Download as pdf or txt
Download as pdf or txt
You are on page 1of 104

DAN HOTEL PROJECT

FPS
Technical Specifications

Prepared By

Larsen & Toubro Limited


MEP DEPARTMENT
DAN HOTEL PROJECT SITE
NO 1&2, EOIZ INDUSTRIAL AREA,
ITPL MAIN ROAD, NEAR ITPL,
BANGALORE-66.

Client/Owner Consultant Consultant


DAN H DAN HOSPITALITY INDIA PVT LTD JONES LANG LASALLE RSP DESIGN CONSULTANTS INDIA PVT
ITPL MAIN ROAD Level-3 Concorde, 30 Museum Road,
WHITEFIELD #24 UB City, Bangalore-1
BANGA BANGALORE-66 Bangalore-1
DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

TECHNICAL SPECIFICATIONS
FOR
FIRE PROTECTION SYSTEMS

Annexure [6] Page 527 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

CONTENTS

SECTION CLAUSE DESCRIPTION


1 INTENT OF SPECIFICATION
2 DESIGN CONSIDERATION
3 DESIGN PHILOSOPHY
4 APPLICABLE CODES AND STANDARDS
5 SYSTEM DESCRIPTION
6 SCOPE OF WORK
7 EQUIPMENT SPECIFICATIONS
A FIRE HYDRANT SYSTEM
2.0 PIPING
3.0 VALVES
4.0 EXTERNAL HYDRANTS
5.0 HOSE REEL
6.0 LANDING VALVES AND HOSE PIPES
7.0 FIRE BRIGADE INLET CONNECTION
8.0 AIR RELEASE VALVE
9.0 DRAIN VALVE
10.0 VALVE CHAMBERS
11.0 PIPE PROTECTION ABOVE GROUND
12.0 PIPE PROTECTION UNDER GROUND
13.0 TESTS AT SITE
13.1 PIPING
13.2 PUMPS
14.0 PUMPS AND ACCESSORIES
15.0 DIESEL ENGINE
B AUTOMATIC SPRINKLER SYSTEM
C ELECTRICAL WORKS
D FIRE EXTINGUISHERS
E SINAGES
8 TECHNICAL DATA SHEETS
9 MAKE OF EQUIPMENT

Annexure [6] Page 528 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

SECTION – 1 INTENT OF SPECIFICATION

This specification is intended to cover design, residual, engineering,


manufacture, test and inspection at works, delivery to site properly packed for
transportation, erection, testing, commissioning, performance demonstration at
site and handing over to purchaser of Fire Protection System as indicated in the
schedule of Requirement and scope of work and as required for reliable and
effective fire protection at DAN HOTEL, BANGALORE.

1.1 This specification also includes complete earthwork, i.e. excavation and back
filling for the entire buried piping for hydrant and water spray system.

1.2 The specification also includes the supply of erection and commissioning of
spares as specified and special tools and tackles.

1.3 This specification also makes it obligatory for the contractor for arranging and
obtaining necessary clearance / approval from all Local / statutory authorities.

1.4 It is not the intent to completely specify all the details of design and construction
herein. Never the less the equipment and installation shall confirm to high
standard of engineering, design, and workmanship in all respect and shall be
capable of performing continuous satisfactory operation and acceptable to the
purchaser as well as to the various statutory authorities. In case of any
violation of the above contract, the purchaser reserves the right to change /
reject / modify the equipment / system during detail engineering.

1.5 Wherever material or article is specified or described by the name of particular


brand, manufacturer or vendor, the specific item mentioned shall be understood
as established type function and quality desired. Other manufacturer’s product
will be considered provided sufficient information is furnished to allow the
purchaser to determine that the product proposed is equivalent to that brand.

1.6 The entire system shall be designed and engineered by the Bidder based on
the guidelines furnished in the specification, various codes / standards.
Bidder’s experience and also good engineering practice. Items and quantities,
which have been furnished in this specification, are tentative and indicative
only. During quoting, the Bidder shall vet the above Bill of Material and may
furnish additional items necessary for satisfactory operation of the system.

Annexure [6] Page 529 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

1.7 Supplies and services to be covered under this tender specification and the
conditions thereof are detailed in the subsequent sections of the specifications.
In case of conflict among various sections, subsections, documents, drawings
the same shall be referred to purchaser whose decision shall be final and
binding to the Bidder. In all cases, the best advantages will go to the
purchaser.

1.8 Bidder to note that no technical deviation shall be permitted for the system

SECTION – 2 DESIGN CONSIDERATION

The proposed facility consists of Four basements, Ground Floor, Ground floor
Mezanine, First Floor, First floor Mezanine, second floor and Twenty three Upper floors +
Terrace Floor .

Following are the various floors envisaged.

2.2. Basement 4: Car Parking, STP, Boiler room, Pump room, UG sump etc.

2.3. Basement 3: Car Parking, Pool filtration room etc.

2.4. Basement 2: Kitchen, Staff cafeteria, Composter room etc.

2.5. Basement 1: Laundry, Electrical room, DG room etc.

2.6. Upper Floors: Guest rooms, Kitchen, Restaurant etc.

SECTION – 3 DESIGN PHILOSOPHIES

3.1 CODES AND STANDARDS


The Fire protection system for Hotel Development @ Whitefield, Bangalore.
shall be designed and installed as per NFPA standards and as per
recommendations of Divisional Fire officer, Bangalore.

Annexure [6] Page 530 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

3.2 HAZARD CLASSIFICATION


The Dan Hotel, Bangalore has been classified, as Residential buildings,
Group – A, Sub -division A5.

3.3 TYPE OF SYSTEMS PROPOSED


Following are the various Fire Protection systems proposed,

 Firewater tank and Fire pump room equipment at Fourth Basement floor

 Wet riser cum down comer system

 Yard Hydrants

 Automatic Sprinkler System

 Fire extinguishers and Signage (Fire safety plans).

3.4 FIRE WATER STORAGE TANKS

 As per NFPA standards.

3.5 FIRE WATER PUMPS

 Electrically driven main pumps for each system.

 Electrically driven standby pumps for both systems fed from standby DG
sets.

 Electrically driven common Jockey pump.

 All pumps are connected to IBMS through Fire alarm system for monitoring.

 All pumps are fed from essential load bus which is backed by DG sets.

3.6 FIRE HYDRANT SYSTEM

 A ring main in the Basement floor ceiling with isolation valves.

 Ring main on Terrace level for inter connecting all Wet risers.

 Wet risers cum down comers for all buildings.

 Landing Hydrants on all floors near Staircases inside the dedicated Shaft.

 Fire Brigade Inlet connection for filling the Firewater tank as well as wet
riser system.

Annexure [6] Page 531 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

3.7 WET RISER CUM DOWN COMER SYSTEM


 Wet riser cum down comer for every 1000 sq.mts floor area for all buildings.
 Landing Hydrants on all floors with Double -headed hydrant valve,
2 x 15Mts. of fire hoses, 2 x 15Mts. of fire hoses, Hose reel with
36.5 Mts. Rubber hose and nozzle.

3.8 YARD HYDRANTS


 Yard Hydrants at the periphery of the Building with Double headed Hydrant
valve, 2 x 15 Mts. long fire hoses and Branch pipe with Nozzle.

3.9 AUTOMATIC SPRINKLER SYSTEM


 Sprinklers at all level in the Basements and above floors both sidewall &
pendent sprinklers are provided for residential apartments & common
areas.
 Design densities for various areas are listed below.
Location Ceiling sprinkler Hose Duration
design
Density Area lpm mins

Office areas 4 140 950 60

Server room 6 186 950 60

Fire pump room / DG Room 8 280 1900 60

 Coverage per Sprinkler is 9 – 12 sq.mts and Sprinklers are Pendant /


upright (as suitable at site) type with 68 deg. Temperature rating.
 Flow switches provided on the Sprinkler mains at all floor levels for
Supervising at Fire alarm Panel.

3.10 PORTABLE FIRE EXTINGUISHERS


Portable fire extinguishers are provided at locations mentioned below,
 Dry chemical powder type fire extinguisher conforming to IS 2171 near car
parking lots, main switch board room, transformer, generator room, pump
room, and lift machine room.
 Water expelled carbon-dioxide type fire extinguisher conforming to IS 940
located near each staircase landing on every floor and office areas.

Annexure [6] Page 532 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

 Carbon dioxide type fire extinguishers conforming to IS 2878, located in


electrical panel room, pump room, lift machine room and office areas.
 Mechanical foam type fire extinguishers at D.G. Rooms, Firewater pump
house and near oil filled Transformers.
 K type Extinguishers for Kitchen area.

SECTION – 4 APPLICABLE CODES AND STANDARDS

Unless specifically mentioned otherwise, all the applicable Codes and Standards
published by the Bureau of Indian Standards and their subsequent revision / BS
Standards shall govern in respect of design, workmanship, quality and properties of
materials and method of testing; standards listed below shall be applicable, in
particular:
NBC ; National Building Code of India Part IV for
Fire Protection System

IS-1239 / IS 3589 : Specification for GI Pipes

API 600 / BS 5163 : Specifications for Gun Metal gate, globe &
IS778/780/2906 check Valves for water
supply.

IS-800 : Specifications for Structural steel

IS-814 : Specifications for covered electrodes for metal


are welding of structural steel.

BS-5155 : Specifications for C. I. butterfly valve.

IS-4927 : Specifications for Canvas Hose Pipes.

IS-903 : Specifications for Branch pipes Fire hose


Couplings and auxiliary equipments

IS-5290 : Specifications for hydrant landing valves.

IS-1200 : Method of measuring of building & civil


Engineering Works
(Water supply, plumbing drain & sanitary fittings)

IS-4853 : Recommended practice for radiographic


Inspection of fusion welded butt joints in steel
pipes.

IS-636 : Synthetic, jacketed hose pipes.

IS-2198 : Control Panels.

Annexure [6] Page 533 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

IS-2159 : Hot dip galvanising of iron and steel

IS-5 : Specification for painting

IS 9137 : Specification for horizontal end suction centrifugal


Pump

BS-1965 Part I : Specification for butt-welded Pipe Fittings.

IS 8423 ; Controlled percolating hose for fire fighting.

IS 2871 : Branch pipe, universal for fire fighting purposes.

IS 884 : First aid hose reel for fire fighting

IS 2190 : Code of practice for selection, installation


and maintenance of portable first aid fire
extinguishers.

IS 937 : Specification for washers for water fittings for fire


Fighting system.

IS 9972 : Specification for automatic sprinkler heads.

IS 2171 ; Dry chemical powder type Fire extinguishers

IS 940 : Water type CO2 Fire extinguishers

IS 2878 : Carbon – di – oxide type Fire extinguishers

SECTION – 5 SYSTEM DESCRIPTIONS

5.1 FIRE WATER STORAGE TANKS

As per NFPA proposed building shall have water tank of 200 cum 2nos located next to
Firewater pump house and 20cum tank is proposed at Terrace level. Tanks shall
consist of inlet, out let, Drain, over flow etc as required and all puddle flanges are sized
to meet the system requirements.

5.2 FIRE HYDRANT SYSTEM

The hydrant system has been designed to cater to the single fire demand at a time.
The pumping philosophy shall be as follows:

Fire pumps shall be installed in firewater pump room at Fourth Basement floor. Pumps
shall have positive suction having common header.

Annexure [6] Page 534 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

3
The hydrant system header shall be fed by one jockey pump of 10.8 m /Hr. (180 LPM)
3
capacity and one main pump set of 285 m /Hr (4750 LPM). There shall be one diesel
engine driven common standby pump of same capacity.

Stopping of the jockey pump set shall occur automatically either due to restoration of
system pressure sensed by pressure switches or due to the operation of interlocking
circuits provided within the local control panel by which main fire pumps comes into
operation.
Stopping of main pump sets shall only be done manually by operation of the respective
push buttons on local control panels.
There will be one riser in the Building running from basement to the terrace. At the
terrace riser is connected to the delivery of the terrace pump-set. All the risers and
interconnecting pipes at the terrace shall be of GI heavy Grade pipes. The terrace
pump-set will take suction from 20,000 Ltrs tank, which will be exclusively used for fire
fighting purpose. At the basement, all these risers are connected to the pump manifold.
Each floor landing shall be provided with outlet hydrant valves, hose cabinet, 2 nos.
hoses of 15 mtr long, nozzle and branch pipe and also hose reel with 36.5 mtr long 19
mm dia hose with nozzles.
External hydrants called yard hydrant shall be spaced at intervals of 45 Mtr.
(maximum) around the periphery of the buildings. Yard hydrants shall be provided with
hose box & two hoses of 15 m length, nozzle & branch pipes. The underground pipe

will be of GI heavy grade, coated and wrapped as per relevant IS standards.

5.3 AUTOMATIC SPRINKLER SYSTEM


A Sprinkler system has two functions to perform, i.e. to detect a fire and then provide
an adequate distribution of water to control or extinguish it. The suction of the sprinkler
pump-sets are connected to a tank of 2 nos 200,000 Ltrs capacity (common tank to
Hydrant and Sprinkler system). The delivery of these pump-sets is connected to a
common manifold and further connected to the risers, which shall run up to the terrace
of the building. In each floor, tapping will be taken from each riser and a network of
piping will be kept under pressure and whenever Sprinkler bulb breaks, Water
sprinkled immediately and the reduction of pressure automatically sensed thereby
switching ON the Sprinkler Pump.

The pump-sets can be either switched ON automatically or manually depending upon


the selector switch in the MCC / Auto start panel.

Annexure [6] Page 535 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Automatic Sprinkler system with piping grid work as required shall be installed at the
ceiling level of all floors Sprinkler shall be installed, if ceiling void is 800 mm and more
and separate piping is not necessary. Sprinklers above the false ceiling shall be upright
type and below the false ceiling / real ceiling pendant type. Sprinklers installed entire
floor area except Toilets, Electrical rooms and Mechanical rooms.

Branch mains for floors consisting with flow switch and Isolation valves. Flow switches
and Isolation valves are connected to Fire alarm panel for monitoring the status of the
system.

5.4 PORTABLE FIRE EXTINGUISHERS


Portable fire extinguishers are provided at various locations as mentioned below,
 ABC type fire extinguisher conforming to IS 2171 near server room on every floor.

 Water expelled carbon-dioxide type fire extinguisher conforming to IS 940 located


near each staircase landing on every floor and office areas.
 Carbon dioxide type fire extinguishers conforming to IS 2878, located in electrical
panel room, pump room, lift machine room and office areas.
 Mechanical foam type fire extinguishers at, D.G. Rooms, Firewater pump house
and near oil filled Transformers.
 K type Extinguisher for the Kitchen area.

SECTION – 6 SCOPE OF WORK

6.1 INTRODUCTION

The scope of work includes complete design, Engineering with necessary design
calculations, Fit – up details, Supporting details, Manufacture / Fabrication, supply,
Storing. Installation / erection, testing, commissioning the fire hydrant system, Hose Reel
system, Sprinkler system, first aid fire extinguishers & Signage and quoted rates should
includes complete earth works i.e., excavation, back filling for the buried pipes wherever
applicable & with all necessary accessories as per Specifications and National Building
Code of India, at DAN HOTEL @ BANGALORE.
.Further it is Bidder’s responsibility to obtain the necessary approval from the,
DIVISIONAL FIRE OFFICER, BANGALORE.

Annexure [6] Page 536 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

6.2 DRAWINGS AND DESIGN CALCULATIONS

The drawings enclosed herewith are for the general guidance to Bidder. The contractor
shall upon the award of the work, furnish detailed working drawings (as mentioned under
Clause No. 6.1 above) necessary to carryout the work at site with detail design
calculation. These shall be submitted to the Employer/Architect for the approval and
the work shall be commenced only after the approval of drawing by the
Employer/Architect.

6.3 INSPECTION AND APPROVAL

The contractor shall guarantee both the material and workmanship of first class quality
corresponding to standard engineering practice. Any defective materials/workmanship
shall be rejected, the contractor has to rectify / replace at his own cost. Guarantee
certificate of the materials supplied shall be handed over to the clients.

6.4 DOCUMENTS TO BE SUBMITTED ALONG WITH BID

List of data/document/drawings to be submitted along with bid shall as mentioned


below,
1) Preliminary Overall dimensions of pump sets /motors/engines
2) List of Deviations (Technical) if any, as an Annexure.
3) Technical parameters of all equipment offered (catalogues, G.A. drawings etc).
Preliminary pump house layout confirming adequacy of space provided for firewater
pumps

6.5 DOCUMENTS TO BE SUBMITTED AFTER AWARD OF CONTRACT

List of data/document/drawings to be submitted after the award of contract shall be


indicated. The list shall essentially contain the following:

1) Design and operation philosophy of the complete fire system


2) Piping layout
3) Schematic drawings,
4) Data sheets of all the equipment envisaged
5) Detailed Hydraulic calculation
Bar chart/network schedule covering all milestone activities.

Annexure [6] Page 537 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

6.6 INSTRUCTION MANUAL/COMPLETION DRAWING/TRAINING

The contractor shall be responsible for training of the Employer's personnel (minimum
6 rounds) in the period of operation and maintenance of the system and conduct Fire
drill. The rates quoted shall inclusive of submitting 6 sets of the following documents
(HARD COPIES) along with CDs (Soft copy) and the following,
1. Detailed equipment data in the approved proforma
2. Manufacture’s maintenance and operating instructions manuals
3. Set of as built drawings, layouts, piping, ducting, cable routing, cable
Schedules etc
4. Approved test readings of all equipment and installations
5. Inspection certificates
6. Certificates of approval from statutory or Local Authorities for the operation
and maintenance of the installations, wherever such approval or certification is
required. This shall include Application filed along with enclosures and receipts
of fees paid and deposits made.
7. Warranty / guaranty certificate for all equipments
8. List of recommended spares together with list of suppliers and their contact
details
9. Undertaking that all the materials supplied by him at site are fully tax paid and
shall produce all documentation for satisfaction of the Employer / PMC
/Architects / Consultants or taxation authorities.
Submission of the above documentation shall form a precondition for final
acceptance of the plant and installation and final payments.

Annexure [6] Page 538 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

SECTION-7 EQUIPMENT SPECIFICATION

A FIRE HYDRANT SYSTEM

1.0 Without restricting to the generality of the foregoing, the fire hydrant system shall include
the following:
1.1 Fire water pumps, prime movers, Base plates, Couplings, suction / delivery pipes,
Valves and Instrumentation for automatic operation etc.
1.2. Galvanized Iron (G.I) Class "C" (heavy grade) fire riser main within the building and as
well outside the building.
1.3 Landing valves, hose reels, hose cabinets, fire brigade connections and connections to
pumps and appliances.
1.4 All materials shall be of the best quality and brand new, conforming to these
specifications and subject to the approval of the Client / consultant.
1.5 Pipes shall be fixed in a manner as to provide easy accessibility for repair and
maintenance and shall not cause obstruction in shafts, passages etc.,
1.6 Pipes and fittings shall be fixed to walls and ceilings by suitable clamps at intervals
specified. Only approved types of anchor fasteners shall be used for RCC ceilings and
walls.
 Pipes and fittings shall be fixed truly vertical, horizontal or in slopes as required in
a neat manner.
 Valves and other appurtenances shall be as located that they are easily accessible for
operation, repairs and maintenance.
 Pipes for wet risers within the Building shall be G.I Pipes conforming to IS 1239 (heavy
duty 'C' class) with Grooved joints.
 Fittings for black steel pipes shall be malleable iron or approved type cast iron fittings
with screwed / welded joints.
1.11 Inter connection between sprinkler and hydrant pumps shall be carried out at discharge
side with check valve and isolation valves.
1.12 Construction of Fire water tanks, Fire water pump house, Puddle flanges at water
tanks for suction / delivery / test lines and core cutting / opening if required on
wall is exempted by Fire protection contractor.

2.0 PIPING

All pipes inside the building and where specified, outside the building shall be G.I Pipes.
tubes conforming to IS: 1239 - heavy duty. Pipes 200 mm dia. and above shall be as

Annexure [6] Page 539 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

per IS: 3589 with minimum 6 mm wall thick & fittings shall be fabricated from pipes
confirming to IS 3589.
Pipes shall be carefully laid to the alignment, levels and gradients shown on the plan and
sections and great care shall be taken to prevent any sand, earth or other matter from
entering the pipes during laying. Pipes shall be kept thoroughly clean during the course
of laying. The ends of pipes shall be blocked with wooden plugs wedged home, at the
end of each days work to prevent dirt and rodents, insects etc., entering the pipe.
Mechanical tee shall with hole cut method shall be provided for Sprinkler tapings.
Delivery header of Hydrant and sprinklers shall be provided with Pressure Transmitter
and also at the tapping of Hydrant and sprinkler riser at the Top most floor.
Pipes up to 50mm dia, shall be joined by threaded type fittings, while for pipes above
50mm dia shall be by butt welded joints. All Flanged joints for pipes / valves shall be
made with 3 mm thick insertion rubber washer / Neoprene rubber Gaskets. All bolt holes
in flanges shall be drilled & making hole by using gas cutting is not acceptable. The
drilling of each flange shall be in accordance with relevant Bureau of Indian Standards.
All “T” joints on pipes 50 mm dia and below shall be drilled to suitable size and no
gas cutting is accepted. Also refer pictures attached for reference.

Picture -1 Picture - 2

As explained above Picture – 1 is right and Picture – 2 is not accepted.

Annexure [6] Page 540 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

The Bolts /Nuts / Washers used in the system (wherever required) shall be
Galvanized as per IS 1367 and suitable length & not more than 15mm beyond the
Nut.

1.12a PIPE PROTECTION – ABOVE GROUND PIPES

All pipes above ground and in exposed locations shall be painted with one coat of Zinc
Phosphate Primer (Epoxy based) and two coats of signal red Enamel paint complete.
Enamel Paint application (First Coat) to be done after minimum 1 hour and maximum
24 hours of application of Primer. The time interval between 1st coat and 2nd coat
enamel paint should be 5 to 6 hours. All pipes should be supported by M.S. Hot dip
Galvanized Brackets (2.5 meter centre to centre) duly painted with Zinc Phosphate
Primer (Epoxy based) and two coats of Enamel paint. The pipes should be initially
brushed to remove all foreign matter before applying paint / primer.

1.12b PIPE PROTECTION – UNDER GROUND PIPES

WRAPPING OF CONCEALED PIPES

Cleaning

Pipe surfaces shall be thoroughly cleaned and dried before tape is applied and shall be
free of dirt, grease and rust scale or other foreign matter. The pipe shall be cleaned
mechanically.
Oil and grease, if present on the pipe surface should be removed by using a suitable
solvent and clean rags. The use of dirty, oily rags should not be permitted.
FOLLOWING PAINTING PROCEDURE SHALL BE FOLLOWED FOR G.I. / M.S.
SURFACES

A ) M.S. Surfaces

a) Internal M.S Surfaces.


One coat of Zinc chromate Primer with two coats of First quality Synthetic Enamel
paint of approved brand and shade.
b) External M.S. Surfaces.
M/s. Asian Paint Zinc phosphate EHB product code: 1343, which has properties of Anti
Corrosive also. (This primer is available in two components) & two coats of First
quality Synthetic Enamel paint of approved brand and shade.

Annexure [6] Page 541 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

B) Open G.I Surfaces.( Internal as well as external ).


M/s. Asian Paint Zinc phosphate EHB product code: 1343, which has properties of Anti
Corrosive also. This primer is available in two components.
For Galvanized surfaces, contractor shall do Zinc Phosphate primer, epoxy based,
followed by 2 coats of Enamel paint. Please note enamel paint application to be done
after min 1 hour & max 24 hrs , after application of Zinc phosphate primer. Time
interval after application of Zinc phosphate & application of 1st coat of enamel should
be min 1hour & max 24 hrs, so that the Zinc phosphate does not loose it's etching
characteristics. The interval will be 5 to 6 hrs between application of 1st coat enamel
paint & 2nd coat enamel paint.

Following procedure should be followed for all under ground G.I. pipe works
a) In case of GI Pipes and fittings laid underground, except welded joints, the Anti-
rust treatment given is as follows:
1. Cleaning of G.I. Pipes and fittings, with sandpaper, to clear the same of all dirt.
2. Application of coal tar (Black Japan brand), on G.I. pipes, in one coat only, on
same day, immediately after cleaning G.I. pipes of all dirt.
3. Wrapping of Plastic coated Hessian Cloth, on the wet coal tar application,
immediately after coaltar application is done.

b) PYPKOTE (4mm) is a polymeric corrossion protection tape.

PYPKOTE (4mm) tape should be applied on all welded joints & M.S. fittings of U.G.
G.I. pipe work for protection of joints & fittings, as per details given in below sketches.
For other areas other than sketches, procedure mentioned in Point (a) should be
followed:

All hatched portion indicates PYPKOTE (4mm) Tape application areas in below
sketches.

Annexure [6] Page 542 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works












APPLICATION PROCEDURE OF PYPKOTE (4MM)

a) Surface Preparation -
The pipe surface shall be cleaned by a wire brush.
b) Application of Pypkote Primer -
Pypkote primer is to be applied on pipes immediately after cleaning. This is to
prevent any further accumulation of rust on the pipe. Pypkote primer is a cold applied
primer and is applied by brush.
c) Application of Pypkote 4mm Tape -

After the primer is applied on the pipe, it is allowed to dry for about 30 min. till it
becomes touch dry. Before adhering the tape to the pipe, it is advisable to gently
heat the primer coated pipe by a run of LPG torch. Remove the bottom
polyethylene from the tape & then heat bottom surface of the tape by LPG Torch or
any heat source & start wrapping the tape to the pipe. By heating the primer coated
pipe & by removing the bottom polyethylene from the tape before wrapping, better
adhesion between the tape & pipe is obtained. Overlaps are maintained with a
minimum of 12.5mm.
d) Tape Coating of Weld Joints -
The tape is applied over the weld joints after the necessary welding & testing
methods of the joints is completed. The procedure for application of tape shall be
the same as bare pipe procedure. Overlaps on each side of the weld joints shall be
50mm.
e) A final coat of White wash with water based cement paint is done immediately over
the entire coated pipe.

Annexure [6] Page 543 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

MODE OF MEASUREMENT

pipes above ground shall be measured along the centre line of the pipes and fittings. The
quoted rate for respective item shall be per Rmt and shall include the following:

a) Cost of respective pipes and specials.


b) Laying, fixing and jointing with standard pipe clamps available for different sizes
inside the wall chase and fixed on MS angle iron brackets and GI U clamps for pipes in ducts
as shown on the drawing.
c) Cutting holes and chases in walls, floors, etc. and making good the same.
d) All supporting arrangements, brackets, etc.

Testing and making good the defects, if any. G.I. pipes below ground shall be measured as
stated elsewhere in the specifications.

2.1 EXCAVATION / THRUST BLOCKS

2.1.1 Excavation for pipe lines shall be in open trenches to line and grade or as required at site
including disposal outside of site at approved dumping yard with the prior approval of
concerned authorities. Pipe lines shall be buried to a minimum depth of 1M (top of the
pipe) from the finished ground level.
2.1.2 The contractor shall support all trenches or adjoining structures with adequate timber
supports wherever required.
2.1.3 On completion of testing and painting of the pipe lines, trenches shall be refilled with
excavated fine earth in 20cms. Layers, and consolidated by ramming and watering.

2.1.4 THRUST BLOCKS

Contractor shall provide suitable PCC blocks of suitable dimensions at Change – in –


direction and regular intervals of 6 meters to support the pipes.

3.0 VALVES

Butterfly valves shall be as per BS 5155 & provided for pipes 50mm dia and above. The
valves shall be CI construction, seat shall be black nitrile rubber with insitu moulding.
The valves shall be PN 25 rating. All valves shall be connected with supervisory switch
for monitoring at Fire alarm panel. Cabling shall be done by other agencies.

4.0 EXTERNAL HYDRANTS

Yard hydrant valves shall be as per IS: 5290 (Type A). The valves should be complete
with hand wheels, quick coupling connections, springs and blank caps. The hydrants
shall be fixed to stand posts of 80mm dia for Double headed hydrants at 1.0M from

Annexure [6] Page 544 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

ground level. External hydrant valves shall be Double headed type, as specified in
Schedule of Quantities.

5.0 HOSE REEL


Contractor shall provide standard fire hose reels with 19mm dia high pressure rubber
braided hose of specified length with gunmetal nozzles and control valve, shut off valve,
all mounted on a circular hose reel drum of mild steel construction and cast-iron / M.S.
bracket. The hose reel shall be installed in fire hose cabinet / fire duct inside the
building.

6.0 LANDING VALVE AND HOSE PIPE

The landing valve (internal) shall be gunmetal Double headed type conforming to IS:
5290 complete with hand wheel, quick coupling, spring and blank cap. RRL type hose
pipe shall be 63mm dia and 15 mts. length as per IS: 636 with 63mm dia. Instan-
taneous pattern type Gun metal heavy duty couplings as per IS: 903, Gun metal Branch
pipe and nozzle shall be as per IS: 903 & to be provided in the fire hose cabinet. The
fire hose cabinet shall be as per Bill of Quantities.

7.0 FIRE BRIGADE INLET CONNECTION (FBIC)

FBIC shall be as per IS 5131 & gunmetal four away connecting head with 4 x 63 mm dia
instantaneous type inlets with built in check valve and 150mm dia outlet connection to
the fire main grid with 150mm dia Butterfly valve and non – return valve.

8.0 AIR RELEASE VALVES

Air release valve is 25mm screwed inlet GM single acting type and shall be fixed on all
high points in the system or as shown on drawings.

9.0 DRAIN VALVES

Gun metal Gate / Ball valve of 25 / 40 / 50mm dia as per IS;778 with GI pipe conforming
to IS 1239 heavy class for draining any water in the system / Risers in low points

10.0 VALVE CHAMBERS

Contractor shall provide suitable brick masonry chambers in cement mortar 1:5 (1
cement : 5 Coarse sand) on cement concrete foundations 150mm thick 1:5:10 mix (1
cement : 5 fine sand : 10 graded stone aggregate 20mm nominal size) 15mm thick

Annexure [6] Page 545 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

cement plaster inside and outside finished with a floating coat of neat cement inside
with cast iron surface box (OR top cover fabricated by M.S. chequered plate of 6 mm
thick with frame / stiffeners etc) approved by local fire brigade including excavation, back
filling and additional Iron rungs for entering in to valve chamber etc, complete.
Mode of measurement
Valves/hydrant/Hose reel/air release valve/FBIC/ shall be measured in number only and the
cost shall include:

a) Cost of valves and jointing materials.

b) Fixing and jointing with necessary bolts, nuts, rubber inserting, etc.

Testing and making good the defects if any.

11.0 PIPE PROTECTION – ABOVE GROUND PIPES

All pipes above ground and in exposed locations shall be painted with two coat of Zinc
rich primer and two or more coats of synthetic enamel paint of approved shade. The
pipes should be initially brushed to remove all foreign matter before applying paint /
primer.
12.0 PIPE PROTECTION – UNDER GROUND PIPES

The pipes (buried) should be initially brushed to remove all foreign matter and apply the
primer over the pipe. Primer is allowed to dry until the solvent evaporates and surface
becomes tacky. The tape 4mm thick and 150/250mm wide shall then be wound in a
spiral fashion and bonded completely to pipe by thermo fusion process. The overlap is to
be maintained at 15mm.

12.1 PIPE SUPPORTS


Supports for above ground pipes type of supports ( Shall be fabricated by M.S. Channel /
Angle / Flat for above 50 mm dia), anchor fasteners, bolts nuts, "U" clamps, bolt,
malleable specials such as Reducers,Tees, elbows, flanges. Including cutting, Welding,
fixing in / on walls, ceiling by using suitable supports etc, as per drawings. The quoted
rate shall also include for chasing / chipping walls, making bore holes in walls / floor and
making them good with filler material and finished in cement mortar. The spacing of
supports shall be 3mts minimum and painted two coats of enamel paint of approved
color over a coat of primer.
Suitable type hangers shall support pipes below 50 mm dia with clamps, anchor
fasteners and suspended rods etc.

Annexure [6] Page 546 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Fasteners (Anchor bolt, suspended rod, U bolts etc) shall not be less than 10 mm for
pipes up to 80mm and 16mm for pipes 100mm & above.

13.0 TESTS AT SITE

13.1 PIPING

All piping in the system shall be tested to hydrostatic pressure of 1.5 times of the working
pressure without drop in pressure for at least 120 minutes. The test should be made in
the presence of and to the satisfaction of the Employers / consultants representatives.
Any defects / leakage should be repaired or if necessary defective works / equipment
should be replaced with new work / equipment. Tests should be repeated until work is
done to the satisfaction of concern representatives.
After testing all pipes shall be flushed with portable water to remove foreign
materials.
Under ground Pipes after lowered in to trenches shall be Holiday tested for damages of
the anti corrosion treatment and damages should be rectified, bring it to the notice of the
engineer – in –charge of site before closing the trenches.
Also the under ground pipes joints shall be tested for Radiographic for 10 % of the total
under ground joints. The test results and films shall be submitted for approval and any
defects found in the welding process shall be rectified the contractor with out any extra
cost to the clients.

13.2 PUMPS

On completion of installation works at site the complete system shall be tested for
satisfactory performance in line with specifications as per Tender / requirements of
Employer / Consultants. Pumps should test for Sequential Auto start in case of using the
Hydrants / sprinklers / on actuation of HVWS system. Also pump shall deliver minimum
required flow & pressure at top most hydrant point. All instruments for testing should be
arranged by the Contractor. The performance test includes commissioning spares like,
diesel oil, engine oil, coolant, grease, gland packs and spare refills for Fire extinguishers
etc complete.

14.0 PUMPS AND ACCESSORIES

The pumps shall be exclusively used for fire fighting purposes and shall be BIS
approved as mentioned in the BOQ. One set for each system with electrical motor

Annexure [6] Page 547 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

driven direct couple centrifugal pump of adequate discharge and additional common
standby Diesel engine driven direct coupled centrifugal pump of adequate discharge
and head shall be provided. The pumping capacity of main and stand by hydrant /
Sprinkler system pumps shall be as mentioned in the BOQ.

14.1 GENERAL REQUIREMENT

The pumps shall be horizontal centrifugal type, pump designed for continuous operation
and shall have a continuously dropping head characteristic without any zone of
instability. The power capacity characteristic shall be non-over loading type. The head
vs. capacity, input power vs. capacity characteristics, etc., shall match to ensure load
sharing and trouble free operation throughout the range. In case of accidental reverse
flow through the pump the driver shall be capable of bringing the pump to its rated
speed in the normal direction from the point of maximum possible reverse speed. The
contractor under this specification shall assume full responsibility in the operation of
the pump and the drive as one unit. The pump shall be capable to discharge 150
percent of rated capacity at a total head of not less than 65 percent of the total rated
head. The total shut off head shall not exceed 120 percent of total rated head on the
pump. An automatic air release valve shall be provided to vent air from the pump
discharge and also to admit to the pump to dissipate the vacuum there, upon stopping
of the pump.
This valve shall be located at the highest point in the discharge line between the pump
and the discharge check valve. Pump coupled with motor or engine on a common base
plate shall perform smoothly without any excessive noise or vibration. Also pump shall
be provided with re-circulation piping with valves.

14.2 PUMP CASING

The casing shall be cast iron to IS 210 and capable of withstanding to the maximum
pressure developed by the pump at the pumping temperature.

14.3 IMPELLER

The impeller shall be of standard bronze. The impeller shall be secured to the shaft with
hydraulically balanced and shall be retained against circumferential movement by
keying, pinning or lock rings. All screwed fasteners shall tighten in the direction of
normal rotation.

Annexure [6] Page 548 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

14.4 SHAFT

Shaft size shall be selected on the basis of maximum combined shear stress. The
shaft shall be of stainless steel AISI-410 ground and polished to final dimensions and
shall be adequately sized to withstand all stresses from motor weight, hydraulic loads,
vibrations and torque’s coming in during operation. Pump Shaft-Motor Shaft Coupling
shall be connected with adequately sized flexible couplings with spacer of suitable
approved design. Necessary guards shall be provided for couplings. Pump shall be
consisting with Gland plate for gland packing.

14.5 BASE PLATE

A common base plate for mounting both the pump and drive shall be provided. The
base plate shall be of rigid construction, shall be fabricated by M.S. channels. Base
plate and pump supports shall be so constructed, the pumping unit shall be mounted
so as to minimize misalignment caused by mechanical forces such as normal piping
strain, hydraulic piping thrust etc.,

14.6 VIBRATION AND BALANCING

The rotating elements shall be so designed to ensure least vibration during start and
throughout the operation of the equipment. All rotating components shall be statically
and dynamically balanced at workshop. All the components of pumps of identical
parameters supplied under these specifications shall be interchangeable.

14.7 INSTRUCTION MANUAL AND TOOLS/SPARES

A comprehensive instruction manual shall be provided by the sub-contractor indicating


detailed requirements for operation, dismantling and periodic operation and
maintenance procedures. Recommended tools/spares shall be provided along with the
Pump set.

15.0 DIESEL ENGINE

15.1 GENERAL

The diesel engine shall be of multicylinder type four-stroke cycle with mechanical
(airless) injection, cold starting type. The engine shall be manufactured as per IS
10000 and shall be ease of maintenance, repair, cleaning and inspection. This will also

Annexure [6] Page 549 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

provide interchangeability of parts. All parts susceptible to temperature changes shall


have tolerance for expansion and contraction without resulting in leakage,
misalignment of parts or injury to parts.

15.2 STARTING

The engine shall be capable of both automatic and manual start. Generally the engine
shall start automatically but in case of the auto-start system failure the engine shall be
capable of manual start. Engine shall be able to start without any preliminary heating
of combustion chamber; cranking mechanism shall also be provided. All controls/
mechanism, which has to be operated in the starting process, shall be within easy
reach of the operator. A DC motor charged by battery shall initiate automatic start of
diesel engine. The battery shall hold adequate retainable charge to provide the
starting of the diesel engine. Starting power will be supplied from two sets of storage
batteries. One set of battery is for automatic starting of the engine and the other
provided for manual starting. A selector switch will be provided at automatic starting
control panel to select any of the two sets of battery for manual / auto starting of the
engine. The battery capacity shall be adequate for ten consecutive starts without
recharging with a cold engine under full compression. The battery banks shall be used
for no other purpose other than starting of the engine and shall be fully charged at all
times with provision for trickle and boost charges. After start of the engine the charger
shall be disconnected, the battery being fed from the engine dynamo. The two-battery
charger of air-cooled type shall be able to charge on battery bank at a time. The D/E
starting panel along with the battery chargers should be of reputed approved makes.

15.3 GOVERNING SYSTEM


The engine shall have a speed control device which will control the speed under all
conditions of load the governor shall be suitable for operation without external power
supply. The Governor shall offer following features: An adjustable governor to regulate
engine speed within a range of 10% between shut-off and maximum load conditions of
the pumps. The governor shall be set to maintain rated pump speed at maximum
pump load.

15.4 FUEL SYSTEM


The diesel engine is to run on high-speed diesel, the tank provided being enough to
hold the volume required for 6 hours (minimum) continuous operation. Fuel tank shall
be double wall type, so that over flow of the fuel shall be collected in the secondary
tank. Fuel supply and return piping shall be metal with necessary valves. Fuel tank

Annexure [6] Page 550 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

shall be mounted on the fabricated consisting with air vent, over flow, drain, filling and
manhole etc. It shall also be provided with the magnetic level switch which shall be
connected to Electrical panel.

15.5 COOLING WATER SYSTEM


Direct cooling system shall be employed for the diesel engine. Water shall be tapped
from the fire pump discharge. This water shall be led through duplex strainer, pressure
breakdown orifice and then after passing through the engine, the outlet water shall be
taken directly to the sump through an elevated funnel. Re-circulating thermo siphon
system of cooling using a fan cooled radiator or indirect cooling system using heat
exchanger shall not be accepted.

15.6 ACCESSORIES
The engine shall be mounted on a base plate of fabricated steel construction.
Adequate access shall be provided for the big end and main bearings, camshaft and
governor drives, water jackets etc., the engine shall have a base plate made from MS
sections. There shall be reasonable space at the big end, camshaft, water jackets,
governor drives and main bearings. The engine shall be provided with intake and
discharge ductwork, inlet filter and silencer, outlet muffler, expansion joints, dampers
etc., as necessary for efficient operation. Intake air should be taken from inside the
building in which the engine is located, but the exhaust should be discharged outside
the building and exhaust duct shall be adequately sized for minimum pressure drop as
per relevant code/standard, and shall be housed clearing man height. The flywheel
shall have graduated marking around the periphery to facilitate checking of valve and
fuel pump timings. Full set of diesel engine spares as per Standard requirement to be
provided along with tool kit.

15.7 INSTRUMENTATION

The diesel engine shall be provided with adequate instrumentation. The gauges etc.,
as required are provided for in the Engine Panel. Also Bidder shall supply one set of
Spare parts recommended by the manufacturer for maintenance purposes.

Annexure [6] Page 551 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

B. AUTOMATIC SRINKLER SYSTEM

1.0 SCOPE OF WORK

The sprinkler system shall be provided in basement and all upper floors. This system
shall include the following:
General

Work Included

This Section specifies the requirements to furnish and install complete automatic
sprinkler system for the fit out areas as shown in the drawing and as per NFPA 13.

It is intended that the work performed pursuant to these specifications be complete in


every respect, resulting in a system, which meets or exceeds the requirements of the
applicable codes, standards, all regulatory requirements, manufacturer’s
recommendations, UL approvals.

In general, labor and material to be furnished and installed shall include preparation
of shop drawings, hydraulic calculations, connection, testing and flushing of the fire
sprinkler system water service, interior piping, automatic sprinklers, valves,
supervisory and alarm devices, and miscellaneous appurtenant work.

This work shall also include furnishing and installing all sleeves and other wall and
floor penetrations required for the fire protection piping. Seal all sleeves and other
wall and floor penetrations of hydrant and sprinkler piping, unless noted otherwise.

Fire extinguishers would be placed at strategic locations as shown in the drawings


and as specified in the BOM:

Related Work

This Section shall be used in conjunction with the following other specifications and
related Contract Documents to establish the total requirements for wet pipe sprinkler
systems:
 Joint Sealers.
 Painting - Equipment and Piping.
 Basic Mechanical Requirements

Annexure [6] Page 552 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

 Pipe and Pipe Fittings - General.


 Piping Supports and Anchors.
 Mechanical Sound and Vibration Control.
 Mechanical Identification.
 Indicating Devices

In the event of conflict regarding fire sprinkler system requirements between this
Section and any other section, the provisions of this Section shall govern.

System Description

The Contractor shall be responsible for the design and installation of a complete
automatic sprinkler system for the fit out areas as shown in the drawings and as per
NFPA 13.
Fire sprinkler system shall have separate zones. Each zone shall have an inspector
test at most hydraulically remote part of system which will have a suitable drain.
Sprinklers shown on the reflected ceiling plans are to be considered aesthetically
critical and are not to be relocated without prior review by the Contractor and the
Project Manager / Professional Team.

Design Criteria

Each zone shall have an inspector’s test connection at the hydraulically remote point
of the system in addition to the main and low point drains required by code. Location
of the inspector’s test connection and drains shall be readily accessible, not more
than 1200mm above the floor, and not within a clean room area. Test drains shall
discharge in the janitor area.

Design of hydraulically calculated sprinkler systems shall include allowance of


1892lpm for outside hose streams and shall be based on the hydraulically most
demanding rectangular area having a dimension parallel to the branch lines at least
1.4 times the square root of the area of sprinkler operation used. Spacing for fire
sprinkler heads shall be in accordance with the Fire Protection Schedule and as per
NFPA 13 for sprinkler spacing..

Design of hydraulically calculated systems shall be based on a flow test provided by


the Contractor and witnessed by Project Manager / Professional Team and by local

Annexure [6] Page 553 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

fire brigade. Hydraulic calculations shall be submitted with detailed sprinkler piping
drawings for review.

Hydraulic calculation shall be done using Hazen-Williams coefficient of 120 for above
ground sprinkler piping. It is intended that the Contractor shall use the sprinkler
system criteria shown on the Drawings and as specified for the basis of the design.
The Contractor shall prepare fabrication shop drawings, which shows installation for
all piping, using the design shown, with minor revisions to allow for coordination with
actual installed locations of the work of other trades. The Contractor shall make such
minor revisions within the specified design criteria, at no additional cost, and shall
verify with hydraulic calculations that such changes remain within the criteria.

Warranty
The Contractor shall be responsible for any replacement due to the use of materials,
tools or equipment, or methods or procedures of installation or fabrication, which are
contrary to, or in direct violation of, the requirements of the referenced codes and
standards and of this Specification, unless the use of such material, equipment,
method, or procedure has the prior written approval of the consultants, including
acknowledgment of the variation from the requirements. Failure to discover the use
by the Contractor of prohibited materials, equipment, methods, or procedures prior to
final approval or acceptance of the fire sprinkler system shall not constitute approval
of such prohibited material, equipment, method, or procedure, nor relieve the
Contractor of the responsibility to replace prohibited materials or correct the
prohibited component of installation at no additional cost.

Professional Team
All work in accordance with, and subject to, the inspection and approval of clients,
Factory Mutual, and the authority having jurisdiction (all of whom are referred to as
the Professional Team). All work shall be designed and installed in accordance with
NFPA 13.

Regulatory Requirements
The Contractor shall be responsible for filing all related documents, obtaining and
paying for all permits for the portion of the fire sprinkler systems covered by the
Work, including arranging and paying for all inspections and tests of the fire sprinkler
installation required by this Specification, codes and standards and Professional

Annexure [6] Page 554 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Team. The Contractor shall submit written evidence to the Contractor that required
permits and approvals have been secured prior to the start of installation.

Quality Assurance
All work pertinent to the fire sprinkler system shall be done by a qualified, competent
fire protection sprinkler system contractor who can furnish a list of satisfactory
installations of this type. The Contractor shall hold all current licenses required by
the authorities having jurisdiction.

All equipment shall be UL approved for fire protection systems unless


otherwise specified.

Submittals
The contractor shall submit nine (9) copies of the following requirements:
Detailed installation shop drawings created with AutoCAD and stamped by a registered
professional engineer recognized by the authority having jurisdiction and hydraulic
calculations of the complete fire sprinkler system. Shop drawings shall show all of the
information required by NFPA for working plans and shall include the location of all
equipment, controls, hangers, piping, valves, drains, the location and diameter of all
core drills, pipe sleeves, and pipe clearance openings in walls and floors.
AutoCAD files of architectural, mechanical, structural, electrical, instrumentation and
control, and life safety plans will be provided as requested by the Contractor for his
use.
 Catalog data sheets showing the type and model of all equipment or material to be
installed, including type of pipe, hangers, valves, pipe fittings/joining methods,
sprinklers, alarm and water flow devices, supervisory devices, bracing, sleeves,
escutcheons, coupling lubricant, thread dope, and sleeve fire-rated sealant. When a
data sheet shows more than one product, the specific proposed product shall be
clearly indicated by arrows or other suitable means.

Annexure [6] Page 555 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

 Complete shop drawings, hydraulic calculations shall be submitted to, and be


approved by the consultants, the state fire marshal, prior to submission to Clients.

 The shop drawings shall show correct installation dimensions and cut lengths for all
piping using the design criteria and allow for coordination with actual installed locations
of the work of other trades.

 Proof of all required approvals by the above shall be submitted prior to the start of
installation.

 Sample of each type of sprinkler to be used, including types of finish and protective
coatings, and a complete list of where each type, finish, and coating will be provided
for review.

 Copies of all permits, licenses, approvals of shop drawings, prior to fabrication of


system.

As-Built drawing
Prior to completion of the project and acceptance of the project by the
Contractor, the Contractor shall submit six (6) copies, including but not limited
to the following:
1. As-built drawings showing deviation from the original approved
items.(Both hard & soft copies)
2. A set of sepias or originals.
3. Updated AutoCAD files.
4. Hydrostatic test data sheets.
5. Contractors material and test certificate

Spare Parts
For each system, furnish and install spare metal sprinkler cabinets with
sprinklers, of the types, finishes and temperature ratings used, and sprinkler
wrenches compatible with each type of sprinkler used. Provide a minimum of
ten spare sprinklers of each type, finish, and temperature rating used
elsewhere.

Annexure [6] Page 556 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Accessories
System Valves

1. Control Valves: gate valve or butterfly valve of approved make.


2. Test and Drain Valves: bronze body and trim, globe type suitable for 16Kg/cm2
design pressure, including plug.
3. Provide and install hose thread adapter and cap for all auxiliary drain valves.
4. Check Valve: cast iron body, bronze trim, wafer, 16Kg/cm2 design pressure.

Supervisory Switch
1. A supervisory switch shall be installed on each fire protection system control
valve, including post indicator valves. Installation of the supervisory switch
shall be as recommended by the manufacturer.

2. The supervisory switch shall be designed to operate between the first and
second revolution of the valve control wheel or if housing cover is removed.
The complete unit shall be 0.25amp, 24 Vdc. Switches shall be of approved
make

Flow Detector Switch


Detectors shall not be mounted in a pipe fitting or within 300mm of any fitting
that changes the direction of water flow. The unit shall be set to signal any flow
of water that equals or exceeds the discharge from one sprinkler head. The
unit shall be rated at 0.25 amps, 24 Vdc and shall be provided with pneumatic
retard element with an adjustable range of 0 to 70 seconds. The units shall
have two 24 Vdc contacts suitable for providing a signal to the local and the
remote fire alarm system.

Sprinklers
1. Sprinklers shall of UL listed recessed/pendant type and shall have 15mm orifice
with the temperature rating specified in accordance with NFPA. Furnish and
install chrome plated canopy flanges on all pendent sprinklers in finished
ceilings.

2. . In order to be approved, the substitution shall have brass content containing


less than 15 percent zinc, shall have a Belleville washer seal coated with TFE,

Annexure [6] Page 557 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

and a machined (not stamped) brass pip. In addition, for the clean room ceiling
grid heads, the head should be of a size, which is capable of being inserted
through the grid from above while attached to the flexible hose.

System Piping
All materials used or installed in the overhead piping, fitting, and hanger
material shall be new and comply with the requirements outlined in Section -
Pipe and Pipe Fittings - General, and NFPA / BIS except as follows:

1. Piping with a wall thickness less than heavy class shall not be joined by cut
threaded fittings.
2. Piping shall be (GI) galvanized steel class (Class C) as per IS 1239 Part I upto
150mm dia. Above 150mm dia. shall be as per IS 3589 with bath galvanizing.
Pipes 50mm above shall be butt welded, 50mm and below shall be socket-
welded joints.

Pipe Hangers And Supports


1. The use of power driven studs is prohibited except for fastening of earthquake
sway bracing to structural steel. Hangers shall not be fastened to the structure
with power driven studs Hangers rod size and spacing should be as per FM
global datasheet 2-0.
2. Hanger types and arrangements other than as shown on the Drawings may be
permitted, provided such hangers meet the requirements of FM 2-0 and the
authorities having jurisdiction, and have the prior review and approval of the
Contractor.

Hydraulic Data Placard

1. In addition to the requirements of Section - Mechanical Identification, provide a


hydraulic data nameplate showing the information required by NFPA for the
area of the building with the greatest demand shall be permanently attached at
the zone valve. Additional nameplates shall be attached at each zone control
valve, showing the zone number and data for that zone.

2. Nameplates shall be metal or engraved plastic, with stamped or engraved


lettering of sufficient contrast to background to be completely legible. Paper,

Annexure [6] Page 558 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

embossed plastic tape, ink or other erasable or semi-permanent media shall


not be used.

Execution
General
A. The location of all equipment, controls, piping, valves, and drains shall be
subject to the Contractor, Project Manager / Professional Team approval.

B. Sprinkler piping located in clean air spaces shall be painted.

Piping
Submittals
1. Contractor shall submit a weld procedure specification (WPS) to the Project
Manager / Professional Team for approval for all pipe and tube welding.
2. Contractor shall submit a procedure qualification record (PQR) to the Project
Manager / Professional Team approval.

Annexure [6] Page 559 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Piping Fabrication
1. The welder or welding machine operator shall stamp an imprint of their
identification into the side of the pipe adjacent to each weld in accordance to
standard.

2. Piping in all clean room areas and adjacent service corridors shall have all joint
compound cleaned from exposed threads and piping shall be otherwise cleaned
and installed as required by Section - Clean Zone General Requirements.

3. All exposed piping which passes through an exterior or interior wall, ceiling, or
floor shall be provided with metal, chrome finish escutcheon plates.

4. All piping shall be installed at a height so as to not obstruct any portion of a


window, doorway, stairway, or passageway, shall not reduce any exitway
clearance, and shall not interfere with the installation, operation, or accessibility of
any mechanical, plumbing, or electrical equipment. Piping shall not be installed
within the required clearance of any electrical equipment.

5. Pipe which passes through any blast resistant barrier shall be grouted to maintain
the tightness of the barrier with flexible couplings installed in accordance with FM
GLOBAL DATA SHEETS and Section 15071, Mechanical Sound and Vibration
Control, on each side of the barrier. All sleeves in fire- and smoke-rated barriers
shall be sealed to maintain the fire or smoke rating, using approved materials and
methods. Seals shall be in accordance with Section 07900, Joint Sealers.

6. Installation of sprinklers in exhaust ducts shall be coordinated with the duct


installer. The duct installer shall provide the sleeve, install cement-bottom
mounting block to ductwork and seal ductwork.

7. All piping shall be independently supported from the structure in all areas requiring
vibration isolation. Piping shall not be suspended from any other equipment, or
from any hangers or supports for any other equipment, in any area where vibration
isolation is required. Piping and hangers shall not be installed so as to come in
contact with any equipment, piping, conduit, or ductwork requiring vibration
isolation. Piping hangers and sway bracing shall not be rigidly connected to duct
walls or to any non-masonry wall. Support piping in accordance with FM GLOBAL

Annexure [6] Page 560 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

DATA SHEETS and section 15061, Piping Support and Anchors, whichever is
most stringent

8. Piping shall be installed without bending or placing undue stress on the pipe,
clear lighting fixtures, air ducts, overhead track doors, and other obstructions.
Piping

9. Piping shall be installed to level, plumb, and parallel to structure line except where
shown otherwise or required by function or regulation to be angled or sloped.

10. Piping shall be concealed within spaces provided in the structure except where
shown as exposed.

11. Install piping to allow for expansion, contraction, and structural settlement.

12. Support vertical piping at each floor level and at each fitting between floors. Install
coupling in piping at floor support; riser clamp shall rest on and transmit load to
support. Supports above the lowest level shall also resist movement by any
upward thrust where flexible fittings are used.

13. Stainless steel corrugated flexible pipe(hose) for dropping sprinklers below false
ceiling, pipe shall be 16 bar pressure rating and 1500 mm long 25 mm dia with
union / reducer collar, clamps etc and approved type rosette plates ( Recessed
type, in two piece) for Sprinklers below false ceiling area, The Rosette shall be
fabricated by M.S. plate of 2mm thick and the finish shall be powder coated and
color shall be as approved by architects / clients as required. Flexible pipe shall be
UL listed.

14. Piping Penetrations:

Annexure [6] Page 561 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

 Where pipes penetrate members of the structure, install proper sleeves,


packing, flashing, and collars as follows unless shown otherwise. All
penetrations must provide 25mm annular space for piping less than
100mm in diameter and 50mm annular space for piping 100mm
diameter and larger.
 At exposed face of wall, floor, ceiling, or soffit, fit penetrating pipe with a
neat, rigid, securely attached collar or escutcheon. In unfinished areas
use galvanized plate; in finished areas use chrome plate escutcheon.
 Piping that penetrates fire rated or smoke rated walls, floors or ceilings
shall be fitted with insulated and encased pipe sleeves manufactured by
approved vendor.

15. Weld neck flanges shall be used with butt weld fittings unless specified

16. Slip on flanges shall be welded inside and outside. The seal weld shall be applied
so that flange face shall be free of weld spatter.

17. Threaded bolt shall be coated with Never – seez prior to being made up with nuts.
For Clean rooms low outgassing thread lubricants shall be used.

Piping supports and anchors


Submittals

Following shall be submitted by the contractor:


1. Hanger and support framing and attachment methods, prior to installation.
2. Load capacities for each hanger and support system proposed.
3. Proposed hanger location drawings.
4. Load calculations and component selection method for contractor designed
supports.
5. As built hanger location drawings, prior to pressure testing the pipe.

Annexure [6] Page 562 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Design Criteria
1. All hangers, rods, clamps, protective shields, metal framing support
components, and hanger accessories shall be electro galvanized or cadmium
plated..

Annexure [6] Page 563 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Fabrication and Erection


1. All materials required for adequate pipe support, such as Unistrut or steel
framing, shall be provided and installed by the Contractor.
2. Slotted channel supports shall be provided in accordance with relevant
standards.
3. All piping shall be supported in a manner which will prevent undue stress on
any valve, fitting, In addition, pipe supports shall be provided at changes in
direction or elevation, adjacent to flexible couplings, and where otherwise
shown. Pipe supports and hangers shall not be installed in equipment access
areas.
4. Where horizontal piping is arranged with two or more parallel lines, trapeze
hangers may be used in lieu of individual hangers. Trapeze assembly shall
consist of structure attachments as previously specified with rod size
dependent upon the total weight supported, spacing of assemblies determined
by the minimum pipe size included in the group supported. Trapeze horizontal
shall be a structural angle or channel section of sufficient size to prevent
measurable sag between rods, all lines attached to the horizontal with
intermediate pipe guides and U-bolts or one-hole clamps. Pre-engineered
support equipment may be used when selected and installed in accordance
with the manufacturer’s recommendations.
5. Horizontal piping hanger support rods shall attach to steel beams with
center-loading I-clamps, to concrete with inserts or flanges fastened with flush
shells, to wood not less than 65mm thick with lag screws and angle clips.
6. During installation, square, debur, and paint saw-cut ends promptly. In areas
where channel encroaches into aisles, egress, etc., provide cap on ends.
7. Provide inserts for suspending hangers from reinforced concrete slabs and
sides of reinforced concrete beams.
8. Provide hooked rod to concrete reinforcement section for inserts carrying pipe
over 100mm.
9. Where concrete slabs form finished ceiling, provide inserts flush with slab
surface.
10. No piping 200mm or larger shall be suspended from embedded slotted
channels.
11. Pipe hangers suspended from embedded slotted channels shall not be less
than 150mm from end of embed.

Annexure [6] Page 564 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

12. Piping loads at inserts shall not exceed the maximum rated point load or
minimum spacing indicated on the insert manufacturers data sheets and
drawings.

Piping Maximum Hanger Spacing shall be as per FM global datasheet 2-0

Pipe Size Water Service Rod Hanger Diameter


(Steel Pipe) (Steel Pipe)
15mm -- 10mm
15mm to 25mm 2.1m 10mm
25 to 40mm 2.1 10mm
40mm 2.7m 10mm
50mm 3m 10mm
65mm 3m 10mm
75mm 3m 10mm
100mm 4m 10mm
150mm 4m 12 mm
200mm 4m 12 mm

Notes: Use these maximum hanger spacing unless stated otherwise on the
Drawings.

8.1 Test And Drain Valves

1. Drain and test valves shall be located within 1200mm of the floor and in an
accessible location. Estimated flows are 227lpm for an inspector’s test drain and
1514lpm for a 50mm riser drain.

2. Install main drain at main risers and auxiliary drains at low points in the system.
Install inspector’s test drain at most hydraulically remote point in each system.
Use angle type drain valves. Five gallons or less may be drained through a
plugged fitting. Pipe drain valves to discharge, as approved by the Contractor,
Project Manager / Professional Team, to sanitary receptor within buildings.

Annexure [6] Page 565 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

3. Vents and drains at all high and low points in the piping that are required for
complete venting and draining shall be considered by the contractor during
detailed piping design.
4. Each vent or drain pipes shall be welded to header shall have hose bib connection
and cap.

Control Valves

1. In addition to the requirements of Section - Mechanical Identification, provide


identification signs on control valves indicating the portion of the total system
controlled by the respective valve. Install on valve or on wall near valve location.
Valve shall be installed within 1800mm of the floor.

2. Control valves shall meet the accessibility requirements. Coordinate with the
Contractor, Project Manager / Professional Team on appropriate access for
control valves.

Annexure [6] Page 566 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Tests
Upon completion of the installation of fire sprinkler system, the Contractor shall
perform acceptance tests as required and outlined by consultant/client/PMC and
as required by the authorities having jurisdiction. The Contractor shall notify the
Professional Team, in advance of scheduled test, to allow that authority an
opportunity to witness tests. Upon acceptance of the fire sprinkler system by the
inspecting authority, inform the Professional Team, in writing, showing proof of
acceptance by the inspecting authority. All cost related to test should be borne by
the contractor.

Prior to connecting the underground fire mains to building piping the Contractor
shall flush and test the underground piping. Flushing and testing of underground
pipe by the Contractor shall be separate from, and in addition to, any requirements
of the site contract. Testing of underground piping shall be accomplished with the
center weight loading of pipe and joints exposed. Joints installed by other
contractors shall remain exposed unless previously tested and covered by the fire
protection Contractor. Provide notification as noted above. The flushing
connections should not be dismantled till the acceptance testing of the complete
system is not carried out.

Testing:
1. Testing shall be performed by the contractor on all piping after erection but before
any installation of insulation.
2. Testing shall be required for the sections which are modified or repaired after
initial pressure test is conducted and completed.
3. Pressure test all pipes to a hydrostatic pressure of 200 psi, or at 50 psi in excess
of the maximum pressure when maximum pressure to be maintained in the
system is in excess of 150 psi, for a minimum of 2 hours with no visible pressure
drop. The pressure test shall not be less than 2 hours without prior written
approval from the Project Manager / Professional Team.
4. Other tests shall be conducted as directed by the governing agencies.
5. A pressure test report shall be submitted to the Project Manager / Professional
Team at the end of the work.
6. Sprinkler installations consisting of three sprinkler heads or less may be
assembled and tested in the shop. Installations consisting of four sprinkler heads

Annexure [6] Page 567 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

or more must be field tested and witnessed by Project Manager / Professional


Team.
7. Completed contractor’s material and test certificates for fire protection system
shall be submitted to the governing agencies.
Submittals
Contractor shall submit a weld procedure specification (WPS) to the Project
Manager / Professional Team for approval for all pipe and tube welding.
Contractor shall submit a procedure qualification record (PQR) to the Project
Manager / Professional Team approval.
Copies of test reports shall be provided to clients.

Project Record Documents

At close of project, the Contractor shall submit to Clients all welding installation
records which shall include weld examination procedures, weld examinations,
weld logs, welder qualification examinations, pressure tests, and leak tests.

Annexure [6] Page 568 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Testing procedure:
1. The Contractor is responsible for providing the necessary test gauges. The
gauges shall have plus or minus 0.25 percent accuracy and a 100mm dial or
larger.
2. Calibration records for gauges used for testing shall be submitted to the
Contractor. Gauges used for testing shall be calibrated once per year.
3. One pressure gauge shall be installed for each testing system. Gauges used for
testing shall be installed as close as possible to the low point of the piping system.
4. When starting the filling of lines to be hydrostatically tested, all vents and other
connections that can serve as vents shall be open during filling so that all air is
vented prior to applying test pressure to a system.
5. If the maximum operating conditions of piping attached to a vessel are the same
as those of the vessel, then the piping and the vessel may be tested together.
However, if the vessel has different maximum operating conditions, then it must
be isolated and tested separately.
6. Valves shall be tested at the same time that the adjacent pipeline is tested. Joints
shall show no visible leakage under test. Repair joints that show signs of leakage
prior to final acceptance. If there are any special parts of control systems or
operators that might be damaged by the pipeline test, they shall be properly
protected. The Contractor shall repair or replace, to the satisfaction of the
Contractor, any valve damaged by the testing.
7. Valves shall not be used as blanking devices for the hydrostatic test.
8. Examination for leakage shall be made at all joints and connections. The piping
system shall show no visual evidence of weeping or leaking. Any visible leakage
shall be corrected at the Contractor’s sole expense.
9. If the pressure falls after the pressurizing system is shut off, the source of
pressure loss must be determined and corrected.
10. Pressure drop in leak test shall be zero, after correction for temperature variation
allowance, unless specified otherwise in Table 2, Piping Schedule.

Testing Media Requirements:

1. Clean, fresh city water shall be used for hydrostatic testing,


2. After hydrostatic testing, all water shall be drained immediately. Authorization is
required prior to discharging water containing oils or chemicals being drained to
the public waste system. Coordinate with Project Manager / Professional Team

Annexure [6] Page 569 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

before any discharge to the public waste system. Care shall be taken not to pull a
vacuum during draining by opening all vents.
Test Repairs:
1. Materials such as gaskets, bolting, etc., damaged during tests and flushing shall
be replaced.
2. New gaskets shall be used each time a flanged joint is made up.
3. Any welded joint that is defective shall be repaired in accordance with the
applicable requirements. Repaired components shall be reexamined by the
original method to determine freedom from defects and all repaired joints shall be
retested. Costs for such repair shall be the responsibility of the Contractor.
4. Test Records: Records shall be made by the Contractor for each piping
installation. These records shall include, at a minimum, the following items:
 Date of test.
 Description and identification of piping tested.
 Test fluid.
 Test pressure.
 Test duration.
5. Remarks, to include such items as:
 Leaks (type, location).
 Repairs made on leaks.
5. Signature and date of persons performing and witnessing the test at start and
at completion. Witnessing shall be by Project Manager / Professional Team
representative.
6. Certification by Contractor and reviewed by the Contractor/QA

Cleaning/Flushing Piping Systems


Prior to final acceptance, liquid pipelines shall be flushed with water and all
accumulated construction debris and other foreign matter removed.

Annexure [6] Page 570 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

1. Flushing velocities shall be a minimum of 3m per second.


2. Cone strainers shall be inserted in the connections to attached equipment and left
there until cleaning has been accomplished to the satisfaction of Project Manager
/ Professional Team under supervision of the water treatment manufacturer's
representative.
3. Accumulated debris shall be removed through drains 50mm and larger or by
dropping spools and valves.
4. For large diameter pipe and tanks that are impractical or impossible to flush at
0.76m/s velocity, clean in place from the inside by brushing and sweeping, then
flush at a lower velocity.
5. Provide jumpers between supply and returns sufficient to accomplish flushing of
all piping with no dead legs.
6. Hydro testing and flushing water containing no chemicals or oils can be drained to
sewer line.
7. Water containing chemicals or oils must be drained to the acid waste system.
8. Coordinate with PMC before any discharge to the acid waste system.

Final Approval And Acceptance


Final approval and acceptance of the Work will be given by the Professional Team when:

1. The completed wet pipe sprinkler system has been inspected, tested and
approved by PMC/Consultant/client and the building and fire departments of the
authority having jurisdiction.

2. Required submittals, system operation and maintenance manuals, as-built


drawings, spare parts, and training have been provided to, reviewed, and
accepted by the Professional Team.

Training
The Contractor shall conduct two training sessions of four hours each to
familiarize Client’s personnel with the features, operation, and maintenance of
the sprinkler systems. Training sessions shall be scheduled by the Contractor
at a time mutually agreeable to the Contractor and Clients.

Service
The Contractor shall be prepared to provide emergency service on the
completed system within 4 hours of a request from clients. The Contractor

Annexure [6] Page 571 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

shall submit in writing, a proposal to provide this service, including location of


the nearest facility, names of service people, and expected hourly rates.

Sprinkler main, branch and internal piping complete with valves, alarms and supporting
arrangements. Sprinkler heads with spare sprinklers. Connections to risers etc., all
material shall be of the best quality conforming to specifications and subject to the
approval of the Engineer-in-Charge. Pipes and fittings shall be fixed truly
vertical/horizontal or on slopes required in a neat manner. Pipes shall be fixed in such
a manner so as to provide easy accessibility for repair and maintenance and shall not
cause obstruction in shafts, passages etc., Pipes shall be securely fixed to walls and
ceilings by suitable clamps at intervals specified. Only approved types of anchor
fasteners shall be used for RCC ceilings and walls. Valves and other equipment shall
be so located that they are easily accessible for operation, repairs and maintenance.

1.1 SPRINKLER HEADS

The sprinkler heads shall be UL listed fixed temperature type with a quartzoid bulb
containing liquid having high vapor pressure held in position by a forged GM yoke and
deflector. The rated temperature of quartzoid bulb shall be 68 deg. C. The spacing
shall however conform to the detailed drawing, in Co-ordination with electrical and
other allied services at the ceiling level. Sub-contractor shall supply spare sprinkler
heads and spanners neatly installed in a steel box with glass shutter at an appropriate
position approved by the Engineer-in-Charge.
A water motor gong and an inspection test connection shall be provided on the down
streamside of the system.
Sprinklers for below false ceiling shall be fixed with recessed (two piece) type Rosette
plate fabricated by M.S. sheet of 2mm thick with Powder coated finish of approved
color. Also note sprinklers for below false ceiling shall be dropped by using flexi pies of
approved make & size and length.

1.2 PIPES AND FITTINGS

Pipes for the sprinkler system shall refer to the clause No. 2.0, 11.0, 12.0 and 13.0 of
Section - A above.

Annexure [6] Page 572 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

C. ELECTRICAL WORKS

1.0 ELECTRICAL WORKS

1.1 General

The CONTRACTOR shall supply and install the electrical equipment and services
necessary for the efficient and safe operation of the fire protection systems detailed
elsewhere in the specification, including :-

(a) Motors for Fire water pumps.

(b) MCC cum control panel housing the starters for all motors and complete with the
switches, relays, push buttons, indicating lamps, etc. necessary for the control of the
fire protection system

(c) Power and control cabling between the MCC, motors, pressure switches, etc. including
accessories like conduits, cable trays, etc.,

(d) To carry out the electrical installation works in accordance with specifications and as
required by the local statutory departments.

(e) To include the preparation of shop drawings and construction drawings for submission
to the Consulting Engineers to review prior to construction. Final as-built drawings after
commissioning of the Fire Protection System.
1.2 ELECTRIC MOTORS

The motor shall be as per IS: 325 and with class “F” insulation, totally enclosed fan
cooled, horizontal induction foot mounted type and rated not to draw starting current
more than 6 times normal running current. Motor shall be capable of driving the pumps
at rated discharge and head & at 150% of its rated discharge at 65 % of the rated head
(in any case 15 % safety load should add) and shall be designed for continuous full
load duty. The motor shall be capable of handling the required starting torque of the
pumps. Speed of motor shall be compatible with the speed of the pump. The cooling
fans shall be directly driven from motor shaft. Motor situated outdoors or exposed to
the weather shall be weather protected. Motors shall be enclosed type and shall have
dust tight construction with suitable means of breathing and of drainage to prevent
accumulation of water from condensation. Drain holes shall exclude bodies greater
than 6mm diameter.

Annexure [6] Page 573 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

All components shall be of adequate mechanical strength and robustness and shall be
constructed of metal unless otherwise approved. All motors shall be dynamically
balanced.
The enclosure shall be designed to provide an effective sealing between the primary
and secondary air circuits. Motor winding shall be vacuum impregnated with heat and
moisture resistant varnish glass fiber insulated. Two independent earthing points shall
be provided in accordance with IS: 3043 on opposite sides of the motor for bolted
connection. The cable boxes and termination shall be designed to enable easy
disconnection and replacement of cables.

2.0 LT SWITCH BOARDS / SWITCH GEAR/ SUB MAIN SWITCH BOARDS

2.1 GENERAL SPECIFICATION OF EQUIPMENT

The switch board shall be metal clad, totally enclosed, rigid, compartmentalized
design, floor mounting, air insulated, extensible cubicle type for use on medium voltage
power, 3 phase 4 wire 50 cycles system. The degree of protection shall be of IP55
incase of outdoor application as detailed in BOQ. The equipment shall be designed for
operation in high ambient temperature and high humidity tropical atmospheric
conditions. Means shall be provided to facilitate ease of inspection, cleaning and
repairs for use in installations where continuity of operation is of prime importance.
The entire logic of the fire protection system shall be built in this panel. It shall have
necessary relays/contactors for accepting contacts from Pressure/limit switches and for
switching ON/OFF motors accordingly. It shall have ammeter, voltmeter, start / stop
push buttons, manual and automatic selector switches, pumps on, off, trip indicating
lamps, relays and other control equipment necessary for the efficient indication and
operation of the system. A visual and audio alarm shall also be provided to raise an
alarm when any of the pumps is tripped. It shall have provision for annunciating the
water tank water level high / low / overflow conditions.
Provision shall be made for interfacing with the Building Automation system. Potential
free contacts for motors ON / OFF / TRIP, MCC trouble and fire water tanks level
LOW/HIGH/OVERFLOW conditions be provided in the control panel for BAS. Also
provision shall be made for receiving signals from BAS.
The control unit will be capable of providing Modbus RTU or RS 485 output to the BMS

system for the following parameters:


a) Flow switch/limit switch at all valves.

Annexure [6] Page 574 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

b) Differential pressure transmitter at the outlet headers of Hydrant and


sprinkler header and at topmost level tapping.

2.2 STANDARDS

Following equipment shall conform to the requirements of:


Air Circuit Breaker (ACB) - IS 13947 - 1,2 / IEC 947 - 1,2
Moulded Case Circuit Breaker (MCCB) - IS 13947 - 1,2/ IEC 947 - 1&2
Contactors - IS 13947 - 1,4
Miniature Circuit Breaker (MCB) - IS 8828 - 1996/ IEC 898 - 1995
Residual Current Circuit Breaker (RCCB) - IS 12640 - 1988 / IEC 1008
HRC fuse link - IS 9224 and BS 8:8
Current Transformer - IS 2705 and IEC 185
Potential Transformer - IS 3156
Relay - IS 3231 & IS 8686 (For Static Relays)
Indicating Instrument - IS 1248

2.3 CONSTRUCTION

The switch board shall be:


Sheet steel enclosed, indoor floor mounted free standing cubicle type. Made up of the
requisite vertical sections modular type which when coupled together shall form
continuous dead front switchboards. Dust, vermin and damp proof and enclosure
protection not less than IP 55. Each feeder/instrument compartment shall be
provided with a hinged door interlocked with MCCB/SFU inside the compartment
such that door can only be opened when MCCB/SFU in off position. Readily
extendable as required by the addition of vertical sections after removal of the end
covers. Switch boards shall have access to the feeders, bus bars, cable termination,
cable alley, etc. as required.

2.4 EACH VERTICAL SECTION SHALL COMPRISE

A front framed structure of rolled/folded CRCA sheet steel angle section of minimum 3
mm thickness rigidly bolted together. This structure shall house the components
contributing to the major weight of the equipment such as circuit breaker cassettes,
fuse switch units, main horizontal bus bars, vertical risers and other front mounted
accessories. The structure shall be mounted on a rigid base frame of folded CRCA

Annexure [6] Page 575 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

sheet steel of minimum 6 mm thickness and 75 mm height. The design shall ensure
that the weight of the components is adequately supported without deformation or
loss of alignment during transit or during operation. A cable chamber housing the
cable end connections and power/control cable terminations. The design shall
ensure generous availability of space for ease of installation and maintenance of
cabling and adequate safety for working in one vertical/horizontal section without
coming into accidental contact with live parts of the adjacent section. A cover plate at
the top of the vertical section, provided with a ventilating hood where necessary. Any
aperture for ventilation shall be covered with a perforated sheet having less than 1mm
diameter perforations to prevent entry of vermin. Front and rear doors fitted with dust
excluding neoprene gaskets with fasteners designed to ensure proper compression of
the gaskets. When covers are provided in place of doors generous overlap shall be
ensured between sheet steel surfaces with closely spaced fasteners to preclude the
entry of dust. The height of the panel shall not be more than 2200 mm unless
otherwise specified and maximum height of operating handle shall not be more than
1800mm from FFL. The total depth of the panel shall be adequate to cater to proper
cabling space. Doors shall be of minimum 14 gauge sheet steel and covers/partitions
of 16G sheet steel. All sheet steel work forming the exterior of switchboards shall be
smoothly finished, leveled and free from flaws. The corners should be rounded. The
Components in the switch boards shall be so arranged as to facilitate ease of operation
and maintenance and at the same time to ensure necessary degree of safety.
Components forming part of the switchboards shall have the following minimum
clearances:
Between phases - 25mm
Between phases and neutral - 25mm
Between phases and earth - 25mm
Between neutral and earth - 19mm

When, for any reason, the above clearances are not available, suitable insulation
barrier/shielding shall be provided. Clearances shall be maintained during normal
service conditions. Creep age distances shall comply with those specified in relevant
standards. All insulating material used in the construction of the equipment shall be of
non-hygroscopic material treated to withstand the effects of high humidity, high
temperature and tropical ambient service conditions. Functional units such as circuit
breakers, fuse switches, MCCBs, etc. shall be arranged in multitier formation except
that not more than two air circuit breakers shall be housed in a single vertical section.

Annexure [6] Page 576 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Metallic/insulated shrouding shall be provided within vertical sections and between


adjacent sections to ensure prevention of accidental contact with: Main bus-bars and
vertical risers during operation, inspection or maintenance of functional units and front
mounted accessories. Cable terminations of one functional unit, when working on
those of adjacent unit/units. All covers providing access to live parts/circuits
shall be provided with tool operated fasteners to prevent unauthorized access.
Provision shall be made for permanently earthing the frames and other metal parts of
the switchgear by two independent distinct connections. Only CRCA steel sheets shall
be used for fabricating the cubicle. Thickness tolerance for sheets shall be as
applicable in relevant IS.

2.5 METAL TREATMENT AND FINISH

Generally the treatment and finish of the metal surface shall be as per detailed
specifications enumerated elsewhere in this document.

DEGREASING

Effective cleaning by hot alkaline degreasing solution followed by cold water rinsing to
remove traces of alkaline solution.

PHOSPHATING

A recognized phosphate process to facilitate durable coating of the paint on the metal
surfaces and also to prevent the spread of rusting in the event of the paint film being
mechanically damaged. This again shall be followed by hot water rinsing to remove
traces of phosphate solution. Drying in dust free atmosphere.

Primer: Primer coating with a coat of corrosion resistant primer applied on wet
Surface.

Finish coat: Two finishing coats of stoving synthetic enamel paint to the specified
shade of IS: 5. both the finish shall be only spray painted or powder coating. For
outdoor units the finishing coat shall be of weather resistant stoving epoxy paint of
specified shade of IS5.

2.6 BUS BARS

The bus bars shall be made of high conductivity high strength E91E aluminum alloy
suitable for 415 volts, 3phase 4 wires 50 Hz 20KA unless otherwise specified. The bus

Annexure [6] Page 577 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

bars shall be suitably supported with non-hygroscopic supports to provide a fault


withstand capacity as specified. High tensile bolts and spring washers shall be
provided at all bus bar joints. Fish plates of equal type and size shall be used at all
joints. The bus bars shall have uniform cross section throughout and shall be capable
of carrying the rated current at 415V continuously. The bus bars shall be designed to
withstand a temperature rise of 45 Deg. C above the ambient. A current density of
1.00 Amp/Sqmm shall not be exceeded for Aluminum bus bars.
The neutral bus bars shall have a continuous rating of at least 50% of the phase bus
bars, unless mentioned otherwise. Bus bars shall be fully sleeved using heat shrunk
PVC sleeves appropriately colour coded to identify different phases and neutral bar. An
earth bus of size not less than 40 x 6 mm aluminum/GI shall run throughout the length
of switch board at top or bottom as required.

2.7 MCCB - MOULDED CASE CIRCUIT BREAKER

The Moulded Case Circuit Breaker shall be incorporated in the switch board wherever
specified and shall be of the current limiting type. MCCB shall conform to IS 2516, IS
13947-1/ IEC 947-1 (part I & II / section 1) 1977 for general rules. It should be suitable
for Horizontal and Vertical mounting and line load reversibility. MCCB shall be suitable
either for Single Phase AC 230V On Three Phase 415V. The MCCB shall be available
in four pole versions for neutral isolation. It shall have tropicalisation as standard
feature.
The MCCB cover and case shall be made of high strength heat-resistant and flame-
retardant thermosetting insulating material. The operating handle shall be quick make,
quick break, trip - free type. The operating handle shall have suitable `ON' `OFF'
`TRIPPED' indicators and in order to ensure suitability for isolation complying with IS
13947-2/IEC947-2, the operating mechanism shall be designed such that the toggle or
the handle can only be in `OFF' position : if the main contacts are actually separated.

NOTE: MCCB’s on oncoming side should be motor operated type of suitable


rating.

2.8 ACCESSORIES

MCCB shall be designed to have following accessories and it shall be fittable at site.
Under voltage trip, Shunt trip, Alarm switch, Auxiliary switch, Remote operation using
motor mechanism with facility of using the same in auto/manual mode.

Annexure [6] Page 578 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

2.9 INTERLOCKING
MCCB shall be provided with following interlocking devices for interlocking the door of a
switch board. Handle interlock to prevent unnecessary manipulations of the breaker.
Door interlock to prevent door being opened when breaker is in ON position. The
interlocking device to open the door even if he breaker is in ON position. In addition to
the above, ant other features indicated in the Bill of Quantities shall also be provided.

2.10 BREAKING CAPACITY

Short time with standing capacities different ratings of MCCB's shall be as follows:
Ratings Breaking Capacity
[Amps] [KA]
01. Upto 400 35
02. 630 to 800 50
03. 1000 & Above 65

2.11 CONTACTORS

Contactor shall comply with IS 13947-1 for general rules and IS 13947 - 4.1 for
Standards pertaining to Contactor and Motor Starter. The Contactors shall be capable
of withstanding breaking and making capacities per following
AC3 category AC4 category
Making Current 10 x Rated Current 12 x Rated Current
Breaking Current 08 x Rated Current 10 x Rated Current

Contactor shall be capable of withstanding an impulse voltage of 8KV and have an


insulation voltage of 1000V. Contactor shall be suitable for aluminum termination with
a maximum permissible temperature rise of 650 C at the terminals with an ambient
temperature of 500 C. The coils shall have three terminals and the insulation should be
of class H type. The auxiliary contact block shall have a switching capacity of 220V,
2A. Contactor shall have one auxiliary in built and it should be possible to have
additional NO/NC contacts in steps of two. Miniature Circuit Breakers [MCB] :
MCB shall be in 1,2,3,4, pole versions. MCB casing shall be made of self
extinguishing, tropicalised material. MCB shall comply with IS 8828-1996/IEC 898-
1995. It shall be suitable for use in frequency range 40Hz to 60Hz and shall
accommodate AC/DC supply according to requirements. It shall have a trip-free
mechanism and toggle shall give a positive contact indication. It shall be suitable for
mounting on 35mm DIN rail/surface mounting. It may be installed horizontally, vertically
on the ceiling in any place without any change in electrical performance. Line supply

Annexure [6] Page 579 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

may be connected to either top or bottom terminals i.e. There should be no line-load
restriction. Degree of protection when the MCB is flush mounted shall be IP40. MCB
shall be supplied with clamping terminals fully open. Contact closing shall be
independent of the speed of operator. The breaking capacity of the MCB shall be
9KA/10KA. The MCB shall be capable of being used as Incomer Circuit Breaker and
shall be suitable for use as isolator. In case of multiple MCBs in a single location (DB),
it should be possible to remove any MCB without having to disturb other MCB in the
vicinity.

2.12 RCCB - RESIDUAL CURRENT CIRCUIT BREAKER

RCCB shall be available in 2 pole and 4 pole versions and threshold sensitivities of
30mA, 100mA, 300mA and current ratings from 25 to 80A. Rating and sensitivities
shall be as per Schedule of Quantities. RCCB shall comply with IS 12640-1988/IEC
1008. The short circuit withstand of the RCCB without the associated short
circuit/overhead protection shall not be less than 3 KA. It shall be operationally
independent of line voltage. The sensitivity thresholds (30mA, 100mA, 300mA) shall be
of nonuser adjustable type by construction.

2.13 FUSE SWITCH UNITS / SWITCH FUSE UNIT

The FSUs / SFUs shall be of the load break heavy duty cubicle type conforming to the
requirements of IS 4064 1978 (AC23 duty) and IS : 13947-1993.The fuse switch units
shall be double break and shall have quick make and quick break mechanisms
designed to ensure positive operation. The unit shall be provided with a front operating
handle. The ON and OFF positions of the switch handle shall be clearly marked. The
handle coupling arrangement shall conform to IS: 8623-1977.Interlocks shall be
provided so as to prevent opening of the unit door when the switch is in the ON
position and also to prevent closing of the switch with the door not properly secured.
It should, however, be possible for competent examiner to operate the switch with the
door open by releasing the interlock. The interior arrangement of the switch unit shall
be such that all 'live' parts are shrouded.

2.14 CURRENT TRANSFORMERS

Current transformer shall comply with the requirements of IS 2705. They shall have
ratios, outputs and accuracy as specified/required. All CT's shall be of resin cast type
unless otherwise specifically called for. All CT's shall be of bar type primary or suitable

Annexure [6] Page 580 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

for the cable given type and size and the CT’s shall be provided with shorting links
irrespective of the CT’s ratio’s preferably with ELMEX / PHOENIX. For all the CT's
suitable type and size clamps are to be supplied for mounting in the switch boards.
Polarities and terminal markings of primary and secondary shall be clearly marked on
all CT's.
Specifications for CT’s:

a. Current Ratios :
i. Primary : As per feeder ratings
ii. Secondary : 5A
b. Type : Resin Cast

c. Class : PS-Differential Protection


5P10-O/C,E/F, RPR
Class 1 for metering
d. System Voltage
i. LT : 415V 3Ph 50Hz

2.15 INSTRUMENTS & METERS

All instruments and meters shall be enclosed in dust proof, moisture resistant, black
finished cases and shall be suitable for tropical use. They shall be calibrated to
read directly the primary quantities. They shall be accurately adjusted and calibrated at
Works and shall have means of calibration, check and adjustment at site.

2.16 INDICATING INSTRUMENTS

Indicating instruments shall be flush mounted with anti-parallel white circular scales
with black pointer and with black numbers and lettering. Knife edge pointers shall be
preferred. Unless otherwise specified, the size of all instruments shall be 144mm x
144mm type. The dials shall be free from warping, fading and discolouring. Spring
controlled instruments shall be provided with front of board zero adjuster, capable of
being safely handled while the instrument is in Service. Instrument covers shall also
have red marks on the dial corresponding to rated values of the associated primary
equipment. Synchronizing instruments shall also meet the requirements of this clause.
The indicating instruments shall conform to IS: 1248 and shall have on an accuracy
class of 1. The Ammeter and Wattmeter current coils shall withstand 200% of rated
current continuously and 10 times the rated current for 0.5 seconds without loss of

Annexure [6] Page 581 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

accuracy. Voltmeter and Wattmeter potential coils shall withstand 120% of rated
voltage continuously and twice the rated voltage for 0.5 sec. without loss of accuracy.

2.17 VOLTMETER

Voltmeter shall be suitable for operating directly on LT supply voltage 415V, 50Hz or
with a PT as per the requirements. All the Voltmeters used for rated operating Voltage
of 415/110V as required at 50Hz AC. With a scale as required at site.
All Voltmeters are 144 x 144mm, suitable for mounting on the panel. Type Sl.No.
accuracy class and borders of the Voltmeter shall be indicated on the dial.

2.18 AMMETER

All the Ammeters shall be CT operated (5A) with a dial marked for line currents.
Type, Sl.No. Accuracy class, Operating Current, Burden etc., shall be indicated on the
dial. All Ammeter shall be of panel mounting type and shall be provided with zero
setting screw.

2.19 PUSH BUTTONS

Push buttons shall be of momentary contact type with rear terminal connection. These
shall be suitably shrouded to prevent inadvertent operation. Integral inscription plates
engraved with their functions shall be provided. All push buttons shall have two
Normally Closed and two Normally Open contacts comprising rivets of pure silver. The
contacts shall be able to make and carry 5 A and breaks up one amp inductive load at
250V DC.

2.20 CABLE TERMINATIONS

Cable entries and terminals shall be provided in the switch board to suit the number,
type and size of aluminium conductor power cables and copper conductor control
cable specified in the detailed specifications. Provision shall be made for top or bottom
entry of cables as required. Generous size of cabling chambers shall be provided with
the position of cable gland and terminals such that cables can be easily and safely
terminated. Barriers or shrouds shall be provided to permit safe working at the
terminals of one circuit without accidentally touching that of another live circuit. Cable
risers shall be adequately supported to withstand the effects of rated short circuit
currents without damage and without causing secondary faults. Cable sockets shall be
of tinned copper and of the crimping type.

Annexure [6] Page 582 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

2.21 CONTROL WIRING

All control wiring shall be carried out with 1100V grade single core PVC cable having
stranded copper conductors with minimum cross section of 1.5 Sq.mm for potential
circuits and 2.5 Sq.mm for current transformer circuits. Wiring shall be neatly bunched,
adequately supported and properly routed to allow for easy access and maintenance.
Wires shall be identified by numbered ferrules at each end. The ferrules shall be of
ring type and of non-deteriorating material. They shall be firmly located on each
termination so as to prevent free movement. All control circuit fuses shall be mounted
in front of the panel and shall be easily accessible.

2.22 TERMINAL BLOCKS

Terminal blocks shall be of 500 Volts grade and of stud/screwless type. Terminal blocks
shall have a minimum current rating of 10 Amps and shall be shrouded. Provisions
shall be made for label inscriptions. At least 20% spare terminals shall be provided on
each panel and these spare terminals shall be uniformly distributed on all terminal
blocks.
Terminal blocks for current transformer and voltage transformer secondary leads shall
be provided with test links and isolating facilities. Also current transformer secondary
leads shall be provided with short circuiting and earthing facilities.
There shall be a minimum clearance of 250mm between the first row of terminal blocks
and the associated cable gland plate. Also, the clearance between two rows of terminal
blocks shall be a minimum of 150mm.

2.23 RELAYS

All Relays shall conform to the requirement of IS: 3231/IS 8686 or other applicable
approved standards Relays shall be suitable for flush and Semi-flush mounting on front
At with connections from the rear. All Protective Relays shall be of draw out or plug in
type/Modular cases with proper built in test facilities. Test blocks and switches shall be
located immediately below each relay for testing. The auxiliary relays shall be self
reset type. All AC Relays shall be suitable for operation at 50Hz. AC Voltage operated
relays shall be suitable for 110/v3 Volts PT secondaries and Current operated relays
for 5Amp. CT. secondaries as specified in this specification. Voltage operated relays
shall have adequate thermal capacity for continuous operation. Auxiliary Relays and

Annexure [6] Page 583 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Timers shall have pairs of contacts as required to complete the scheme. Contacts
shall be silver faced with spring action.
All Protective Relays, Auxiliary Relays and Timers except the lockout relays and
interlocking relays specified shall be provided with self reset type contacts. All, Trip
and Timers shall be provided with externally hand reset positive action provided with
inscription subject to /Consultant approval. Timers shall be of the electromagnetic or
solid state type.
Wherever solid state relays are used the following requirement shall be met with:
All Relays shall be designed for operating under or ambient temperature 55.C and
100% relative humidity. Electronic type timers shall be as far as possible avoided.
All accessories required for correct operation of each relay shall be supported by the
Sub-contractor without any extra cost. The solid state relays shall be stable and
suitably protected against transient/induced over voltages. The bidder shall state
clearly in his list special requirements, if any, for DC input arrangement or cabling
considered necessary for satisfactory operation of solid state relays quoted by him.

2.24 NAME PLATE

The panel as well as feeder compartments shall be provided with name plate of
anodized aluminum with white engraving on black background. They shall be properly
secured with fasteners/rivets. The panel/feeder descriptions shall be as indicated in
the drawings/ by the employer.

2.25 TESTS

The routine tests shall be conducted as per IS standards on each Power Control Centre
and shall comprise:
Inspection of the Switch Boards including inspection of wiring and electrical
operational/functional tests where necessary.

2.26 DIELECTRIC TESTS

Insulation resistance of the power circuit between each pole and the earth and that
between the poles shall be measured. Insulation resistance of all secondary wiring
between phase and earth shall be measured. Insulation test shall be carried out both
before and after high voltage test. Checking of protective measures and electrical
continuity of the protective circuits.

Annexure [6] Page 584 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

2.27 HIGH VOLTAGE TEST


A high voltage test with 2.5 KV for power circuit and 1.5KV for Control Circuit, Duration
one minute shall be applied between each pole and earth and between poles. Test
certificate shall be submitted along with panel.

2.28 STORING, ERECTION AND COMMISSIONING

2.29 STORING

The panels shall be stored in a well ventilated dry place. Suitable polythene covers
shall be provided for necessary protection against moisture, dust and vermin.

2.30 ERECTION

Switch boards shall be installed over trench/floor as required. Suitable grouting holes
shall be provided in the flooring. Suitable MS base channel shall be embedded in the
flooring on which the panel can directly be installed. The switch boards shall be
properly aligned and bolted to the flooring by at least four bolts. Cables shall be
terminated on the bottom plate or top plate as the case may be, by using brass
compression glands. The individual cables shall then be led through the panel to
the required feeder compartments for necessary terminations. The cables shall be
clamped to the supporting arrangement. Either side, the switch board earth bus shall
be connected to the local earth grid. The base channel used for erection of panels shall
form part of the cost of the panel and shall not be measured or paid separately. All
steel work used in erection will be finish painted with two coats of red oxide primer and
two coats of synthetic enamel of approved colour.
2.31 PRECOMMISSION TESTS

The panels shall be commissioned only after successful completion of the following
tests. The test shall be carried in the presence of Architect's representative. All main
and auxiliary bus bar connections shall be checked and tightened. All wiring
terminations and bus bar joints shall be checked and tightened. Wiring shall be
checked to ensure that it is according to the approved drawing.
All wiring shall be tested for insulation resistance by a 500 volt megger. Phase rotation
tests shall be conducted. Suitable injection tests shall be applied to all the measuring
instruments to establish the correctness and accuracy of calibration and working
order if required by the Employer. All relays and protective devices shall be tested for
correctness of settings and operation by introducing a current generator and an
ammeter in the circuit or shall produce calibration/test certificate as required by the

Annexure [6] Page 585 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Employer / Inspectorate / consultant. Functional tests on all feeders. Makes, type and
ratings of all components shall be checked/verified as per approved drawings.

3.0 GENERAL SPECIFICATIONS FOR LOW VOLTAGE CABLES

3.1 TYPE

Low voltage cables shall be aluminum conductor, PVC insulated, PVC sheathed and
steel wire armored or steel tape armored, FRLS- PVC out sheathed construction. The
cables shall conform to IS 1554 Part I in all respects. Cables shall be laid in tray/Hume
pipe/in ready made trenches etc., as required.

The FRLS outer sheath material shall meet the following requirements:

i) The oxygen index value shall be minimum 29 when tested at 27  2 C


as per ASTM-D-2863-77 and temperature index value shall be
minimum 250 C when tested as per NES 715.
ii) The maximum total acid gas generation as determined by titration shall
be less than 20 % by weight. The test shall be conducted as per IEC-
754-1 (1994).
iii) The smoke density shall be 60 % maximum, when tested as per ASTM-
D-2843-77 (1988).
iv) The finished cable shall pass the flammability test as per IEC-332-1
(1993), In addition, it shall also pass flammability test as per Class F3
of Swedish Standard SS-424-1475 (1978).

The sizes of cables shall be selected to limit the voltage drop during running and
voltage dip during starting to 5% and 10% respectively. Adequate derating factors shall
be considered

3.2 RATING

The cable shall be rated for a voltage of 1100 Volts.

3.3 CORE IDENTIFICATIONS

Cores shall be provided with the following colour scheme of PVC insulation:
1 core : Red/Black/Yellow/Blue
2 core : Red and Black
3 core : Red, Yellow and Blue
3 1/2 / 4 core : Red, Yellow, Blue & Black

Annexure [6] Page 586 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

4.0 STORING, LAYING, JOINTING AND TERMINATIONS

4.1 STORING

On receipt of cables at site the cables shall be inspected and stored in a safe place.

4.2 LAYING

Cables shall be laid as per the specifications given below.

4.0 CABLES IN OUTDOOR TRENCHES

Cables shall be laid in outdoor trenches wherever called for. The depth of the trenches
shall not be less than 75 cm from the final ground level. The width of the trenches
shall suit easy laying of cable. Where more than one cable has to be laid in the
same trench, all attempts shall be made to keep the axial distance between
successive cables to be at least 1d where 'd' is the diameter of the bigger cable. The
trenches shall be cut square with vertical side walls and with uniform depth. Wherever
cables are bent, the minimum bending radius shall not be less than 12 times the
diameter of the cable. After the cable is laid and straightened, it shall be covered with
minimum 150mm deep sand cushion. Over this a course of cable protection tiles or
burnt brick shall be provided on either sides and above. A yellow market tape will be
placed on top and then the trench shall be back filled with earth and consolidated.
Cables shall be laid in hume pipes/stoneware pipes at all road crossings & wall entries.
A 200mm concrete cover shall be provided over all road crossing hume pipes.
Approved cable markers made of CI indicating the voltage, no. of cables and the
direction of run of the cables shall be installed at 50m intervals and all changes in
direction.
6.0 CABLE IN INDOOR TRENCHES

Cables shall be laid in indoor trenches wherever specified. Suitable angle iron
brackets, clamps, hoods and saddles shall be used for securing the cable in position.

7.0 CABLE ON TRAYS/RACKS

Cables shall be laid on cable trays/racks wherever specified. Cable racks/trays shall be
of perforated steel section/slotted angles suitable for the purpose. The trays/racks shall
be complete with plates, tees, elbows, risers and all necessary hardware. The steel
trays shall be hot dip galvanised. Cable trays shall be erected properly to present a
neat and clean appearance. Suitable cleats or saddles shall be used for securing the
cables to the cable trays. The cable trays shall comply with the following requirements

Annexure [6] Page 587 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

The trays are ladder type and shall have suitable strength and rigidity to provide
adequate support for all contained cables. It shall not present sharp edges, burrs of
projections injurious to the insulation of the wiring/cables. If made of Sheet metal, it
shall be adequately protected against corrosion or shall be made of corrosion resistant
material. It shall have side rails or equivalent structural members. It shall include
fittings such as horizontal, vertical bends, tie rods, hooks etc., or other suitable means
or changes in direction and elevation of runs, fish plates and hard ware.

8.0 INSTALLATION

Cable trays shall be installed as a complete system. Trays shall be supported properly
from the building structure. The entire cable tray system shall be rigid. Each run of the
cable tray shall be completed before the installation of cables. In-portions where
additional protection is required, non-combustible covers/enclosure shall be used.
Cable trays shall be exposed and accessible. Where cables of different system are
installed on the same cable tray, non-combustible solid barriers shall be used for
segregating the cables. Cable trays shall be grounded by two nos. Earth continuity
wires. Cable trays shall not be used as equipment grounding conductors.

9.0 JOINTING AND TERMINATIONS

Cable jointing shall be done as per the recommendations of the cable manufacturer.
Jointing shall be done by qualified cable jointers. Each termination shall be carried out
using brass compression glands and cable sockets. Hydraulic crimping tool hall be
used for making the end terminations. Cable gland shall be bonded to the earth by
suing suitable size G.I. wire/tape.
Suitable identification tags with the feeder designation inscribed on an aluminum/G.I.
sheet shall be tied to either ends of each cable.

10.0 TESTING

Cables shall be tested at factory as per the requirements of IS 1554 Part I. The tests
shall incorporate routine tests, type tests and acceptance tests. Copy of such test
certificates shall be furnished to the Employer prior to dispatch.

D. FIRE EXTINGUISHERS

Fire extinguishers shall be worked out in such a way that the Occupants shall not
travel more than 15m to reach a Fire extinguisher. Also there shall be a Fire
extinguisher for every 300 sq.m of floor plate / rooms of suitable type / size. Additional

Annexure [6] Page 588 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

to Office areas Extinguishers to be provided at Surface car parks, out door


Transformers / electrical installations and on the landing of each Staircase of all floors.
All Fire extinguishers shall be portable and hand held, a operating instruction should be
pasted on the extinguisher body.
Portable Fire extinguishers should be BIS approved and valid ISI certificates to be
furnished at the time of delivery to site.

E. SIGNAGE

Required, as per Local fire force like exit signs & Floor indication (eg Ground floor, 1st
floor.), size shall 200mm x 500mm & action chart (size shall be 600mm x 1000mm) in
case of fire / emergency, Staircase location indication etc. The location / quantity shall
be on each landing of every staircase on each floor.
Signs shall be made out of 3mm thick PVC foam board with self glowing reflective self-
adhesive vinyl foam board OR equivalent material with Mirror fasteners for fixing
complete.
Please refer the specimen BOQ format for the details to be printed on the Fire order
boards.

Annexure [6] Page 589 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

SECTION - 8

TECHNICAL DATA SHEEETS

(Note: Bidder should fill Blanks)

DATA SHEET FOR DIESEL ENGINE DRIVEN PUMP


DESCRIPTION REMARKS

Service

Type

Manufacturer

Model No. / Approval

Quantity

Duty

Design and Performance

Number of cylinder, orientation of cylinder, bore and


stroke (in mm)

Direction of Rotation

Rated R.P.M

Brake horse power rating of engine at rated RPM

Lube oil temperature


Lube oil pressure at rated load

Fuel oil pressure


Blow type pressure
Exhaust Temperature

Water temperature

Lube oil consumption

Annexure [6] Page 590 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Permanent Governing

Oil Lubrication System

Material and wire mesh size of filters

Whether pumps are crank driven

Capacity and location of reservoirs

Whether all valves, piping and fittings

Whether cooling arrangement for oil lubrication


system
provided

Cooling water inlet temp. to cooler (temp gauge)


Cooling water outlet temp. from cooler (temp gauge)

Cooling (Raw) water flow

Design pressure

Governing System

Whether speed governing system provided


Make

Type

Steady state speed

Steady state incremental speed regulation

High water temperature alarm switch provided as per


specification

Self stating system

Voltage and capacity

Starting motor - make and type

Annexure [6] Page 591 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Battery - make and type


Battery - No. per engine

Time required by the engine to accept fill load after


receipt of the signal to start from cold condition

Alternative manual starting arrangement provided

Lubrication oil pr. Gauge

Make & type

No. per engine

Range

Location

Accuracy

Thermometer for coolant temperature measurement


(capillary type)

Make & type

No. per engine

Location

Accuracy

Techo-meter for Engine RPM measurement

Make & type

No. per engine

Location

Accuracy

Battery charging system

Make

Annexure [6] Page 592 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Type

No. per engine

Rectifier type battery charger

Type of semiconductor

Supply voltage, phase and frequency

Delivery current rating

Voltmeter details

Make

Nos. per engine


Range

Dial size. mm

Ammeter details

Make

Nos. per engine

Range

Dial size. mm

Fuel System

Gravity tank details

No. (for each engine)

Whether integral with engine

Capacity, litres

Material

Annexure [6] Page 593 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Engine fuel pump supplied

All pipes, valves, fittings, filter etc. supplied

Cooling system

Direct cooling system provided

Necessary piping, fittings, valves, Pr. Reducing


orifice,
pressure gauges, duplex strainer etc. furnished

Cooling water requirement

Cooling water pressure

Cooling water inlet temperature before cooling

Cooling water outlet temp. after cooling

Heat exchanger type

Alternative engine mounted air cooled radiator for


cooling
system, if offered of the bidder

a) Type
b) Make
c) Location
d) Water inlet temp.
e) Water outlet temp.
f) Cooling air flow
g) Total cooling surface area
h) Material of construction (Indicate applicable codes/
standards)
i) Tubes
ii) fins
iii)Header
Cooling system
a) Type
b) Number
c) Location
d) Capacity of each fan

Annexure [6] Page 594 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

e) Power required at fan at rated condition of the


engine.
f) fan speed
h) Material of construction (Indicate applicable codes/
standards)
i) Blade
ii) SHaft

Whether provision made for by-passing radiator


system to avoid chilling of engine

Temperature indicator in Lubricating oil outlet from


the oil cooler

Make and type


Nos. per engine

Range
Location

Throttle Mechanism

Whether throttle mechanism provided

Type

Number per engine

Engine Protection

Type of engine protection provided

Flywheel with guard provided

Material of construction

Fly wheel

Guard for flywheel

Material of construction of the various parts of the


engine

Annexure [6] Page 595 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Base plate

Foundation bolts

Crankcase integral with cylinder block

Cylinder head

Cylinder liner

Crank Shaft

Connecting rods

Engine block

Piston

Cam Shaft

Piston ring

Inlet and exhaust valves

Valve gear

Painting

Primer

Finish paint

Weight of the engine (dry)

Annexure [6] Page 596 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

DATA SHEET FOR ELECTRIC DRIVEN PUMP


DESCRIPTION REMARKS

General

Project / System

Manufacturer

Type

Model No

No. of Pumps offered

Equipment Performance

Performance Standard

Guaranteed Design capacity (Cu.M/Hr.)

Guaranteed total head at discharge flange at rated


capacity (MLC) with respect to MWL as specified in
Data Sheets

Shut off Head (MLC)

Range of operation within which the pump can operate


Continuously without any problem

Pump rated speed (RPM) (Normal design speed)

Guaranteed pump efficiency at rated capacity (%) with


HIS tolerance

The Pumps offered have stable rising H-Q


curves characteristics from the specified duty
point to the Shut-off. The pump should be capable of
giving up to 150% of its rated flow at not less than 65%
head as per NFPA.

The pumps offered have stable rising H-Q


curves characteristics through the Range of
Operation

Annexure [6] Page 597 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Expected noise level

Expected vibration limit

Power Consumption

Guaranteed pump Shaft input power at rated


capacity (KW)

Maximum pump Shaft input power required at


rated condition motor terminal(input power at
specified capacity and head of pump)

Shaft input power at pump Shut off

Pump Shaft input power required during starting

Power consumption at 150% of rated capacity at


motor terminals

Total head at discharge flange at 150% rated


capacity (MLC) with respect to Minimum water
level (MWL)

Motor Rating (KW)

Design and Constructional Features

Pump Duty

Pump Type

Pump Design

Impeller Type

Number of stage

Moment of Inertia GD2 of the complete rotating


system including pump (Kg. Sq.m)

Whether the pumps offered can be started with


discharge valve closed

Annexure [6] Page 598 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

What precautionary measures is required to


be taken to action on the valve disc. if the pump
started with valve fully closed

Type and make of coupling


between pump and drive

Lubricant specification for external lubrication


(stuffing box) self-lubrication for pump

Manufacturer’s Catalogue No.

Design axial load (kg) (at duty point)


Material of Construction

Base Plate

Impeller

Impeller shaft

Impeller wear rings

Casing wear rings

shaft Sleeve

shaft Coupling

Stuffing box

Stuffing box packing

Casing bowl

Connections and other dimensional details

Discharge nozzle diameter

Flange drilling standard


and pressure rating

Rated RPM

Annexure [6] Page 599 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Inspection & Testing

Material Test

Hydrostatic test Pr. and duration (min)

Performance Test

Testing standard

Test to be conducted on

Loading Data

Weight Data

Pumps approval

DATA SHEET FOR JOCKEY PUMP


Manufacturer

Type

Model No.

Duty

Location

No. of Pumps required

No. of Pumps working

No. of Pumps Standby

No. of Pumps working in parallel

Pump Performance

Performance standard

Rated Capacity

Annexure [6] Page 600 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Total Dynamic Head (MWC)

At rated capacity

At Shut off

Rated Speed

Noise level in ‘dbA’ at a distance of 1.5 m from


the pump centre line

Pump Input Power at drive end (KW)

At rated duty point

Maximum Pump Shaft input power required within


the working range of the pump
Motor rating (KW)
Permissible tolerance in rated capacity (%)
Permissible tolerance in efficiency at rated
capacity (%)+_2.5%
Range of operation

Min./Max. capacity at which pump can operate


continuously

Direction of Rotation (VFCE)

Design standard

Pump type

Impeller type

Type of gland lubrication & sealing

Type of pump motor connection

Type of coupling

Material of Construction

Impeller

Wearing rings (casing / impeller)

Annexure [6] Page 601 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Shaft Sleeve

Shaft bearings

Base plate

Stuffing box

Stuffing box packing

Pump Shaft

Casing bowl
Shaft coupling

Discharge head

Companion flange

Supply of accessories

Base Plate

Foundation bolts, nuts, etc.

Discharge companion flanges with bolts, nuts


and gaskets

Painting and protective coating

Inspection and Testing

Annexure [6] Page 602 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

DATA SHEET FOR SPRINKLER BULB


Name of manufacturer / Approval

Type
Design Particulars

End connection

Operating Temperature

Colour coding of bulb

K factor
Material of construction

Housing

Glass bulb

Deflector

Painting

finish

Testing and Inspection

Visual

Marking on equipment

Manufacture’s name

Year of manufacture

Operating temperature

Annexure [6] Page 603 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

DATA SHEET FOR FIRE HOSES


Manufacturer

Type

Code

Size & Length

Working pressure

Test pressure

Burst Pressure

Coil diameter for 45 m length

Weight gm/m

General Construction

End fittings (quick coupling end)

Material of Construction

Hoses

Quick coupling

Approval

Testing and Inspection

Catalogues

Annexure [6] Page 604 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

DATA SHEET FOR ALARM VALVES


Name of manufacturer

Model / Approval

Size

Type

Design Particulars

Inlet flange

Outlet flange

Flange dimensions

Friction loss (Eqiu. Length Pipe)

Max. Working Pressure

Hydro test pressure

Approval

‘UL’ listed

Material of construction

Housing

Clapper / clapper bush

Rubber clamp

Body bush

Seat Rubber

Annexure [6] Page 605 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

ACCESSORIES FOR ALARM VALVES

Water motor gong bell

Wet pilot trim

Test & Alarm trim

Painting

Primer

finish

Testing and inspection

Visual

Hydro test pressure

Marking on equipment

Manufacture’s name

Year of manufacture

Serial No.

Size

Rated Pressure

Documents to be submitted for inspection

Test Certificate

Material test certificate

Guarantee Certificate

Annexure [6] Page 606 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

HYDRANT VALVES
Manufacturer / Approval

Size / Model

Type

Spring / washer

Material of construction

Body

Bonet

Stop vale

Instantaneous Female outlet

Blank Cap

Hand wheel

Spindle

Document for approval

Testing / inspection

Annexure [6] Page 607 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

DATA SHEET FOR GATE VALVES


Manufacturer

Size

Type

Code

Pressure class
End connection
Material of construction

Body

Bonnet

Wedge

Stuffing box

Gland

Hand wheel

Stem

Body seat ring

Wedge seat ring


Wedge nut
Gasket

Gland pack

Thrust plate

Bolt and nuts


Test Pressure

Body

Seat

Model of operation

Annexure [6] Page 608 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Testing & Inspection

DATA SHEET FOR NON RETURN VALVE


Manufacturer

Type

Code/ Standard

Material of construction

Body

Cover

Flap

Hinge Bracket

Body seat ring

Flap seat ring

Hinge Pin

Size

End connection

Max. System working Pressure

Hydrostatic test pressure

a) Body

b) Seat

Testing & Inspection

Approval / Certification

Annexure [6] Page 609 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

DATA SHEET FOR BUTTERFLY VALVES


Manufacturer

Type

Code/ Standard

Material of construction

Body

Disc

Shaft

Shaft Seal

Control lever

Test Pressure

CATALOGUE

Inspection & Testing

Annexure [6] Page 610 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

DATA SHEET FOR PIPES


Manufacturer

Standard

Type

Material

Class & Grade

End type

Type of End connection

Type of protective coating

Under Ground

Above Ground

Testing Pressure

Working Pressure

Inspection & Testing

Welding Electrodes
Type / make

PIPE FITTINGS
Manufacturer

Type

Code/ Standard

Couplings

Bolts & Nuts

Annexure [6] Page 611 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Gaskets
DATA SHEET FOR FIRE SHUTTER
Manufacturer

Standard

Material of Construction

Finish

Glass thickness

Size

Colour

Marking

Locking arrangement

DATA SHEET FOR FIRE BRIGADE INLET

Manufacturer

Standard

Material of Construction

Inlet

Out let

Spring

Seat washer

Flange

Blackcap

Annexure [6] Page 612 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Hydro test pressure

Mounting

DATA SHEET FOR BRANCH PIPE WITH NOZZLE


Manufacturer

Standard

Branch pipe

Nozzle

Material of construction

Branch pipe

Nozzle

Coupling

Size

Branch pipe

Nozzle

Hydro test pressure

Flow

Annexure [6] Page 613 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

DATA SHEET FOR HOSE CABINET


Manufacturer

Standard

Material of Construction

Finish

Glass thickness

Size

Colour

Marking

Locking arrangement

Type

DATA SHEET FOR HOSE REEL


Manufacturer

Standard

Type

Material of Construction

Drum

Base plate

Bearing

Annexure [6] Page 614 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Hose

Finish

Size

Colour

Marking

Accessories
Anchor bolts, Hose clamps

Hose length and dia

DATA SHEET FOR PRESSURE SWITCH


Manufacturer

Type of Mounting

Material of Construction

Casing & Body

Sensing Element

Enclosure

Type of contact

No. of Contacts

Size of Process connection

Pressure Setting

Annexure [6] Page 615 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Max. over Pressure

Adjustment

DATA SHEET FOR PRESSURE GUAGE


Manufacturer / Standard

Type

Range

Accuracy

Size of Dial

Dial Material & Colour

Window

Material of Construction

Enclosure

Movement, Shank, Burdon

Connection size

Mounting & Entry

Cock

Siphon tube

Annexure [6] Page 616 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

DATA SHEET FOR FLOW SWITCH


Make

Type

Model

Size(mm)

Operating temperature range

DATA SHEET FOR FIRE EXTINGUIHSERS


CO2 type

Manufacturer

Type C02 4.5 kgs & 2 kgs

Standard

Size

Diameter

Height

Weight

Quantity

Mechanical Foam type


Manufacturer

Mechanical Foam 9
Type lts. capacity

Standard

Size

Diameter

Annexure [6] Page 617 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Height

Weight

Quantity

DCP type

Manufacturer

Type DCP 5 Kgs

Standard

Size

Diameter

Height

Weight

Quantity

Water CO2 type

Manufacturer

Type Water CO2 9 Lts

Standard

Size

Diameter

Height

Weight

Quantity

Annexure [6] Page 618 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

DATA SHEET FOR FLEXIBLE DROP


General

Project / System

Manufacturer

Type

Model No

Material

Size

Length

Maximum working pressure

Hydraulic test pressure

Approvals

Testing and Inspection

Visual

Marking on equipment

Manufacture’s name

Annexure [6] Page 619 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

DATA SHEET FOR STRAINER


General

Project / System

Manufacturer

Type

Model No

Material :Body
Material :Mesh and no. of mesh
Size

Length

Maximum working pressure

Hydraulic test pressure

Approvals

Testing and Inspection

Marking on equipment

Annexure [6] Page 620 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

DATA SHEET FOR BALL VALVE


General

Project / System

Manufacturer

Type

Model No

Material :Body
Material of ball:
Disc packing
Size

End Type
Type of threads
Maximum working pressure

Hydraulic test pressure

Approvals

Testing and Inspection

Annexure [6] Page 621 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

DATA SHEET FOR AIR RELEASE VALVE


General

Project / System

Manufacturer

Type

Model No

Material :Body and Cap

washer

End Type

Maximum working pressure

Hydraulic test pressure

Approvals

Testing and Inspection

Annexure [6] Page 622 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

DATA SHEET FOR AIR VESSEL


General

Project / System

Manufacturer

Type

Model No

Material :

Tank size
Diaphragm material
Liquid Temp

Maximum working pressure

Hydraulic test pressure

Approvals

Testing and Inspection

DATA SHEET FOR CABLES


General

Project / System

Manufacturer

Conductor Type
Insulation type
IS Standard

Core Identification
3.5 core
4.0 Core
2 core

Annexure [6] Page 623 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

Laboratory Tests
a) Smoke density measurement test
b) Oxygen Index test
c) HCL liberation test
d) Flammability Test of Outer Sheath
e) Routine and Acceptance Test

DATA SHEET FOR PRESSURE TRANSMITER


PARAMETER SPECIFICATION
Qty.
Fluid
Location

Fluid State

Make
Flow through chamber
Measuring Range
Fluid Handled
Temperature of Fluid
Operating Pressure (bar)
Installation

Application
pH Range
Output
Power Supply
Installation
Enclosure
Model

Annexure [6] Page 624 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

SECTION - 9

MAKE OF EQUIPMENT

Annexure [6] Page 625 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

A. RECOMMENDED MAKES FOR MECHANICAL WORKS

1. FIRE PUMPS : KIRLOSKAR / PENTAIR


GRUNDFOS

2. DIESEL ENGINE : KIRLOSKAR OIL ENGINE / CUMMINS


INDIA/CATTER PILLAR

3. G.I. PIPES : TATA/JINDAL

4. PIPE FITTINGS : VICTUALIC/UL APPROVED

5. BUTTERFLY VALES : AUDCO / KITZ/HATTERSELEY

6. NON – RETURN VALVES : H. SARKER / AUDCO

7. GATE VALVES (Screwed end) : LEADER / AUDCO

8. BALL VALES (Screwed end) : LEADER /AUDCO

9. STRAINERS : GUJRAT OTO FILT / GRAND FRIX /


TEL FLOW

10. C.I. GATE VALVES : H. SARKER / AUDCO

12. PRESSURE SWITCH : INDFOS / SWITZER / DANFOS

13. PRESSURE GAUGE : H. GURU / FIEBIG

14. ANTICORROSIVE MATERIAL : I W L / RUSTECH

15. HYDRANT VALVES : NEWAGE / SHAHBHOGILAL /MINIMAX

16. BRANCH PIPE WITH NOZZLE : NEWAGE / SHAHBHOGILAL /


MINIMAX

17. FIRE HOSES : NEWAGE / CRC

18. HOSE COUPLINGS : NEWAGE / SHAHBHOGILAL /


MINIMAX

19. HOSE REEL : EVERSAFE / TYCO / KIDDE / MINIMAX

20. HOSE BOX : EVERSAFE / TYCO / KIDDE /


MINIMAX

21. FIRE EXTINGUISHERS : SAFEX / KANEX / TYCO

22. SPRINKLERS : TYCO / VIKING / KIDDE

Annexure [6] Page 626 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

23. SPRINKLER ALARM VALVE : HD / TYCO / VIKING / KIDDE

24. FLOW SWITCH : SYSTEM SENSOR / SWITZER

25. PAINT : ASIAN / BERGER

26. AIR RELEASE VALVES : LEADER / HAWA

27. WELDING ELECTRODES : ESAB / ADVANI / SUN ARC

28 CABLE TRAYS : PROFAB / INDIANA

29 CABLES : POLYCAB/ FINOLEX/UNIVERSAL


CABLES

30 PRESSURE TRANSMITTER : HONEY WELL/SIEMENS

31 FLEXIBLE DROP : NEWAGE / EASYFLEX (KANWAL)

32 FOOT VALVES : KIRLOSKAR

33 FLOW METER : GERAND / VIKING / VICTAULIC

34 HOSE REEL DRUM : TYCO/EVERSAFE

35 HDPE TANK : SINTEX

36 FIRE BRIGADE INLET


CONNECTION : NEWAGE/WINCO/SHAHBOGHILAL

37. PIPE SUPPORTS : EASYFLEX (KANWAL)

Annexure [6] Page 627 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

B. RECOMMENDED MAKES FOR ELECTRICAL WORKS

1. ELECTRIC MOTORS : KIRLOSKAR ELECTRIC / CROMPTON


GREAVES / SIEMENS / ABB

2. BATTERY : EXIDE / STANDARD / AMAR RAJA/

MINIMAX

3. MOTOR CONTROL CENTRE : PRAGATHI CONTROLS / LOAD


CONTROLS / DYNAMO / BRIGHT
ENGINEERING/ELLINS / LOTUS

4. CONTROL / POWER CABLES : GLOSTER / UNIVERSAL / ASIAN / CCI/


FINOLEX

5. MCCB : GE(IMPORTED VERSION ) /


L&T/ALSTOM/MERLINGERIN / ABB

6. CONTROL MCB : MERLINGERIN / SIEMENS


/LEGRAND/GE

7. VOLT METER SELECT SWITCH : SALZER / L & T / KAYCEE

8. VOLTMETER (AC / DC) : MECO / AE

9. AMMETER (AC / DC) : MECO / AE /CADEL /CONZERY

10. POWER CONTACTORS : ABB / SIEMENS /L&T/ SCHNEIDER

11. INDICATING LAPS (LED type) : BINAY / TEKNIC /SIEMENS

12. PUSH BUTTONS : TEKNIC / SIEMENS

13. AUTO / MANUAL SELECTOR : SALZER / KAYCEE

14. TIMERS : EAPL / AE

15. TERMINAL BLOCKS : ELMEX / WAGO

16. CURRENT TRANSFORMERS : PRAGATHI / KAPPA /INSTANS

17. OVER LOAD RELAY : ABB / SIEMENS/MERLINGERIN

18. SINGLE PHASE PREVENTORS : MINILEC / AE

19. ENGINE CONTROL SELECTOR : SALZER / KAYCEE / L&T

20. MAIN SUPPLY SELECTOR – DPMCB : SIEMENS / MERLINGERIN

21. BATTERY CHARGING SELECTOR : SALZER / L & T/ KAYCEE

22. BATTERY CHARGER : KAYBEEPOWEREC/ HBL-NIFE/ AFCO/CHABBI

Annexure [6] Page 628 of 938


DAN HOTEL @ WHITEFIELD, BANGALORE Technical Specifications for Fire Protection Works

23. SIREN / HOOTER : KHERAJ/EQUI.

24 TOGGLE SWITCH : JAY / EQUI / MINI ELEC

25. END TERMINATIONS : DOWEWLS / SMI / JAINSONS

26. CABLE TRAY : PROFAB/ / INDIANA

Annexure [6] Page 629 of 938

You might also like