Saudi Aramco Inspection Checklist: Depressurization & Disposal of Hydrotest Water SAIC-A-2017 3-Jul-18 Mech
Saudi Aramco Inspection Checklist: Depressurization & Disposal of Hydrotest Water SAIC-A-2017 3-Jul-18 Mech
Saudi Aramco Inspection Checklist: Depressurization & Disposal of Hydrotest Water SAIC-A-2017 3-Jul-18 Mech
00 30-Apr-18
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A General Requirements
New pipelines, and pipelines in gas service do not require oil/water SAEP-327,
B1
separation
Disposal ofprior to wastewater
wastewater discharge/disposal
to the terrestial environment is not permitted. Section 4.4
Wasteater can be dischared directly to sabkhah if provisions are met.
• The wastewater does not flow to the marine environment, or any of the
SAEP-327,
B2 ecologically sensitive areas listed above; and
Section 4.11
• The wastewater passes through an oil/water separator pond (Figure 1)
before it is discharged to the sabkhah to ensure retention of residual
hydrocarbon
As for subsequent
far as possible locate the collection andwithin
disposal site proper handling.
the existing pipeline
corridor while ensuring adequate pipeline access and without causing SAEP-327,
B3
damage to the existing roadways, pipelines, private entities or other Section 4.6
Disposal
structures to the Marine Environment
Dispose wastewater to the marine environment to the Arabian Gulf or Red
Sea in accordance with the criteria in Table 1 and SAES-A-103. Ensure
SAEP-327,
B4 adequate dispersal of wastewater in the marine environment by
Section 4.10
employing diffusers or similar technologies. Alternatively, transfer
wastewater onshore for treatment/disposal as per Sections 4.3 through
4.8.
Previously Used Approved Pond
Disposal to existing, previously used evaporation ponds requires
evaluation as a new disposal request. The volume, water quality, and SAEP-327,
B5
potential for contamination from additional disposal require a separate Section 4.9
evaluation as per this procedure.