LAPORAN BULANAN CONSTRUCTION

PLTM CILEUNCA
Nama Pekerjaan : Proyek EPC PLTM Cileunca 2 x 500 KW
Kontrak No. : 243.PJ/061/IP/2019
Kontraktor Pelaksana : Konsorsium PT. Maharani Prima - WWS Wasserkraft GmbH
Periode : 16 January 2021 - 15 February 2021
Report No : M-13 (02-2021)
Porsi Pekerjaan : LOKAL

KEMAJUAN PEKERJAAN TOTAL KEMAJUAN PEKERJAAN S/D


BULAN LALU BULAN INI BULAN INI
BOBOT
PER TOTAL EPC 13,11%
NO URAIAN PEKERJAAN SATUAN VOLUME PER TOTAL
BOBOT BOBOT CONSTRUCTION
22,86%
VOLUME VOLUME
(%) (%)
(%) BOBOT
VOLUME % Pekerjaan
(%)

4 CONSTRUCTION and COMMISSIONING


4.1 General Works -
4.1.1 Temporary Facilities -
4.1.1.1 Direction Keet (Owner) ls 1,00 0,50 0,47 0,23 0,47 0,23 46,80%
4.1.1.2 Direction Keet (Contractor) ls 1,00 0,50 1,00 0,50 1,00 0,50 100,00%
4.1.1.3 Temporary warehouse ls 1,00 0,36 1,00 0,36 1,00 0,36 100,00%
4.1.1.4 Project safety fence ls 1,00 0,36 1,00 0,36 1,00 0,36 100,00%
4.1.1.5 Temporary site access ls 1,00 0,28 1,00 0,28 1,00 0,28 100,00%
4.1.1.6 Temporary warehouse 2 ls 1,00 0,50 1,00 0,50 1,00 0,50 100,00%
4.1.1.7 mobilization and demobilization ls 1,00 0,28 0,75 0,21 0,06 0,02 0,81 0,23 81,25%
4.1.2 Access Road Area -
4.1.2.1 Site Preparations - Access Road Area ls 1,00 0,73 1,00 0,73 1,00 0,73 100,00%
4.1.3 Pipe Penstock Area -
4.1.3.1 Site Preparations - Pipe Penstock Area ls 1,00 1,45 1,00 1,45 1,00 1,45 100,00%
4.1.4 Powerhouse Area -
4.1.4.1 Site Preparations - Powerhouse Area ls 1,00 0,73 1,00 0,73 1,00 0,73 100,00%
4.1.5 Insurance (EAR, Tenaga Kerja) ls 1,00 0,46 0,34 0,16 0,34 0,16 34,00%
4.1.6 Report and Documentation ls 1,00 0,46 0,77 0,35 0,03 0,01 0,80 0,37 79,64%
4.2 Civil Works -
4.2.1 Access Road Area -
4.2.1.1 Base + Sub Base ls 1,00 2,01 0,55 1,11 0,00 0,01 0,56 1,12 55,90%
4.2.1.2 Paving + Drainage ls 1,00 2,51 0,22 0,54 0,22 0,54 21,60%
4.2.1.3 Access Bridge -
4.2.1.3.1 Soil Work ls 1,00 0,55 0,35 0,19 0,35 0,19 35,00%
4.2.1.3.2 Structure ls 1,00 4,98 0,18 0,89 0,03 0,13 0,21 1,03 20,60%
4.2.2 Pipe Penstock Area -
4.2.2.1 Pipe Penstock - Saddle Construction -
4.2.2.1.1 Penstock Pipe - batch 1 (morning Glory - AB 1) ls 1,00 2,19
4.2.2.1.2 Penstock Pipe - Batch 2(AB 1-AB 5) ls 1,00 2,19 0,21 0,45 0,07 0,15 0,28 0,60 27,60%
4.2.2.1.3 Penstock Pipe - Batch 3 (AB 5 - AB 11) ls 1,00 2,19 0,48 1,05 0,18 0,39 0,66 1,44 65,93%
4.2.2.1.4 Penstock Pipe Batch 4 (AB 11 - AB 15) ls 1,00 2,19 0,14 0,31 0,14 0,31 14,25%
4.2.2.2 Anchor Block Construction -
4.2.2.2.1 Penstock Pipe - Batch 2(AB 1-AB 5) ls 1,00 1,66 0,14 0,23 0,14 0,23 14,00%
4.2.2.2.2 Penstock Pipe - Batch 3 (AB 5 - AB 11) ls 1,00 1,66 0,31 0,51 0,35 0,58 0,66 1,09 65,83%
4.2.2.2.3 Penstock Pipe Batch 4 (AB 11 - AB 15) ls 1,00 1,71 0,13 0,23 0,13 0,23 13,30%
4.2.2.3 Tunnel - Pipe Foundation ls 1,00 1,53
4.2.2.4 Penstock Bridge 1 (tunnel Outlet) ls 1,00 3,28
4.2.2.5 Penstock Bridge 2 ls 1,00 3,28 0,13 0,43 0,00 0,00 0,13 0,43 13,02%
4.2.3 Powerhouse Area -
4.2.3.6 Soil Work - Powerhouse Area ls 1,00 2,73
4.2.3.1 Foundation -
4.2.3.1.1 Foundation for Equipment - Turbine 1 ls 1,00 1,28
4.2.3.1.2 Foundation for Equipment - Turbine 2 ls 1,00 0,68
4.2.3.1.3 Foundation for Powerhouse ls 1,00 0,49
4.2.3.1.4 Foundation for Guard Post ls 1,00 0,27
4.2.3.2 Building -
4.2.3.2.1 Powerhouse - Contruction ls 1,00 2,42
4.2.3.2.2 Powerhouse - Arsitektural and Finishing ls 1,00 0,26
4.2.3.2.3 Powerhouse - Installation Overhead Crane ls 1,00 0,56
4.2.3.2.4 Guard Post - Contruction ls 1,00 0,37
4.2.3.2.5 Guard Post - Arsitektural and Finishing ls 1,00 0,11
4.2.3.3 Tailrace -
4.2.3.3.1 Tailrace Works ls 1,00 0,87
4.2.3.4 Access Road -
4.2.3.4.1 Pavement access road and existing road with sirtu ls 1,00 0,44
4.2.3.5 Fence and Gate -
4.2.3.5.1 Gate and Fence Installation ls 1,00 0,28
4.2.3.5.2 Drainage ls 1,00 0,15
4.2.4 Station Service (Gardu 7R2) ls 1,00 0,87
4.3 Piping Works -
4.3.1 Pipe Penstock Area -
4.3.1.1 Penstock Pipe - batch 1 (morning Glory - AB 1) ls 1,00 1,13
4.3.1.2 Penstock Pipe - Batch 2(AB 1-AB 5) -
4.3.1.2.1 Pipe Stringing ls 1,00 0,39
4.3.1.2.2 Pipe Welding and NDT ls 1,00 0,39

Page 1 of 3
LAPORAN BULANAN CONSTRUCTION
PLTM CILEUNCA
Nama Pekerjaan : Proyek EPC PLTM Cileunca 2 x 500 KW
Kontrak No. : 243.PJ/061/IP/2019
Kontraktor Pelaksana : Konsorsium PT. Maharani Prima - WWS Wasserkraft GmbH
Periode : 16 January 2021 - 15 February 2021
Report No : M-13 (02-2021)
Porsi Pekerjaan : LOKAL

KEMAJUAN PEKERJAAN TOTAL KEMAJUAN PEKERJAAN S/D


BULAN LALU BULAN INI BULAN INI
BOBOT
PER TOTAL EPC 13,11%
NO URAIAN PEKERJAAN SATUAN VOLUME PER TOTAL
BOBOT BOBOT CONSTRUCTION
22,86%
VOLUME VOLUME
(%) (%)
(%) BOBOT
VOLUME % Pekerjaan
(%)

4.3.1.2.3 Pipe Coating ls 1,00 0,34


4.3.1.3 Penstock Pipe - Batch 3 (AB 5 - AB 11) -
4.3.1.3.1 Pipe Stringing ls 1,00 0,39
4.3.1.3.2 Pipe Welding and NDT ls 1,00 0,39
4.3.1.3.3 Pipe Coating ls 1,00 0,34
4.3.1.4 Penstock Pipe Batch 4 (AB 11 - AB 15) -
4.3.1.4.1 Pipe Stringing ls 1,00 0,39
4.3.1.4.2 Pipe Welding and NDT ls 1,00 0,39
4.3.1.4.3 Pipe Coating ls 1,00 0,34
4.3.2 Powerhouse Area -
4.3.2.1 Pipe Installation ls 1,00 0,25
4.3.3 Hydrostatic test ls 1,00 0,25
4.4 Mechanical Works -
4.4.1 Powerhouse Area -
4.4.1.1 Turbine Installation -
4.4.1.1.1 Spiral Housing & Draftube (Unit 1 & 2) ls 1,00 -
4.4.1.1.2 Turbine Accessories ls 1,00 -
4.4.1.1.3 Power Cable & Control ls 1,00 -
4.4.1.1.4 Final Installation Turbine Accessories ls 1,00 -
4.4.1.2 Generator Installation -
4.4.1.2.1 Generator & HPU ls 1,00 -
4.4.1.2.2 Generator Accessories ls 1,00 -
4.4.1.2.3 Electric & Instrument ls 1,00 -
4.4.1.2.4 Final Installation Generator & Electrical ls 1,00 -
4.5 Electrical, Instrument & Control Works -
4.5.1 Powerhouse Area -
4.5.1.1 Cable Pulling ls 1,00 -
4.5.1.2 Switchgear Installation ls 1,00 -
4.5.1.3 Main Transformer Installation ls 1,00 -
4.5.1.4 Station Service Trafo Installation ls 1,00 -
4.5.1.5 SKTM Works ls 1,00 0,75
4.5.1.6 Gardu Tembok Works ls 1,00 0,75
4.5.1.7 Grounding System ls 1,00 0,07
4.5.1.8 Lighting ls 1,00 0,02
4.5.1.9 CCTV ls 1,00 0,02
4.5.1.10 Air Conditioning ls 1,00 0,02
4.6 Commissioning and Completion -
4.6.1 General -
4.6.1.1 Training (Class & Site) ls 1,00 -
4.6.1.2 Brosure, Catalog, Spare Parts ls 1,00 -
4.6.1.3 SOP & Maintenance Procedure ls 1,00 -
4.6.1.4 As Build Drawing & MDR (Asing) ls 1,00 -
4.6.1.5 As Build Drawing & MDR (Lokal) ls 1,00 0,06
4.6.2 Electrical -
4.6.2.1 Gardu Tembok Test ls 1,00 0,13
4.6.3 Commissioning & Running Testing -
4.6.3.1 Commissioning -
4.6.3.1.1 Preparation Test ls 1,00 -
4.6.3.1.2 No Load Test ls 1,00 -
4.6.3.1.3 Load Performance Test 40%, 60%, 80% and 100% ls 1,00 -
4.6.3.1.4 Emergency Overload Test ls 1,00 -
4.6.3.1.5 Stop Rejection Test ls 1,00 -
4.6.3.1.6 Over Speed Test For Relay Over Speed ls 1,00 -
4.6.3.1.7 Temperature Measurement On Load Test ls 1,00 -
4.6.3.1.8 Start and Automatic Stop Test ls 1,00 -
4.6.3.1.9 Vibration And Noise Test ls 1,00 -
4.6.3.1.10 Guide Vane And Generator Output Test ls 1,00 -
4.6.3.1.11 Index Polarity Test ls 1,00 -
4.6.3.1.12 Report ls 1,00 -
4.6.3.2 Test Run -
4.6.3.2.1 Performance Test (Non-Stop) ls 1,00 -
4.6.4 Final Report & Handover -
4.6.4.1 Closed Out Report ls 1,00 0,14
4.6.4.2 Hand Over Unit 1 & Unit 2 ls 1,00 0,05

Page 2 of 3
LAPORAN BULANAN CONSTRUCTION
PLTM CILEUNCA
Nama Pekerjaan : Proyek EPC PLTM Cileunca 2 x 500 KW
Kontrak No. : 243.PJ/061/IP/2019
Kontraktor Pelaksana : Konsorsium PT. Maharani Prima - WWS Wasserkraft GmbH
Periode : 16 January 2021 - 15 February 2021
Report No : M-13 (02-2021)
Porsi Pekerjaan : LOKAL

KEMAJUAN PEKERJAAN TOTAL KEMAJUAN PEKERJAAN S/D


BULAN LALU BULAN INI BULAN INI
BOBOT
PER TOTAL EPC 13,11%
NO URAIAN PEKERJAAN SATUAN VOLUME PER TOTAL
BOBOT BOBOT CONSTRUCTION
22,86%
VOLUME VOLUME
(%) (%)
(%) BOBOT
VOLUME % Pekerjaan
(%)

TOTAL 57,33 11,81 1,29 13,11 22,86%

Diajukan Oleh: Diperiksa Oleh: Disetujui Oleh:


Konsorsium PT. Maharani Prima - WWS Wasserkraft GmbH PT. LAPI ITB PT. Indonesia Power

Page 3 of 3