Warsak - DRAFT - Packages Phyisical Progress in %age - 13.04.2021
Warsak - DRAFT - Packages Phyisical Progress in %age - 13.04.2021
2021
1 USD 0.914 €
PHYSICAL PROGRESS OF WORKS AND SERVICES 1 Euro 175 PKR Percent Share & Physical Progress -April 2021
1 US$ 160 PKR
1 Package - I (Fast Track) Trashrack Cleaning and Handling Machine 2,317,000 € 2,317,000 € 100% Completed 2.11% 100% 2.11%
US$ 4,569,000+ PKR
2 Package -II (Fast Track) Spillway Gate Wire Rope Hoist System 4,291,411 € 100% Completed 3.90% 7.96% 100% 3.90%
19,957,000
3 Package - III (Fast Track) Supply of Complete Stator Winding 2,147,000 € 2,147,000 € 100% Completed 1.95% 100% 1.95%
Package IV (Contract No. PKR 896,292,000 (exclusive
4 Civil Works 5,121,669 € Signing of Contract is scheduled on April 12th, 2021. WRC 4.65% 0% 0.00%
GMHD/C-01) local taxes)
Euro47,755,014.06+US$24,6 NOC is released by AFD and expected to held the pre- 75.04%
Package – V+VI, (Contract No
5 E&M Work 54,229.06 and PKR 77,449,113 € clarification meeting in April 2021 and contract signing in WRC 70.39% 0% 0.00%
GMHD/E&M-02)
1,251,790,595.36 May 2021
Contract No.
US$ 413,108.49 and PKR
6 ICB/AFD/H&R/01, Awarded to Flood Management (Equipment) 628,002 € WRC 0.57% 15% 0.09%
43,803,000
M/s CDIGITAL on 22.07.2019
7 Flood Management for two CNR Trainings Euro 44,240 44,240 € 0.04% 0% 0.00%
Community Development & Accompanying
8 PKR 59,580,000 340,457 € Mott MacDonald Pakistan (MMP 0.31% 0% 0.00%
Measure (Consultancy Contract)
Community Development & Accompanying
9 Euro 500,000 500,000 € Mott MacDonald Pakistan (MMP) 0.45% 0% 0.00%
Measure (Works Contract)
2.37%
JV of M/s GLM Engineering
Sustainable Sediment Management Euro 231,505 and PKR COOP, M/s Nespak (Pvt) Ltd &
10 522,728 € 0.48% 0% 0.00%
(Consultancy Contract) 50,964,000 Hagler Bailly Pakistan (Pvt) Ltd on
14.01.2021
JV of M/s GLM Engineering
Sustainable Sediment Management (Works Euro 208,196 and PKR COOP, M/s Nespak (Pvt) Ltd
11 475,942 € 0.43% 0% 0.00%
Contract) 46,855,500 &HaglerBailly Pakistan (Pvt) Ltd
on 14.01.2021
Sustainable Sediment Management (M/s ISRIP
12 PKR 17,417,000 99,526 € 0.09% 100% 0.09%
WAPDA Service)
Enhancement of Workshop Equipment
13
(Equipment)
0.95% 0.95% 0.31%
13.1 Lot 1 US$ 410,000 374,857 € Delivery of Lot-01 is expected in the last quarter of 2021 WRC 0.341% 50% 0.17%
13.2 Lot 2 Euro 12,400 and US$ 70,300 76,674 € Delivery of Lot-02 is expected in the last quarter of 2021 WRC 0.070% 50% 0.03%
Consulting Services Activity 1 a - Sediment Euro 188,884 and PKR Final version of Detailed Engineering Design of Hopper
14 Consulting Services 1a 244,202 € WRC 0.22% 95% 0.21%
Management Structure 9,680,651 Structure shall be submitted by WRC in April 2021
Euro 101,048 and PKR Would be Coming into Force after conclusion of the
20 Consulting Services 6 Consulting Services Activity 6 - Training 116,975 € WRC 0.11% 0% 0.00%
2,787,250 Activity 3
Euro 112,594 and PKR
21 Amendment 2.1 Flood Management (Consulting Services) 205,116 € In progress WRC 0.19% 20% 0.04%
16,191,382
Technical and Financial Proposal of WRC is submitted
Sustainable Management Strategy, (Consulting Euro 265,586 and PKR
22 Amendment 2.2 284,108 € to WAPDA. It would be coming into force after signing WRC 0.26% 0% 0.00%
Services) 3,241,378
the said proposal
Progressing in parellel to the Works Progress of the
23 Administrative Service Administrative Cost of the Employer (WAPDA) Euro 9,000,000 9,000,000 € 8.18% 8.18% 40% 3.27%
Active Packages
GRAND TOTAL (EURO) 110,029,353 € * The currency rate is taken as an average value 100.00% 12.55%