Sample PWHT Procedure

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

JUTASAMA SDN. BHD.

Document Title POST WELD HEAT TREATMENT PROCEDURE Document No. JS13019 – DC011
Revision No. 3 Revision Date 15 October 2014 Page Number 1 OF 4

1.0 Objective
1.1 To ensure Post Weld Heat Treatment (PWHT) work is properly conducted as per this procedure
and Code requirement.
2.0 Scope
2.1 This procedure is applied to all equipment fabricated for this project as below;
No Equipment Furnace PWHT 1 Furnace PWHT 2 Localise via Electrical
Heating
1 9V-91408 Section fr LW-02 Section fr LW-01 to CW-02
to Top Bottom (inc. skirt)
2 9S-91110A/B/C Whole vessel
3 9V-91301 Whole vessel
4 V-1009A/B/C Whole vessel
5 9V-95103 Whole vessel
6 9V-95101 Section fr LW-04 Section fr LW-03 to CW-04
to Top SLW-01 Nozzle N3-J2
7 9S-91106 Whole vessel
8 V-98120 Whole vessel
9 9V-91106 Whole vessel
10 9V-91304 Whole vessel
11 9V-91411 N1 to shell insert plate
12 9V-91413 N1 to shell insert plate

3.0 Definitions
3.1 QC - Quality Control
3.2 HOD - Head of Department
3.3 SOP - Standard Operating Procedure
3.4 PWHT - Post Weld Heat Treatment

4.0 Reference
4.1 ASME Section VIII Division 1, 2010 Edition & 2011 Addenda.
4.2 S-000-1351-005 - Specification for Pressure Vessel
4.3 PTS 3122.20.31 - Pressure Vessel

5.0 Responsibilities
5.1 Production Section shall liaise with PWHT contractor on arrangement & preparation of PWHT
activities.
5.2 QC Inspector shall prepare Heat Treatment Work Instruction (Attachment 1) and ensure that
PWHT works is conducted in accordance with the instruction, this procedure and related Code &
Specification.
5.3 PWHT Contractor shall prepare report & submit to QC Inspector for review & acceptance. QC
Inspector to submit the report to 3rd Party / Authorized / Client Inspector (if applicable) for review
& acceptance.

6.0 Procedure
6.1 Equipment List
6.1.1 Type of equipment : a) Furnace.
JUTASAMA SDN. BHD.
Document Title POST WELD HEAT TREATMENT PROCEDURE Document No. JS13019 – DC011
Revision No. 3 Revision Date 15 October 2014 Page Number 2 OF 4

b) High velocity combustion equipment


c) Electrical heating pad
6.1.2 Power supply : a) LPG gas
b) Input ~ 440V 3ph + Neutral (70 amps)
6.1.3 Insulation : 128 gm / cm ceramic fiber.
6.1.4 Temperature controller: Thermocouple sensor, Auto temperature programmer or
manual gas regulator control unit.
6.1.5 Temperature recorder: Chino multi point temperature recorder for Type `K'
thermocouple calibration twice a year basis.
6.1.6 Thermocouple : Type `K' confirms to BS 4397 Part 4 with certificate of conformity.
6.1.7 Compensating cable: Copper constantan type conforms to ASTM B220, E452.

6.2 Heating Method


A. Furnace
6.2.1 The heat treatment operation will be by means of high velocity LPG burners insert equal
spaced at the lower portion of the furnace chamber and will fire parallel with furnace
hot face wall.
6.2.2 Manually adjusted exhaust flues shall be positioned in the roof of the furnace so that
exhaust gases will be controlled to maintain the positive pressures within the furnace
chamber. Gas and combustion air changes will be made manually so that hot gases
produce a `scrubbing action’ and maintain total temperature and expansion uniformity.
6.2.3 The high velocity burner is design to give maximum flame length of approximately 12
inches (300mm) and hence only hot gases reach the component. The turndown ration is
extremely high – in order of 50:1 and this feature gives complete and accurate
temperature control at all stages of the firing. In addition no local ‘hot spot’ are
produced and optimum temperature uniformity is achieved.
6.2.4 The hot gases omitting from the burner(s) reach an exit velocity of 450ft per second (150
meters per second). The high speed of these gases produces a ‘scrubbing’ action on
the component walls, which further promotes temperature uniformity.
6.2.5 The combustion product is accurately controlled at all times, and minimum oxidation of
the component occurs.
6.2.6 The burner(s) fitted with constant spark ignition devices to give completed safety of the
firing process. The flame is also monitored by an ultra-violet flame-sensing device
coupled to an automatic gas safety shut-off valve. Coupled to burner, via flexible hose,
is a combustion air fan, which can be accurately controlled to deliver exact quantities
of air to the burner. The burner(s) is of nozzle mixed design so as to eliminate any danger
of burner light back.
6.2.7 The positive pressure within the furnace chamber shall be maintained by utilizing
adjustable damper controls at the exhaust flue positions.

B. Electrical Heating

6.2.8 The heating elements shall be applied either as a single band, or two discrete bands,
arranged symmetrically about the centerline of the weld seam. The heated bandwidth
shall be a minimum of 6t, inclusive of any centerline gap, where “t” is the maximum
thickness at the joint and/or. Suitable pad size shall be used to get adequate and
consistence temperature.
6.2.9 The centerline circumferential gap between two bands of elements shall be limited to a
maximum of 30mm or “t”, whatever is the lesser. (t = wall thickness) for wall thickness
above 10mm. For a wall thickness below 10mm, the maximum gap shall be 10mm.
JUTASAMA SDN. BHD.
Document Title POST WELD HEAT TREATMENT PROCEDURE Document No. JS13019 – DC011
Revision No. 3 Revision Date 15 October 2014 Page Number 3 OF 4

6.2.10 Longitudinal gaps between individual elements shall be limited to 50mm or “t”,
whichever is the lesser, for wall thickness above 10mm. For a wall thickness below 10mm,
the maximum longitudinal gap shall be 10mm.
6.2.11 For a two band heating system, the heater pads on one side of the weld should be
rotated one quarter of a pad width, with respect to the heaters on the opposite side.
6.2.12 Where the nominal pipe outside diameter is equal to or greater than 250mm (10”), the
heating pads shall be arranged so as to give independent control of temperature on the
top and bottom halves.
6.2.13 Where the wall thicknesses of the two joint members differ, the elements shall be
arranged so as to give side-to-side temperature control.
6.2.14 Thermal insulation should be achieved by following means one layer of 50mm (T),
128kg/m density ceramic fiber or rock wool (50mm) which is suitable for hot face
temperature up to 1200 ºC.
6.2.15 The insulation shall be applied for a minimum of 300mm on each side of weld that is to
be PWHTed. Insulation shall not be removed before the temperature has cooled to
below 150oC. Opening shall be restricted in order to eliminate drafts or air circulation that
could lower the temperature on the inside surface of the joint unless the internal surface
also insulated.
6.2.16 Insulation shall be fixed using black annealed iron wire taking care, not damaging or
cutting into the insulation.
6.2.17 By following proper PWHT cycles, the item or the particular joint shall be completed & the
cooling rate should be controlled under insulation

6.3 Temperature Recording & Monitoring


6.3.1 Thermocouple used to monitor the temperature during the heat treatment process shall
be type ‘K’ as describe in 6.1.6. Thermocouple shall be welded onto the vessel by means
of capacitor discharge action (Electric Resistance Sparkling Process) with the aid of the
thermocouple attachment unit, sufficient precautions shall be taken to ensure surface
defect will not be created. The thermocouple shall be removed and the surface or the
weld seam shall be smoothened by filing or grinding after heat treatment.
6.3.2 Thermocouples shall be attached onto the vessel at different location and thickness on
each firing. Number and location of thermocouple shall be as per individual Heat
Treatment Work Instruction which to be prepared prior to PWHT application.
6.3.3 Thermocouple indicated shall be connected to the temperature recorder thus providing
a total record of temperature variation and trends during the whole heat treatment
cycle. Recorder used shall be of the range 0-1200oC and chart speed of 25mm or 50mm
per hour.
6.3.4 Temperature recorder used shall be calibrated at least once a year and calibration
certificates shall be submitted to client’s representative.
6.4 Heating Temperature requirement
6.4.1 PWHT shall be conducted as per Code & Specification requirement.
6.4.2 For case of Carbon Steel material, ASME Section VIII Division 1, Part UCS shall be follow.
Heating, soaking & cooling requirement shall be as per UCS-56 of the code.
5.2 Heating rate from 425oC to soaking temperature, the rate of heating shall not exceed
222oC divided by the maximum thickness of shell or head plate in inches, but in no case
more than 222oC/hr.
5.3 Holding temperature and holding time shall be as per Table UCS-56.
5.4 The cooling rate from holding temperature to 425oC shall not exceed 280oC/hour
divided by the maximum thickness of shell or head in inches, but in no case more than
280oC.
5.5 Cooling rate from 425oC down to ambient temperature, the component may be
allowed to cool naturally in the furnace.
JUTASAMA SDN. BHD.
Document Title POST WELD HEAT TREATMENT PROCEDURE Document No. JS13019 – DC011
Revision No. 3 Revision Date 15 October 2014 Page Number 4 OF 4

6.5 Documentation
6.1 Documentation will comprise the following:-
i) Client’s Name
ii) Project’s Name
iii) Job Number
iv) Report Number
v) Equipment Number / Name
vi) Chart Number
vii) Heat Treatment Data
viii) Recorder Calibration Certificates.
ix) Thermocouple Certificates of Conformity.
6.2 The above documentation will be prepared and checked by the supervisor to ensure
that all are fully complied with the procedure before submission to client’s
representative for review. These documents shall be prepared and reflected to ‘Heat
Treatment Work Instruction’ for all equipment.

Holding / Soaking
C (Note 3) D
600oC
Heating (Note 2) Cooling (Note 4)

B E
425oC

HEAT TREATMENT TEMPERATURE REQUIREMENT (ASME Sect. VIII Div. 1, UCS-56)


Notes :
1) A-B Unrestricted heating rate.
2) B-C Control heating - Maximum 222oC/hour divided by the maximum metal thickness, but in
no case more than 222oC/ hour
3) C-D Holding temperature : As per table in UCS 56.
Holding time : 1 hour/inch for metal thickness up to 2 inches and 2 hours plus
15 minutes for each additional inch over 2 inches for P no. 1
and 3 material.
4) D-E Control cooling - Maximum 280oC/hour divided by the maximum metal thickness, but in
no case more than 280oC/hour.
7.0 Attachment
7.1 Heat Treatment Work Instruction
JUTASAMA
JUTASAMA SDN. BHD.
HEAT TREATMENT WORK INSTRUCTION
CO. NO. 095631-H

ITEM NO : 9V-91408 PROJECT : LNG TRAIN 9

EQUIPMENT : PROPANE RECEIVER CLIENT : JGC - PETRONAS


Accp.Code : ASME VIII Div. 1 2010, 11 Addenda JOB NO. : JS13019
Part : Vessel devided to 2 Section Material Spec. : SA516 Gr.70N + S5 + S3
Thickness (mm) Shell : 50 Head : 61 / 73 Other : -

TYPE OF HEAT TREATMENT

PWHT x Normalizing
Others

HEAT TREATMENT METHOD

Enclosed furnance X Localized


Others PWHT in 2 segment before final joint

HEAT TREATMENT PROCEDURE

HOLDING/SOAKING TEMPERATURE COOLING RATE


HEATING RATE 600 - 620 O
C
Max: 75 o
C / Hr Max: 95 o
C / Hr
o
ABOVE 425 C o
HOLDING/SOAKING TIME (minimum) ABOVE 425 C
2 Hrs 15 Mins

LOCATION OF THERMOCOUPLES
i. Number of thermocouples as per attached sketch
ii. Calibration certificates for thermocouple & temperature recorder shall be submitted
iii. Thermocouples location as per attached sketch.

Note : Vessel dimension Ø : ID 4500 mm TL/TL : 11000 mm

PREPARED BY : CHECKED BY :

JS QC Department
D t Client Representative Owner Representative

9V-91408-1 QC EXHIBIT 8.1


JUTASAMA
JUTASAMA SDN. BHD.
HEAT TREATMENT WORK INSTRUCTION
CO. NO. 095631-H

ITEM NO : 9V-91408 PROJECT : LNG TRAIN 9

EQUIPMENT : PROPANE RECEIVER CLIENT : JGC - PETRONAS


Accp.Code : ASME VIII Div. 1 2010, 11 Addenda JOB NO. : JS13019
Part : Whole vessel @ CW-02 Material Spec. : SA516 Gr.70N + S5 + S3
Thickness (mm) Shell : 50 Head : 61 / 73 Other : -

TYPE OF HEAT TREATMENT

PWHT x Normalizing
Others

HEAT TREATMENT METHOD

Enclosed furnance Localized X


Others Localise electrical heating on CW-02

HEAT TREATMENT PROCEDURE

HOLDING/SOAKING TEMPERATURE COOLING RATE


HEATING RATE 600 - 620 O
C
Max: 75 o
C / Hr Max: 95 o
C / Hr
o
ABOVE 425 C o
HOLDING/SOAKING TIME (minimum) ABOVE 425 C
2 Hrs 15 Mins

LOCATION OF THERMOCOUPLES
i. Number of thermocouples as per attached sketch
ii. Calibration certificates for thermocouple & temperature recorder shall be submitted
iii. Thermocouples location as per attached sketch.

Note : Vessel dimension Ø : ID 4500 mm TL/TL : 11000 mm

PREPARED BY : CHECKED BY :

JS QC Department
D t Client Representative Owner Representative

9V-91408-2 QC EXHIBIT 8.1


JUTASAMA
JUTASAMA SDN. BHD.
HEAT TREATMENT WORK INSTRUCTION
CO. NO. 095631-H

ITEM NO : 9V-91408 PROJECT : LNG TRAIN 9

EQUIPMENT : PROPANE RECEIVER CLIENT : JGC - PETRONAS


Accp.Code : ASME VIII Div. 1 2010, 11 Addenda JOB NO. : JS13019
Part : Vessel devided to 2 Section Material Spec. : SA516 Gr.70N + S5 + S3
Thickness (mm) Shell : 50 Head : 61 / 73 Other : -

THERMOCOUPLE LOCATION SKETCH

2,4

2 2 6 10

1
1 14
3,5 3,5 7,9 11,13

4 4 8 12

0O

270O 90O

Thermocouples distributed evently at


four major orientation
180O

Note : Vessel dimension Ø : ID 4500 mm TL/TL : 11000 mm

PREPARED BY : CHECKED BY :

JS QC Department
D t Client Representative Owner Representative

9V-91408-3 QC EXHIBIT 8.1


JUTASAMA
JUTASAMA SDN. BHD.
HEAT TREATMENT WORK INSTRUCTION
CO. NO. 095631-H

ITEM NO : 9S-91110ABC PROJECT : LNG TRAIN 9


DEEP AGR LEAN SOLVENT ACTIVATED
EQUIPMENT : CLIENT : JGC - PETRONAS
CARBON FILTER
Accp.Code : ASME VIII Div. 1 2010, 11 Addenda JOB NO. : JS13019
Part : Whole vessel Material Spec. : SA516 Gr.70N + S3
Thickness (mm) Shell : 50 Head : 55 Other : -

TYPE OF HEAT TREATMENT

PWHT x Normalizing
Others

HEAT TREATMENT METHOD

Enclosed furnance X Localized


Others

HEAT TREATMENT PROCEDURE

HOLDING/SOAKING TEMPERATURE COOLING RATE


HEATING RATE 600 - 620 O
C
Max: 100 o
C / Hr Max: 125 o
C / Hr
o
ABOVE 425 C o
HOLDING/SOAKING TIME (minimum) ABOVE 425 C
2 Hrs 15 Mins

LOCATION OF THERMOCOUPLES
i. Number of thermocouples as per attached sketch
ii. Calibration certificates for thermocouple & temperature recorder shall be submitted
iii. Thermocouples location as per attached sketch.

Note : Vessel dimension Ø : ID 5200 mm TL/TL : 5250 mm

PREPARED BY : CHECKED BY :

JS QC Department
D t Client Representative Owner Representative

9S-91110ABC-1 QC EXHIBIT 8.1


JUTASAMA
JUTASAMA SDN. BHD.
HEAT TREATMENT WORK INSTRUCTION
CO. NO. 095631-H

ITEM NO : 9S-91110ABC PROJECT : LNG TRAIN 9


DEEP AGR LEAN SOLVENT ACTIVATED
EQUIPMENT : CLIENT : JGC - PETRONAS
CARBON FILTER
Accp.Code : ASME VIII Div. 1 2010, 11 Addenda JOB NO. : JS13019
Part : Whole vessel Material Spec. : SA516 Gr.70N + S3
Thickness (mm) Shell : 50 Head : 55 Other : -

THERMOCOUPLE LOCATION SKETCH

2 1

3 4,6 5

0O
7 8,10 9

270O 90O

11 12,14 13
180O

Thermocouples distributed evently at four


major orientation

15 16

Note : Vessel dimension Ø : ID 5200 mm TL/TL : 5250 mm

PREPARED BY : CHECKED BY :

JS QC Department
D t Client Representative Owner Representative

9S-91110ABC-2 QC EXHIBIT 8.1

You might also like