 Y
600 Z
2
400 1.5
1
200
50.82 0.5
0 0
2006 2007
Year
FINDINGS:
1. Cost per tonne of cement increases in year 2007 w.r.t. year 2006.
ACTUAL COST
Cost Per Tonne-
(X)
2006 1157.36 - -
2007 1199.44 42.08 3.64
1400 4
1157.36 1199.44 3.64
1200 3.5
Percentage Increases
3
1000
2.5
800 X
Rs
2 Y
600
1.5 Z
400
1
200 0.5
42.08
0 0
2006 2007
Year
FINDINGS:
1. Cost per tonne of cement increases in year 2007 w.r.t. year 2006.
2. Percentage increase of cost per tonne is 3.64 in year 2007 w.r.t. year 2006.
(X)
2006 1283.47 - -
2007 1445.23 161.76 12.60
1600 14
1445.23
12.6
1400 1283.47 12
1200
Percentage Increases
10
1000
8 X
Rs
800 Y
6 Z
600
4
400
161.76 2
200
0 0
2006 2007
Year
FINDINGS:
1. Cost per tonne of cement increases in year 2007 w.r.t. year 2006.
2. Percentage increase of cost per tonne is 12.6 in year 2007 w.r.t. year 2006.
PRICE & USAGE DATA
2007
Actual Budget Cumulative
Raw Material
Limestone 0.00
Purchased
Limestone
consumption as
a %age of
clinker
production
Fuel & Indian Coal - 3379.64 2645.00 1815.38
Coal(Price
Rs/Tonne)
Alternate Fuel
( Price
Rs./Tonne)
Weighted average
Fuel(Price
Alternate Fuel
CV(NOW) - Wt.
TGs ( Kg per
kwh generated)
Sister Works
Gypsum Rs/Tonne)
Imported(Price
Rs./Tonne) 1857.09
Usage % 4.77% 4.50% 4.65
Slag (Avg) Price Rs/Tonne 501.05 593.71 578.13
Usage % 33.12% 34.87% 34.55
Fly Ash.
(including Fly
( including
Distributed –
as a %age of
Power generated
(based on net
Year 2007
Description Unit Actual Budget
Clinker Production Tons 1100026 1204500
Cement Production " 719457 856000
Cement Despatches " 716349 856000
Cost Per
Tonne-
(Note: - Cost of packing, storage, handling, transportation, taxes and levies, profits
etc. are to be added to fix MRP which is done by the head office.)
CHAIBASA
31-Dec-06 ACC R
E
V
I
Consolidat S
ed Group E
Company D
In
dia
JANUA
Clinker and RY /
Cement - DECEM
Cost per Ton BER
(15 A) 2006
Sub-Segment:
Clink
er
and
Cem
Support Process: ent
n
/
a
T T C
ot ot e
T
al al m
ot
Cl Cl e
al
in in n
Raw Clink Pr
Raw Raw k k t
Materi er od
Material Meal er er G
al Prod uc
Extractio Preparati P P ri
Prepar uctio tio
n on ro ro n
ation n n
d d i
C
u u d
os
ct ct i
t
io io n
n n g
C
o
s
t
C
C P C T o T
o e C o T ot s ot
s r o s ot al t al
t st t al C P C Tot
C P C T C P P C o e os al
o e o o o e e o st r t Am
s r s n s r r st P T P oun
t T t t T T P er o er t of
P o P - P o o er T n T Cos
e n C e e n n T o on t
C r - o r C C r - C - o n- C - - Rs/
o T C s T l o T C o C n- C o C C Tho
s o li t o i s o li s li Cl e s e e usa
t n n n n t n n t n in m t m m nds
Variable Cash Cost
Raw Materials 0 0 0 0 0 0 6 3 6 0 0 6 3 1 2 29 242
3 4 0. 0. 3. 7 6 9. 853
7 . 7 7 9 9 6 97
1 8 4 1 .
3 0
7 7 6 3
4 4
8 6 4 2
4 0 6 5 0
9 . 0. 7. 3 . 25
Fuels/Thermal 5 7 7 6 9 5 8. 485
Energy (Kiln) 0 0 0 0 0 0 0 0 0 3 9 9 7 0 8 25 343
1 1
4 8 3 1 0
3 . . 3. 7. 07
3 1 7 7 6 .6 143
Diesel/Gasoline 0 7 3 0 0 0 0 0 0 0 0 3 8 0 0 8 30
1 1 1
1 1 3 2 1 7 0
1 0 1 0 5 0 3 2 6 9 4 8 0 4
4 . . 3 . . 6 . 3. 5 . 4. 0. 1 . 18
Electrical Energy 5 8 3 1 9 0 8 0 5 3 7 6 9 1 1 5. 222
Variable 3 3 9 0 8 4 5 2 1 5 3 7 0 4 3 03 097
1
2 1 7 6 0 7 0
7 . 2. 0 . 5. 0 . 15
2 4 5 6 7 9. 2 6 4 .6 168
Wear Parts M0 0 0 0 0 0 2 9 9 5 1 3 0 3 9 9 50
1 1 1 1
3 7 2 1 0 2 8
1 . . 2. 7. 7 . 25
Production and 8 5 6 6 0 4 9 .9 259
Distribution Material 5 2 3 0 0 0 0 0 0 0 0 3 6 1 2 8 26
0
0. 00
0 .0
Packing Material 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0
Labour Expenses 1 . 0. 0. . 00
Subcontracted 1 1 1 0 4 0 .1
Variable 0 0 0 0 0 0 0 0 0 4 1 1 6 9 7 3 163
Labour Expenses 0 0
Maintenance . 0. 0. 00
Subcontracted 6 0 0 0 .0
Variable M0 0 0 0 0 0 0 0 0 2 6 6 3 0 0 3 62
0
0. 00
Third Party 0 .0
Transportation 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0
0. 00
Outsourced Quarry 0 .0
Activities 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
8 7
0 7 7 4
6 . 7. 3. 43
Mining Concessions 5 4 2 2 2 .2 806
and Royalties 7 6 7 0 0 0 0 0 0 0 0 7 1 0 0 1 57
1 1 6 2 4
0 6 0 1 1 7 3 2 5 7 4 6 0
9 2 5 0 5 0 0 8 8 9 7 3 9 0
6 . . 3 . . 1 . 6 7 7 9. 5. 4 . 83 108
2 5 0 1 9 0 2 3 6. 2 . 2 7 9 2 5. 828
Variable Cash Cost 5 2 2 0 8 4 4 8 8 9 4 6 6 3 2 98 1
Fixed Cash Cost
1 1
0 0 0 0 0 1 0 1 0 5 8
1 . . 8 . . 2 . 0. 0 . 1. 6. 6 . 14
Electrical Energy 1 0 1 3 4 8 9 1 2 5 5 7 5 7 4 .9 179
Fixed 8 7 1 5 8 1 9 6 8 9 1 1 5 9 3 8 90
1 1 5 5 2 3
0 6 0 2 1 2 1 0 4 2 6 3 6 9
9 . . 0 . . 0 . 7 . 5. 6. 4 . 75
Labour Expenses 4 2 4 8 2 0 4 5 3 0 5 6 8 3 .9 953
Own 7 4 9 3 1 3 7 7 1 7 1 3 4 7 4 8 01
1 1
5 2 4 0 0 0 5 4 2 1 4
Labour Expenses 0 . . 1 . . 7 . 0. 2 . 0. 1. 7 18
Subcontracted 1 8 8 4 0 1 4 4 7 0 4 1 2 1 .2 258
Fixed 9 6 1 4 8 4 0 1 1 4 5 1 5 4 7 5 21
1 0 1 0 0 6 6 0 3 5
2 . . 6 0 . 4 . 0. 4 . 8. 4. 3 . 09
Labour Expenses 1 6 1 8 . 6 7 2 4 9 1 4 7 8 0 .7 122
Maintenance Own M2 9 6 8 4 7 1 6 5 5 7 5 3 3 2 5 49
1
Labour Expenses 1 0 1 0 0 0 5 1 0 5 8
Maintenance 1 . . 4 . . 7 . 0. 7 7. 9. 4 . 17
Subcontracted 5 6 1 7 2 4 0 3 6 8 1 2 6 7 1 .7 235
Fixed M9 6 1 9 8 7 1 8 7 6 5 5 5 4 3 8 99
0 3 5
0. 7 . 05
Other Personnel 0 1 5 .5 371
Expenses 0 0 0 0 0 0 0 0 0 0 0 0 0 2 1 1 2
0
0. 00
Third Party 0 .0
Services 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
2 1 2 0 0 0 2 2 0 1 2
Third Party 3 . . 4 . . . 0. 9 . 5. 3. 4 . 05
Services 8 3 2 8 2 4 5 0 0 6 8 6 1 0 0 .2 728
Maintenance M1 6 8 0 8 7 2 3 5 7 2 2 4 8 9 3 8
8 4 7 1 1 5 5 1 2 3
3 7 9 6 5 8 4 5 2 5 8 3 4
0 . . 3 9 . 7 . 8. 2 . 6. 7. 2 . 12
Maintenance 5 3 5 8 . 9 4 7 3 3 4 3 4 4 5 1. 186
Material M8 7 7 6 5 6 0 8 3 3 8 4 3 7 2 95 664
0 0 0 0 1 1 1 1 0 5 7
3 . . 1 . . 9 . 1. 6 . 3. 2. 1 . 09
6 2 3 8 1 1 2 0 8 5 5 9 2 1 5 .7 924
Assets Charged Off 4 1 5 4 1 8 3 5 3 6 7 3 0 3 9 9 0
4 3 1 2
0 8 3 2 7 5
6 . 8. 1. 4 . 47
Other Cost Center 4 6 6 6 2 8 .4 580
Expenses 0 0 0 0 0 0 0 0 0 9 2 2 0 1 7 7 70
- - - - -
5 4 - 0 2 3 -
0 . 4. 2. 1 . 05 -
By-Products and 0 7 7 6 4 1 .8 715
other Revenues 0 0 0 0 0 0 0 0 0 5 6 6 6 5 9 5 0
Fixed Cash Cost 1 5 9 2 1 2 1 7 1 1 1 3 1 9 1 32 432
0 9 9 1 2 0 3 . 3. 9 8 2 8 4 4 0. 784
4 8 8 0
2 . . 2 . . 9 7 . 0. 4 .
5 4 8 7 3 7 7 6 3 8 8 2. 5 9 3
8 6 8 9 4 3 3 4 2 1 7 8 1 3 1 82
2 1 8 7 1 3 5
1 2 2 3 1 3 8 4 2 8 1 6 6 4
3 1 0 1 8 0 4 6 8 7 6 0 1 3 0 11
8 . 4 5 . . 0 . 0. 5 . 2. 6. 9 . 56 152
8 9 . 8 3 7 9 0 1 1 2 0 2 8 5 .8 106
Cash Cost 3 8 9 9 2 7 7 2 2 0 7 6 7 6 3 0 5
0
0. 00
Clinker Recd. From 0 .0
S.W. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0
0. 00
Provision/Deferral 0 .0
for Wear Parts M0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0
Provision/Deferral 0. 00
for Absorption of 0 .0
Fixed Costs 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1 0
0 0 0. 00
Other Provision and 4 . 5 .5 104
Write-Offs 9 6 1 0 0 0 0 0 0 0 0 1 6 0 0 6 9
1 0
0 0 0. 00
4 . 5 .5 104
Sub Total: 9 6 1 0 0 0 0 0 0 0 0 1 6 0 0 6 9
2 1 8 7 1 3 5
1 2 2 3 1 3 8 4 2 8 1 6 6 4
4 2 0 1 8 0 4 6 8 7 6 0 1 3 0 11
9 . 5 5 . . 0 . 0. 5 . 3. 6. 9 . 57 152
3 5 . 8 3 7 9 0 1 1 2 0 8 8 5 .3 211
Actual Cost 2 8 9 9 2 7 7 2 2 0 7 6 3 6 3 6 4
1 1 1 1 4 2 9 1 2 3
Depreciation and 5 9 5 5 8 5 0 1 3 4 8 5 8 5 7
Amortization of 9 . . 4 . . 1 . 8. 1 9 8. 8. 4 . 12
Long-Term 0 0 2 7 9 0 4 9 2 9 . 0 3 0 7 6. 191
Operating Assets 8 7 4 2 7 7 2 7 4 8 5 5 8 5 3 11 125
2 1 2 1 9 8 1 3 5
3 3 2 4 2 4 2 6 1 2 7 2 7 8 7
0 1 1 7 7 5 4 7 1 1 5 6 0 9 8 12
8 . . 0 . . 2 . 8. 7 . 1. 5. 3 . 83 171
Cost of Goods 4 6 1 6 2 8 3 9 3 0 7 1 2 9 2 .4 323
Produced 0 5 4 1 9 4 9 9 6 8 7 1 1 1 6 7 9
5
1 1 1 1 1 8
7 7 8 0 0 8 6
5 2 2 5 5 5 7 12
3 4 7 2 2 2 3 61
4 3 0 4 4 8. 3 88
1 8 2 4 4 3 5 5.
Production Tons 0 5 0 0 9 0 0 9 0 0 7 7 6 0 7 36 0
Factors: 0 1 0 0 1 0 0 1 0 0 0 0 0 0 0 00 0
. . .
6 6 7
7 7 4 0.
9 9 0 5 .5
7 7 4 6 6
8 5 8 1 1 1 1 8 8 1 1 4 6
7 0 4 8 0 7 2 6 1 7 3 9 1 0 0
8 . . 0 . . 6 . 2. 6 . 7. 0. 5 . 17
Maintenance Cash 1 0 1 3 4 5 8 9 0 0 2 0 1 7 2 0. 246
Cost 0 8 2 3 6 7 6 4 9 8 4 2 7 5 5 42 712
0
0. 00
Provision/Deferral 0 .0
for Wear Parts 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
8 5 8 1 1 1 1 8 8 1 1 4 6
7 0 4 8 0 7 2 6 1 7 3 9 1 0 0
8 . . 0 . . 6 . 2. 6 . 7. 0. 5 . 17
1 0 1 3 4 5 8 9 0 0 2 0 1 7 2 0. 246
Maintenance Cost 0 8 2 3 6 7 6 4 9 8 4 2 7 5 5 42 712
Pag
e
No.:
-
77-
A
ACTUAL JAN / DEC 2007 CHA
ACC Consolidated Group Company
India
Clinker and Cement - Cost per Ton (15 A)
Sub-Segment:
Support Process: Clinker and Cement
n/a
REASON FOR VARAINCE
production of PPC.
Fuels/Thermal Energy (Kiln) Price Avg. Coal price for kiln is higher by
CV.
Diesel/Gasoline Price
As per market rate.
Usages
kiln.
Material
Subcontracted Variable
Maintenance Subcontracted
Variable
Royalties
Labour Expenses
Fixed /Despatches.
Maintenance party.
crores.
Revenues
CHAPTER-VI
FINDINGS
1. After analysis of variable cost and fixed cost of plant, I got the knowledge
about how costing has done by cost accountant in plant, detail process of cost
cost centers.
2. After analysing of variable cost of plant I got the following findings about
i. Raw Material cost per tonne of cement in year 2007 increases w.r.t.
year 2006. Percentage increase of cost per ton of cement is 5.12 in year
ii. Fuels/Thermal energy Cost per tonne of cement increases in year 2007
w.r.t. year 2006. Percentage increase of cost per tonne in year 2007 is
year 2007 w.r.t. year 2006. Percentage decrease of Power cost per
iv. Percentage increase of wear parts cost per tonne of cement is 188.66 in
Budgeted for last year along with reasons of difference of cost involve in
variable cost.
CHAPTER-VII
Suggestions:
increasing in year 2007 w.r.t. year 2006. So source of gypsum should be near
to the plant that will help to reduce cost per ton of cement manufacturing.
one utilising in plant is very high quality is more than requirement of plant.
equipment Kiln has changed in year 2005 to improved dry process Kiln. That
will required more maintenance cost in year 2007 w.r.t year 2006.
Conclusions:
Cost Analysis is a broad topic and most vital activity in any company. During my
understanding of cost concept in this plant, I have visited all departments and got
valuable information regarding cost. In this project I have done comparative analysis
of main element of Variable Cash Cost, overall Fixed Cost, Cost of Goods Produced
per tonne of cement, Total quantity of clinker production, cement production and
cement despatches. Total quantity of clinker production is growing in year 2007 w.r.t.
year 2006. and percentage growth of clinker production is increasing in year 2007
w.r.t. year 2006. Total quantity of cement production is growing in year 2007 w.r.t.
year 2006. It means plant capacity is increases successive year and Percentage
increase in year 2007 is 6.85 w.r.t. year 2006. Total cement despatches increases in
year 2007 w.r.t. year 2006 and percentage increase of cement despatches is 7.48 in
year 2007 w.r.t. year 2006. Total variable cash cost per tonne of cement increases in
year 2007 w.r.t. year 2006 due to increase in cost per tonne of cement of Raw
Materials, Fuels/Thermal Energy (kiln), Wear Parts and Production and Distribution
Material. Total Fixed cash cost decreases in year 2007 w.r.t year 2006 due to decrease
Own, Labour Expenses Maintenance Subcontracted Fixed and Other Cost Center
LIMITATION OF PROJECTS
itself that was the main constraint for getting knowledge about costing.
BIBLIOGRAPHY
Mannual