Professional Documents
Culture Documents
2018 - APC Part 2 Assessors Notes
2018 - APC Part 2 Assessors Notes
PRACTICE PROBLEMS
CONTENTS
1) Candidates’ Role
2) Candidates’ Experience
3) Depth of Answers
5) Notes to Assessors
6) Marking
7) Acceptance Standard
8) General Notes
Page 2
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
2.1 In many cases, Candidates would not have much experience of the
situations encountered in this Final Assessment. This should be kept in
mind when carrying out your assessment.
3.3 The answers given by Candidates should show that they had identified the
problem, recognised a practical solution and given constructive professional
advice or solid arguments to the recipient. You should put yourselves in the
position of the recipient and ask if you have received proper advice on the
problem or if you could easily reject the arguments.
Page 3
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
4.2 Candidates should begin their answers with a brief introductory description
of the matter being asked, such as “With reference to the telephone
conversation with you yesterday regarding …”, “We refer to your query
regarding …”, etc. They should not jump straight to give points of answers.
4.4 It is not suggested that you should mark down the paper if the format and
style of the answers are not in the above desirable conditions. However,
answers should be presented in a professional manner such that the
recipient would understand the answers.
5.2 The time spent in preparing the Notes to Assessors is much more than that
allowed to Candidates. Therefore, Candidates should not be expected to
mention all the points given in the Notes to Assessors for full marks. It
should be considered as Acceptable if a Candidate could address the core
issues.
Page 4
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
6.0 MARKING
6.2 See “NOTES TO CANDIDATES” below for the number of questions and the
passing marks.
6.3 A marking sheet is given in table form for you to assign marks.
6.4 Just before the final total of each day’s paper, a line is given for you to add
discretionary bonus marks of up to 2.5 marks. The bonus marks should be
given to Candidates for good presentation, good English, good handwriting,
and those who deserve a few more marks after your second-thoughts on
their overall performance and potential.
6.5 You should not write notes or other marks on the submissions which you
are assessing since such notes or other marks may influence the next
Assessor’s marking.
7.1 In case you desire not to follow the Notes to Assessors in detail or you want
a simper guide, you are offered the following questions to ask yourself
when giving your marks:
(a) Would I sign the letter for dispatch after minor editing corrections as
supervisor?
(b) Would the recipient consider sufficient advice has been given?
(c) Could the recipient easily reject the arguments?
7.2 If the answers are “yes” to (a) and (b) and “no” to (c), then the answer
should be considered as Acceptable or better.
7.3 The most important question when concluding the overall result as a pass
or a failure would be “Would I employ the Candidate to work as a
qualified Quantity Surveyor with the ability to resolve problems in a
professional manner?”
Page 5
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
8.1 This year’s questions are intended to test Candidates’ knowledge from a
wide spectrum of issues, with weight given to their associated and extended
thinking.
9.1 Headings to questions are for ease of identification only and do not form
part of the questions.
DAY 1
Page 6
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
9.4 The total mark of each day’s paper is 50. The passing mark of each day’s
paper is 55% of the total mark of that paper. Candidates who have
passed both days’ papers will be considered as having passed the APC
Practice Problems.
Page 7
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Abbreviations
GCC 1999 General Conditions of Contract for Building Works 1999 Edition
published by the Government of the Hong Kong Special
Administrative Region.
Candidates should clearly state the standard form of contract upon which their
answers are based.
Page 8
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
DAY 1
Page 9
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
You are the in-house quantity surveyor of property owner Hubbo. Hubbo is
planning to refurbish its existing industrial building in Kowloon Bay to attract more
affordable tenants. The whole building will be vacated before refurbishment.
The schematic design of G/F, 1/F and 2/F was reviewed this morning between
Hubbo and the designer. The following two proposals i.e. P1 and P2 have been
identified for further study:
P1. Add two pairs of escalators connecting G/F, 1/F and 2/F to attract F&B
tenants and convert the areas around the escalators to public foyers on the
three floors. Refer to Attachment A showing the proposed changes. The
storey height is 6.5m for G/F and 5m for 1/F and 2/F. There is no basement.
You are required to estimate the cost implication of this proposal. You may
need to talk to the designer for further details. Record any backup
discussions or assumptions.
[10 marks]
P2. Build a footbridge 15m long x 4m wide on 2/F across road to connect to an
existing commercial development also owned by Hubbo and having a
connectable lobby also on 2/F. You are required to prepare a query list of 10
items to clarify the choices of design and scope of work which may affect the
costs very differently, and deserve attention for discussion with the Project
Director and the designer. Cost estimate is not required at this moment. It
would be premature to ask for structural member sizes.
[5 marks]
Page 10
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Page 11
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Objective
Identify the work required to add escalators and provide modern public foyers,
and prepare cost estimate with sufficient account for the work assumed; and
Cost Estimate for P1 – Add two pairs of escalators connecting G/F, 1/F and 2/F
and convert surrounding areas to public foyers
Page 12
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
On 2 floors
Glass or metal, with curbs
Length 8.5m x 2 x 2 levels x rate
Page 13
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
j. Lighting and power, air conditioning, fire sprinklers, public 1.50 ~ 2.50
address, CCTV
Floor area x rate
Bonus marks if records given of discussions with the designer to support the
assumptions.
Composite items with approximate quantities x rates are preferred to lump sums
only.
Detailed listing of all work like a Bill of Quantities is not expected and in fact not
recommended.
[10 marks]
Page 14
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Cost Estimate for P2 – Build a footbridge of 15m long x 4m on 2/F across road to
connect to an existing commercial development
Footbridge itself
6. Elevations - Open with railings or fully enclosed? Materials and type? If fully
enclosed, air conditioning and additional fire services protection required.
9. M&E services – Any special provisions over the normal? Extension distance
from main services in existing buildings?
Existing buildings
12. Elevations – special provisions other than forming openings and jointing?
Fire or security shutters?
Page 15
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Items are expected to have more encompassing scope and depth. An item like
“Type of floor finishes.” would be considered as too light.
[5 marks]
[total 15 marks]
Page 16
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Developer Bumba recently won a land bid for a commercial site. Bumba is going
to develop it into an office building – Project X. Bumba has just appointed your
firm as the consultant QS.
Project X particulars:
Site area = 2,000m2
No. of storeys = 40 (no basement)
Typical floor-to-floor height = 4.2m
Typical floor area = 1,500m2
You are required to respond to the email below from Bumba’s Commercial
Manager.
Dear QS,
The design team is studying two structural frame options: A) In-situ reinforced
concrete frame; and B) Composite steel frame i.e. steel columns and beams with
in-situ reinforced concrete core. Pre-stressing or post-tensioning is not considered
at this moment.
1. Please estimate the structural cost difference between these two options.
Please show your build-up of the elemental cost per m2 construction floor area
(CFA) with assumptions in the absence of structural design information. The
effects on the substructure and foundations can be excluded.
Attachment S is the BQ extracted from the Main Contract of Project S for your
estimation of structural option A. The BQ quantities have no error but the rates
would need careful review.
[10 marks]
2. Apart from the structural frame, please advise on the very different impacts of
using composite steel frame instead of reinforced concrete frame on the rest of
the construction costs and procurement.
[5 marks]
Thanks.
CM Lee
[total 15 marks]
Page 17
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Page 18
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Page 19
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Page 20
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Page 21
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Page 22
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Page 23
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Page 24
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Page 25
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Candidates should firstly work out the approximate structural ratios from the BQ of
Project S. Please see Appendix 1 to Notes to Assessors. Candidates should
exclude the substructure works and the non-structural walls or work.
Obviously, pile caps, ground beams and beds are to be excluded. It is also
reasonable to assume that the 100mm thick walls in the BQ are non-structural
walls to be excluded. 150mm thick walls may or may not be. Good Candidates
should state doubt and make assumptions. The other walls are structural walls. It
is straightforward to work out the concrete ratio per floor area after making
reasonable exclusions.
Page 26
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Market rates based on recent tenders are normally used for pricing common
structural items. However, the BQ rates might contain irregularities due to
contractor’s pricing strategy or other project specific issues. They should therefore
be rationalized before use. Project S BQ rates were tendered for in 1Q2014. It
may be too crude to use published Tender Price Index to adjust to the present.
Recent reasonable market rates should be used. If the Candidate chose to use
Project S BQ rates, he should demonstrate the adjustment to the rates for the
difference in the price levels between the two projects. The formwork rates in the
given BQ after published Tender Price Index adjustments would be still quite low.
If the Candidate simply adjusted all rates by considering only the difference in
published Tender Price Index, his answer should be marked down. No published
Tender Price Index has been given to the Candidates. They may make sensible
assumptions as appropriate.
Miscellaneous 5% 164
Total 3,448
Page 27
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Miscellaneous 5% 323
Total 6,786
While different calculated approaches to arriving at the cost per CFA are
acceptable, the use of structural ratios backed up with some calculations and
assumptions should be the quickest.
Page 28
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
The structural ratios for the in-situ reinforced concrete option should be based on
those of Project S. The structural ratios for concrete work for the composite steel
structure option should preferably be by pro-rata from Project S otherwise the
differences may not be easily justified.
Based on the above build-up, the cost of composite steel frame is around 120%
higher than the cost of the in-situ reinforced concrete frame. It is considered
acceptable if the Candidate’s estimate of the difference is up to 140%.
[10 marks]
Apart from the structural cost, there could be impacts on the following:
2. Walls – More non-structural walls to replace the structural walls outside the
core. More floor, wall and ceiling finishing areas created due to thinner walls.
Junctions between non-structural walls and partitions with fireproof coated
steel columns and beams and with corrugated metal decking need special
treatment.
4. Metal decking – The interfacing details between corrugated metal decking and
beams or columns and around edges must be carefully thought out before
procurement to avoid variations.
5. Hangers for architectural work and M&E works – Hangers fixed to steel beams
or concrete slabs on steel decks would be by welding or special bolting.
Hangers fixed to fireproof coated steel beams would also need fireproof
coating.
Page 29
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
8. Design – The design of the steel frames must therefore be frozen very early for
tendering and in any case before prefabrication. Subsequent design changes
are usually costlier than changes to reinforced concrete structure.
10. Plant – Special cranes must be used for the erection of the steel members.
They may not be continued to be useful after the erection of the structure.
Other cranes may need to be used.
Candidates’ answer covering 70% of the points above warrants full mark.
[5 marks]
Please see Appendix 1 following this page.
[total 15 marks]
Page 30
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Rebar
Total 9,068,980 kg
Page 31
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Page 32
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Rebar
With steel columns and beams, the rebar ratio
should be reduced significantly, say overall 160 kg/m3
Formwork
Slabs; allow for slab mainly inside RC core, say 0.150
Columns; smaller than Option A say by 20% 0.222
Walls; same as Option A 0.657
Beams; most replaced by steel beams, say 0.120
Sundries; same as Option A 0.093
1.242
Say 1.25 m2/m2 CFA
Page 33
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Your subordinates have completed the attached draft Bill No. 3. The piling and
excavation works are subject to remeasurement. Please edit and bulk check the
bill with reference to HKSMM4 (without amendments by Preambles) and give the
marked copy and/or separate notes to your subordinates for discussion.
[10 marks]
Page 34
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
BILL NO. 3
LANDSCAPED WALKWAY
BILL NO. 3
LANDSCAPED WALKWAY
Notes
1. Finishes and waterproofing to walkway
are measured under Bill No. 4;
2. Electrical and fire services installations
(except external lighting pole
and fittings) are measured separately.
PILING
Plant
Boring
Page 35
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
BILL NO. 3
LANDSCAPED WALKWAY
Grouting
Steel plates
F 45 mm diameter 6,591 kg
G 219 mm diameter 18 nr
Page 36
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
BILL NO. 3
LANDSCAPED WALKWAY
PILE CAPS
Excavating
3
A 1.50 - 3.00 m deep 143 m
Filling
Excavated material
Disposal
CONCRETE WORKS
IN-SITU CONCRETE
2
D 75 mm thick 10 m
Page 37
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
BILL NO. 3
LANDSCAPED WALKWAY
3
A pile caps 157 m
3
B tie beams 76 m
3
C suspended slabs; 300mm thick 1,440 m
REINFORCEMENT
General reinforcement
FORMWORK
Fair-faced formwork
Vertical surfaces
2
F pile caps 84 m
2
G sides of tie beams and slabs 73 m
Flat surfaces
2
H soffits of suspended slabs 9,600 m
Page 38
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
BILL NO. 3
LANDSCAPED WALKWAY
Spatterdash
2
A concrete floor surfaces 4,800 m
2
B finished with steel trowelled floor 4,800 m
Sundries
To Summary HK$
[10 marks]
Page 39
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Objective
The objective of this question is to test Candidates’ knowledge of the SMM rules
and ability in bulk checking the BQ item descriptions and quantities, which is a
fundamental competence to be expected from a qualified QS.
Page 40
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
BILL NO. 3
LANDSCAPED WALKWAY
Why “Plastering and
Notes Paving” is included later in
1. Finishes and waterproofing to walkway this Bill?
are measured under Bill No. 4;
2. Electrical and fire services installations
(except external lighting pole
and fittings) are measured separately. “ALL PROVISIONAL”?
D Steel H-piles; 305 x 305 x 323 kg/m 35 m SMM Section V(e).2.1.1 &
(In 4 No.) 2
Total length of raking pile
E Steel H-piles; 305 x 305 x 223 kg/m; raking 145 m shaft ≤ 10.00 m and in
not exceeding 15 degrees from vertical further stage of 5.00 m
(In 4 No.) not stated
Mismatch between numbers of Pile casing longer than pile
pile holes and pile casing? holes?
Page 41
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Steel plates
E Size 600 x 600 x 60 mm thick (In 8 No.) 1,355 kg Only 8 No. capping plates
to 18 No. piles?
and hence any effect to
Reinforcing starter bars to pile heads the quantity, weight of
steel plates?
Ribbed steel reinforcing bars;
general reinforcement 40 mm diameter?
as there is no 45 mm
F 45 mm diameter 6,591 kg diameter steel reinforcing
bars
and hence any effect to
Pile head treatments
the quantity, weight of
Cutting off heads of pile; straightening or reinforcing bars?
bending and cleaning projecting
reinforcement; removing debris from site SMM Section V(f).8
Length to be cut-off
G 219 mm diameter 18 nr missing
SMM Sections V(e).10, V.(e)12 Items for test loading of piles, concrete coring test for
testing founding level and proving bedrock missing
Page 42
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Disposal
CONCRETE WORKS
IN-SITU CONCRETE
Page 43
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
3
B tie beams 76 m
Any suspended beams?
3
C suspended slabs; 300mm thick 1,440 m
REINFORCEMENT
Double check reinforcement quantities
if not provisional;
Ribbed steel reinforcing bars The steel ratios are unreasonably low:
4,512 kg / 157 m3
= 29 kg / m3
General reinforcement 68,373 kg / (76 + 1,440) m3
= 45 kg / m3
D 32 mm diameter in pile caps 4,512 kg
SMM Section VII (c)2.1
E bar diameter of any size in tie beams 68,373 kg Nominal size of bar
SMM VII (c)2.1.3 reinforcement not stated
Item for links, stirrups and
binders missing
FORMWORK Review as fair-faced
formwork not normally
Fair-faced formwork used for pile caps, tie
beams and slabs below
ground level.
Vertical surfaces
2
F pile caps 84 m
Why formwork to sides of
G sides of tie beams and slabs 73 2 slabs?
m
Edge formwork?
Suspended slabs?
Flat surfaces
Review if left-in formwork
H soffits of suspended slabs 9,600 m
2 should be used for
Review the quantity of soffit suspended ground floor
formwork as it is double the slabs.
area of concrete floor measured
below.
Page 44
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
To Summary HK$
Candidates who rightly pointed out 70% of the above remarks warrant full mark.
[10 marks]
Page 45
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
You are the consultant QS of a 2-storey warehouse development in Tai Po. The
procurement approach is intended to be lump sum contract based on drawings
and specification, with payment to the Contractor on a milestone basis. Tender
documents have been prepared and are ready for tendering.
The Employer has set a tight time frame for completing the development.
Furthermore, the budget for the development is tight and it is difficult for the
Employer to raise additional finance if the budget is exceeded. Accordingly, the
design consultants and you have already worked together to arrive at a completed
and cost-effective design for the development.
In order to ensure the development be completed within the tight budget and on
time, the Project Manager has just recommended the Employer to change the
current contractual arrangement by adopting target cost contract with a pre-
determined pain/gain share arrangement.
The Project Manager believes that cost savings and early completion can be
achieved if target cost contract is adopted, and accordingly the development can
be completed within the tight budget and timeframe.
Having said that, the Employer is unsure whether the said benefits of using target
cost contract is applicable to the warehouse development and would like you to
advise on the following in the form of a letter:
(b) Your recommendation on whether target cost contract should be adopted for
this warehouse development.
[5 marks]
[total 10 marks]
Page 46
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
“cost” here refers to the costs to the Contractor, not the costs to the Employer.
The following are additional requirements to be included under the current tender
documents if target cost contract is adopted:
(b) Target cost – A pre-determined target cost or a mechanism for fixing the
target cost based on the tenderer’s estimate of the costs will be stated.
(Bonus point: The target cost plus Contractor’s fee and the Employer’s
contingencies for permissible adjustments to the target cost should be less
than the maximum budget. The target cost itself should contain an
allowance for changes not permissible to adjust the target cost.)
(c) Adjustment of target cost – Circumstances that the target cost will be
adjusted will be specified. The normal definitions of variations and events
leading to loss and expense compensation under a lump sum contract will
be reduced. “Variations” will usually be defined to mean a change of the
scope of the Works only, excluding any necessary changes to complete the
Works.
(d) Fee – The tenderers will be asked to quote their percentage fees or lump
sum fees or a combination of both, with or without the benefit of a cost
estimate. The percentage fee will be expressed as a mark-up on the actual
costs, and may be calculated on a sliding scale. The fee can be specified
to include lump sum preliminaries, lump sum attendance, percentage
overheads and profit. A definition of what should be included in the
preliminaries, attendance and overheads will be stated.
(e) Pain/gain share – Apart from the fee, a pre-determined formula to calculate
the pain/gain share of the difference between the final actual costs and the
target cost will be stated. The pain/gain share may be of a sliding scale. A
cost cap may also be set so that any cost overrun beyond the target cost by
a certain percentage is not reimbursable to the Contractor.
Page 47
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
(f) Contractor’s cost saving proposal – Any cost saving proposal by the
Contractor will not be regarded as variations and will have no effect on the
target price so as to encourage the Contractor to suggest cost saving
proposals. The cost saving proposals must be agreeable to the Employer.
(g) Payment – The Contractor will be reimbursed the actual costs supported by
an open book cost accounting system.
(h) Definition of ‘Cost’ and ‘Fee’–What can be and cannot be included in the
actual costs to be reimbursed will be clearly stated. The definitions of ‘Cost’
and ‘Fee’ will be complementary with one of them to contain a catch-all
statement that any cost not falling into one will be deemed to be included in
the other.
(i) Cost estimate – The tenderers may be required to submit an estimate of the
costs based on the drawings and specification. The estimated total cost
plus fee and contingencies may become the target cost. The breakdown
will serve post contract monitoring of the actual costs. The rates will be
used to value cost adjustment to the target cost. It is possible that no cost
estimate is expressly mentioned. In any case, the Contractor will be
obliged to submit cost estimate and regular financial reports during the post
contract stage.
Page 48
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
(l) Bonus point: Lump sum price arrangement - It is also possible that the
tenderers are required to give a lump sum price based on the drawings and
specification plus some contingencies to become a target price. Adjustment
of the lump sum price will resemble the normal lump sum contract. The
only differences will be that Contractor’s cost saving proposal will be
permitted and pain/gain share mechanism will be in place.
Candidates’ answer covering 60% of the points above warrants full mark.
[5 marks]
Your recommendation of whether target cost contract should be adopted for the
current development
Cost savings by adopting target cost contracts are mainly achieved by:
For this project, it should be considered whether the above conditions exist.
Despite the design for the development is completed for the Contractor to
establish a realistic target cost, together with the inclusion of a cost cap so that
any budget overrun will be wholly borne by the Contractor, the adoption of target
cost contract is not recommended for the current development due to the following
reasons:
(a) Design already completed – Given the completeness of the design, there
is little room for early contractor involvement to realize the potential of
cost savings by providing advice on buildability. Cost saving proposals
may likely downgrade the existing design.
(b) Simple project nature - Given the simplicity in nature of the development,
it is unlikely that the Contractor can suggest significant cost saving
proposals.
Page 49
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
(c) Tight construction time frame – The already tight construction time frame
renders early completion of the development difficult. Any savings
related to site supervision cost are unlikely.
(a) Employer’s own costs - Extra costs will be required for arranging
trainings and partnering workshops to enhance the level of
understanding and cooperation between the Employer, the consultants
and the Contractor.
(b) Additional consultancy fee – The consultants may request for additional
fees, especially in providing more resources in checking the Contractor’s
open-book accounts against many invoices and receipts.
Page 50
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
(a) Cost certainty – The main concern of the Employer is cost certainty.
Target cost arrangement does not excel in offering cost certainty to the
Employer.
(b) Target setting – Incorrect target setting can drive a focus on raising the
target through claims rather than suggesting innovative savings.
(e) Well suited to long term relationships – Use of target cost favours the
establishment of long term relationships but not for one-off project.
Candidates’ answer covering 60% of the points above warrants full mark.
[5 marks]
[total 10 marks]
Page 51
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
DAY 2
Page 52
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
You are the consultant QS of a sports centre project. The Employer has awarded
the piling and superstructure works under a single contract where the Works
(except the foundation works) are to be designed by the Architect while the
foundation works are to be designed by the Contractor. The Contract included a
set of Bills of Quantities for the superstructure part while the Contractor was
required to submit a lump sum price with quantity and rate breakdown for the
foundation works in the tender (refer to Attachment A for part of the breakdown).
At the tender stage, apart from the provision of a loading schedule for the piles to
support, the Project Structural Engineer has prepared a design for the piling and
incorporated the same as part of the Tender Booklet for tenderers' reference. The
piling design was marked “for reference only”, which comprised 200 No. 305 x 305
x 180 kg/m driven steel H piles with an average length of 35m.
One week after the Commencement of the Works, the Project Structural Engineer
issued a Site Instruction No. SE-002 to revise the loading schedule. The
Contractor, based on the revised loading schedule, prepared and submitted a
revised piling schedule.
At the following site meeting, the Contractor reported that the revised piling
schedule came up with 190 No. 305 x 305 x 180kg/m driven steel H piles with an
average length of 35m, and submitted a quotation for a net addition of $700,000 to
the Contract Sum (refer also to Attachment A).
The Project Structural Engineer subsequently carried out a check and agreed to
the Contractor's submitted revised design but has query about the cost implication
of the variation. In his opinion, the variation should result in a cost reduction for 10
No. of piles, when compared with the original design.
The Project Manager asks for your opinion on the above. You are required to
provide a contractual analysis and advise on the proper fact finding approach to
deal with the issue. The Project Manager is a meticulous person and would not be
satisfied with a simple broad-brush answer.
[12 marks]
Page 53
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Attachment A
Extract from the Contractor’s quantity and rate breakdown for foundation works in
the accepted tender:
Page 54
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Objective
Contractual Analysis
1. The Tender Documents were prepared based on the Architect's design with
Bills of Quantities, but the foundation works were required to be included in
the tender based on Contractor's design. The quantities estimated by the
Contractor based on his design and indicated in the lump sum price
breakdown for the foundation works shall not form part of the Contract.
2. The piling design prepared by the Project Structural Engineer though issued
to the Contractor for tendering was marked to be for reference only and
therefore does not form part of the Contract.
3. The mere fact that the Contractor’s quantities in the price breakdown match
nicely with the reference design prepared by the Project Structural Engineer
does not necessarily follow that the quantities or the reference design shall
form part of the Contract.
4. For the same Contract Sum, the Contractor shall be and shall only be
responsible for providing a piling design sufficient to support the building in
compliance with the original contract requirements. Any up or down errors
made in the preliminary design or in the estimated quantities or rates shall not
result in any adjustment to the Contract Sum or completion time.
5. Instead of comparing against the quantities stated in the price breakdown, the
variation shall be valued by comparing the piling design that has or would
have been prepared by the Contractor fulfilling the original contract
requirements, i.e. the baseline piling design based on the original loading
schedule, against the revised piling design based on the revised loading
schedule under Site Instruction No. SE-002.
Page 55
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Suggested Approach
1. In order to compare between the original and the revised piling designs, it is
necessary to identify the “baseline design” which is the one fulfilling the
original contract requirements (i.e. the original loading schedule).
5. Even though the acceptable design may result in fewer or lighter piles than
those stated in the lump sum price breakdown, the Project Structural
Engineer cannot insist on adding more piles. The baseline design so
accepted shall be used for the valuation of the variation as described
earlier.
7. If the Contractor refuses to submit any baseline design, advice from the
Project Structural Engineer should be sought regarding a notional baseline
piling design for the purposes of valuation of the variation.
Page 56
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
[12 marks]
Hi,
I refer to the Contractor’s claim submitted last week claiming extension of time of
15 days and an extravagant amount of HK$500,000. Having studied the
Contractor’s submission, I am of the view that the claim is unjustifiable under the
Contract and shall be struck out at once for the following reasons: -
1. Although there is no dispute that the disruptions were caused by the late
release of information by the Architect, most of such disruptions indeed ran
parallel with the Contractor’s own delay. The Contractor would still have
been in delay had there been no late release of information causing the
said disruptions. As such, no extension of time shall be granted.
[5 marks]
2. By the same token, the Contractor shall not be entitled to any monetary
compensation for disruptions which run concurrently with the Contractor’s
own delay.
[5 marks]
3. Although the Contractor has served an extension of time and loss &
expense claim in accordance with the Contract, the particulars submitted by
the Contractor, though appearing to be comprehensive in terms of volume,
are not satisfactory as they do not cover the FULL details of each of the
particulars of the claim.
[5 marks]
Could you please look into this and give me your advice for my further discussion
with our Finance Director?
In your reply to Mr. Chan, you should analyze the contractual position with
reference to the relevant clauses of the Contract and advise whether there are
sufficient grounds to strike out the Contractor’s claim.
[total 15 marks]
Page 57
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Objective
“concurrent delay” has very special and strict meaning as decided by court cases,
but there is no need to dwell into that detail for the purpose of this Question No. 2.
“overlapping delays” is used here to avoid going into that complication.
“Contractor’s delay” here means a delay not entitling the Contractor to extension of
time.
Subject to the contract provisions, the general principle of law is that the Employer
is obliged to afford the agreed time to the Contractor to carry out the Works. If
during the course of the Works, the remaining time afforded for carrying out the
balance of the Works is reduced due to an Employer’s delay, the Employer shall
compensate the time so reduced by granting an extension of time of equal
magnitude. Whether the remaining time is already not achievable due to
Contractor’s delays is immaterial. The foregoing is an example of the application
of the principle that the Employer shall not prevent the Contractor from carrying
out the Works, and the Employer shall not benefit from his own prevention.
If the work affected by the late provision of information lies on the critical path to
the completion of the Works, the late provision will reduce the remaining time
afforded for carrying out the balance of the Works and should entitle the
Contractor to extension of time.
Bonus point: Recent case laws in the UK decided that if it is expressly agreed in
the Contract beyond doubt that the Contractor will not be entitled to extension of
time due to Employer’s delay overlapping Contractor’s delay, the contract
agreement will be upheld. The standard forms of contract to be used for these
Practice Problems do not contain such provisions.
Page 58
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
‐ Similar principle applies in the case of GCC 1999 save that the relevant
provisions are Clauses 50(1)(b)(vii) and 63(a) (read together to confer valid
ground), and Clause 50(2A) (similar to clause 25.3(6) of SFBC 2005 / 2006).
[5 marks]
There is a school of thought that if a compensable event occurs during the period
of Contractor’s delays, since the Contractor would have incurred the loss and
expense anyway, the compensable delay would not cause additional loss and
expense to the Contractor and the Employer would not need to compensate the
loss and expense.
Page 59
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
An argument would be that if a view is taken prospectively at the time of the start
of the compensable event, extension of time would need to be granted for the
compensable event, which invariably is also an Employer’s delay. The period of
extension would cause loss and expense to the Contractor and the Contractor
should be compensated. During the period until the end of the extended period,
the Contractor is free to work at his own pace. Any slow progress during this
period should be affect the compensation.
Another argument is that after the start of the compensable event, its impact is
more dominant than that of the Contractor’s delay, e.g. lasting for a longer time.
Loss and expense should be compensated for the dominant delay.
Candidates are not expected to deliberate fully the different views and are allowed
to take one view or the other provided the rationale is reasonably put forward.
‐ It may be noted, however, that clause 27.3 requires that when a qualifying
event is partly contributed to or aggravated by the Contractor’s default, the
loss and expense should make a corresponding reduction. However, this
clause can only be read to mean that extra loss and expense caused by the
Contractor’s default over those caused by the Employer’s default should be
taken out, but it does not read to mean that the Employer is only
responsible for the extra loss and expense caused by him over those
caused by the Contractor.
‐ Similar principle applies in the case of GCC 1999 save that the relevant
provision is Clause 63.
Page 60
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
‐ For extension of time, clause 25.2 requires the Contractor to submit full
particulars with his second notice of an extension of time claim, and the
Architect is obliged to consider the extension of time entitlement after the
receipt of the second notice. However, there is no provision stating that the
submission of the full particulars must be a condition precedent to
considering extension of time. In fact, clauses 25.3(4), (7) and (8) permit
the Architect to take the initiative to review previous extensions of time to
the extent that he is able to do so based on the information available or so
far as fair and reasonable.
‐ For extension of time, Clause 50(3) authorizes the Architect to require the
Contractor to submit full and detailed particulars of the cause and extent of
the delay. However, if the Contractor fails to submit, the Architect shall still
consider the extension of time but only to the extent that he is able to do so
based on the information available.
‐ For loss and expense compensation, the principle is the same. Clauses
50(3) and (4) authorize the Surveyor to require the Contractor to submit
contemporary record and full and detailed particulars of the claim. However,
if the Contractor fails to submit, the Surveyor may still consider such claim
to the extent that the Surveyor is able to do so based on the information
available, subject to the proviso that the Surveyor shall not be obliged to
take account of any particulars received later than 180 days after the date
of the last certificate of completion of the Works.
[5 marks]
[total 15 marks]
Page 61
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
“Clause 1.20 - The possession date of the Site as stated elsewhere in the
Contract is for indication only. No monetary claim in connection
therewith will be entertained.”
Now two weeks later after the award of the Superstructure Contract, the Structural
Engineer just reported today that the foundation works were in serious trouble. A
number of critical footings without piles had been found to have been constructed
incorrectly and would require complete removal. It is expected that, with due
diligence, the foundation works can only be completed in 6 weeks, i.e. about 4
weeks later than the one month anticipated in the letter of acceptance. Another
big trouble is that the Foundation Contractor has already been in financial
difficulties. He may not be able to bear the costs of rectification of the footings and
may slow down or go bankrupt.
Page 62
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
You are not related to the project at all. The Employer has just called you after
hearing the report by the Structural Engineer, and requested you to act as a devil’s
advocate to critically see whether Particular Specification Clause 1.20 and Clause
1.21 are able to protect him from monetary claims that may be submitted by the
Superstructure Contractor when either of the following situations occurs:
(i) The Foundation Contractor still survives with financial support by the
Employer and the remaining foundation works can be completed in 6 weeks
from now for handover to the Superstructure Contractor.
Please provide your advice in a letter and explain your reasons with reference to
relevant contract provisions.
[10 marks]
Page 63
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Objective
Normally, this kind of clause would say that the possession date of the Site
as stated elsewhere in the Tender Documents is for indication only. The
date will be subject to confirmation upon the award of the Contract or by
means of an Architect’s Instruction after the award of the Contract. No
monetary claim will be entertained if the confirmed date is not later than a
certain date. This would give a limited period for the Contractor to take the
risk of a non-definite possession date.
The possession date of the Site has been confirmed in the Employer’s
letter of acceptance with no similar stipulation that this is still indicative.
The letter of acceptance is the concluding document confirming the offer
and acceptance process and shall take precedence over the Particular
Specification. The no claim intention should apply if the actual possession
date is within the one month as confirmed in the letter of acceptance, but
would not apply to the period beyond.
The Employer may argue that Particular Specification Clause 1.20 is wide
enough to refer to the date as stated in the letter of acceptance as
indicative only subject to further adjustment. This argument would appear
to be weak.
Page 64
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
The Contractor may also argue that there is no definite period for him to
take the risk. In the absence of a definite period, the tender validity period
may serve as a useful limit. The Contract is supposed to be awarded
within the tender validity period for immediate commencement after one or
two weeks’ notice. The no claim period can reasonably be interpreted as
no later than the end of such notice period but not beyond. It is considered
that this is the best approach to operate Particular Specification Clause
1.20.
Bonus point: The final defense available to the Contractor would be to see
whether the Contract contains provision for him to determine his
employment or terminate the Contract if the delay to site possession is
exceeding a certain permissible maximum period.
Clause 5.1 means that the Conditions of Contract take precedence over
the Particular Specification, but the letter of acceptance takes precedence
over the Conditions of Contract unless modified later in the Appendix upon
formal signing of the Contract.
Page 65
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Although the letter of acceptance shall not prevail over the Conditions of
Contract, it would be difficult to argue that the one month stated in the
letter of acceptance would be of no effect. It is because such information is
not contrary to the provisions in the Conditions of Contract and can be
interpreted as a supplement to the Conditions of Contract. The letter of
acceptance is issued later than the Particular Specification and shall
prevail over the Particular Specification.
Clause 47 stipulates that the date for commencement of the Works shall
be notified by the Architect within the period of time after the date of
acceptance of the Tender as stated in the Appendix to the Form of Tender.
Clause 48 requires that so much of the Site required to commence the
Works shall be given to the Contractor on the date for commencement.
Clause 48(2) entitles the Contractor to loss and expense compensation in
case of failure to give such possession.
Page 66
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
The Contractor may argue that the foundation works are of special nature
not belonging to his usual nature of work or the foundation works are
outside the scope of the Superstructure Contract, and therefore, he is not
obliged to take up the additional foundation works simply by way of an
Architect’s Instruction. However, it is normal for the Specification to
describe the scope of the Works and optional works. The additional
foundation works have been specified as possible optional works, there is
no reason to deny the validity of Particular Specification Clause 1.21 in this
manner.
As the possession date was supposed to be available one month after the
award of the Superstructure Contract, this should serve as a good
indication to the Contractor at the time of entering into the Superstructure
Contract regarding the time required to complete the additional foundation
works if so instructed, and hence the period of prolongation in respect of
which the waiver of monetary claim should apply.
The Contractor may also argue that breaking up and removal of the
incorrect footings are entirely abnormal. The extra time to do so should
not be counted in the period of waiver.
The conclusion of the above is that the maximum period of waiver that the
Employer can argue for is one month after the date of the letter of
acceptance and a reasonable settlement would be a shorter period to be
negotiated. The breaking up and removal of the incorrect footings should
not be included in the waiver.
Page 67
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
As far as the monetary waivers are concerned, the two situations (i) and
(ii) are both subject to the same arguments mentioned above. A possible
difference would be that the bankruptcy under situation (ii) may happen
any time within or beyond the 6 weeks’ periods estimated for situation (i).
Stoppage of work due to bankruptcy will require extra time to conduct
survey, to check and record the work done, to take over the incomplete
work, to retrieve past inspection records and test certificates, and to rectify
any defects found, not to mention the possible need to put the works out
for competitive tendering.
[10 marks]
Page 68
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
6 weeks after the award of the Main Contract to Smart Build Construction Co. Ltd.
(“Smart Build”), the Architect issued an instruction to Smart Build which requires
Smart Build to enter into a Nominated Sub-Contract with Bravo Engineering Co.
Ltd. (“Bravo”) for the Supply and Installation of MVAC Works.
Within 3 days from the receipt of the Architect’s instruction, Smart Build wrote to
the Architect rejecting the nomination of Bravo as the MVAC Nominated Sub-
Contractor on the following grounds: -
2. Smart Build noted that the Prime Cost Sum for MVAC provided in the Bills of
Quantities is HK$50 million while Bravo’s tender sum is HK$45 million only.
Bravo’s financial capability of completing the MVAC works is therefore
questionable. Furthermore, Smart Build considers that he has suffered a loss
of profit due to the difference between the Prime Cost Sum and the awarded
Sub-Contract Sum.
The Architect has just called you to request you to send him an email advising the
relevant contract provisions by noon tomorrow.
Page 69
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
[13 marks]
Page 70
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Objective
Under SFBC 2005/2006, the Contractor has the right to raise reasonable objection
to an Architect’s instruction requiring him to enter into a Nominated Sub-Contract
[clauses 29.2(1) & (3)].
Bravo has made his objection to the nomination within the time required under
clause 29.2(3). It is for the Architect to decide whether the objection is valid
[clause 29.2(5)].
If the Architect considers the objection to be valid, the Architect may withdraw the
nomination instruction per clause 29.2(5)(a). Alternatively, the Architect may
invoke clause 29.2(5)(b) and refuse to withdraw the nomination instruction despite
the valid objection with the caveat that the Contractor will have the right to
extension of time [clause 25.1(3)(n)] and loss and expense compensation [clause
27.1(2)(h)] to the extent that the delay or disruption was attributable to the grounds
for objection raised by the Contractor to the nomination.
Page 71
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Under SFBC 2005/2006, Smart Build can raise objection if Bravo’s tender sum is
not financially viable [clause 29.2(1)(c) or if Bravo is not financially capable [clause
29.2(1)(b)].
The mere fact that Bravo’s tender sum (HK$45M) is 10% lower than the
corresponding Prime Cost Sum (HK$50M) cannot be a sufficient justification that
the tender sum is not financially viable because the difference can be caused by
many reasons, e.g. an over estimate of the Prime Cost Sum, a change in scope or
design after the inclusion of the Prime Cost Sum in the Main Contract, or a very
competitive market, etc. A 10% deviation cannot be considered as abnormal.
Even if the tender sum is low, it is not an indication that Bravo is not or will not be
financially capable to support it, nor an indication that Bravo is currently financially
incapable.
Bravo’s tender prices and Bravo’s financial standing (should) have been
scrutinized during the tendering stage to be in reasonable order. Smart Build’s
objection should therefore not be accepted as valid, unless Smart Build can
provide better evidence to prove his case. To be prudent, Smart Build’s story
should be heard to ensure that there is no insider information to be missed.
Reduced profit due to the difference between the awarded Sub-Contract Sum and
the Prime Cost Sum shall not be considered as a valid ground for objection to
nomination under the Contract.
If this is put forward as a claim for loss of profit, it is not admissible for various
reasons:
There has been no guarantee that the awarded Sub-Contract Sum must be
very close to the Prime Cost Sum.
Prime Cost Sums serve as budgetary allowances and are usually set higher.
The final Sub-Contract Sum may become higher to narrow down the difference.
Some other Nominated Sub-Contract Sums may be higher than the Prime Cost
Sums to offset this particular difference.
Page 72
THE HONG KONG INSTITUTE OF SURVEYORS
QUANTITY SURVEYING DIVISION
ASSESSMENT OF PROFESSIONAL COMPETENCE
TH TH
FINAL ASSESSMENT – 18 & 19 SEPTEMBER 2018
PRACTICE PROBLEMS
NOTES TO ASSESSORS
Disparity between rate of liquidated damages under the Main Contract and that
qualified by NSC
Under the Standard Form of Sub-Contract, the liability for delay damages are
written in such a way that the Sub-Contractor is liable to reimburse the Contractor
any loss and/or expense incurred by the Contractor and any liquidated damages
imposed by the Employer upon the Contractor due to the failure of the Sub-
Contractor to complete on time [clauses 24.1 and 24.2 of the Standard Form of
Sub-Contract under SFBC 2005/2006].
If the rate of liquidated damages payable by Bravo is not sufficient to cover Smart
Build’s rate of delay damages caused by Bravo’s delay, Smart Build will suffer.
The terms of the Sub-Contract to be nominated must be consistent with those
made known to Smart Build during his tendering. If such disparity is not made
known to him during his tendering, Smart Build’s objection is valid. Unless the
nomination is withdrawn or Bravo agrees to withdraw the qualification now, the
disparity should be regarded as a variation [clause 29.5(2) of the Standard Form of
Sub-Contract under SFBC 2005/2006]. The Employer will have to bear the
shortfall in recovery caused by the disparity.
For Answer based on GCC1999, the same principle generally applies except that
GCC do not go into that great detail like SFBC 2005/2006 and that the Contractor
is NOT obliged to enter into a sub-contract with an NSC against whom the
Contractor may raise any objection which the Architect considers reasonable. The
relevant contract provisions under GCC1999 are Clause 66(1) for varied form of
sub-contract (or disparity between delay damages) and Clause 66(2) for
objections to nomination.
[13 marks]
Page 73