SKENARIO PELAKSANAAN

REKONSTRUKSI JALAN SAGEA – PATANI 2/UMYC/PN

0+000 0+900 6+500 14+000 20+000 24+900


LPA LPA
AC -WC AC - WC AC -BC AC -BC
AC - WC AC - BC

- LPA, Target Selesai 10 des 2019

- AC-BC Target Selesai ,Rabu 30 Okt 2019

- Sisa AC - WC 1.012 ton - Perbaikan LPA s/d tgl 16 Nov 2019


( 14 Nov 2019 ) 2 km 10 DT Kecil

± 350 ton/hari
Selesai Tgl 16 Nov 2019 - AC -BC , 17 Nov 2019 s/d 1 Des 2019
5 DT Kecil , 4934 ton
- AC -WC , 27 Des 2019 ± 350 ton/hari
5 DT Kecil - AC -BC , 25 Nov 2019 s/d 14 Des 2019
- AC - WC , 15 Des 2019 s/d 26 Des 2019 3904.56 ton
± 455 ton/hari 3795 ton ± 300 ton/hari
± 350 ton/hari

BAHU JALAN
- 12.000 M3
Target 11 Des s/d 21 Des 2019

Diperiksa Oleh : Di buat Oleh :


Disetujui Oleh : KONSULTAN PENGAWAS PENYEDIA JASA
DIREKSI LAPANGAN PT. ARIA JASA REKSATAMA PT. NAVIRI MULTI KONSTRUKSI

Haryanto Malik Agus Pramono, ST. Ir. Miftahul Iman Hamid


NIP. 19771031 200710 1 002 Site Engineer General Superintendent