CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

INTERIM PAYMENT CERTIFICATE NO.09


DETAILED MEASUREMENT SHEET: (CIVIL WORKS)
BoQ Item at Serial # 46 Ceramic Tiles Dado

Length Width
S.No Description of Location Unit Nos. (Ft) (Ft) D/H Qty (Sft) Remarks

A Abolution (12x18)

1 Basement Toilet/Bath sft 3 x 21.00 x x 7.50 472.50

2 sft 1 x 22.50 x x 7.50 168.75

3 Ded Doors Inside sft (4) x 2.50 x x 7.00 (70.00)

only kitchen shelves wall


4 (8.37+4) L-shape sft 2 x 12.37 x x 5.00 123.70

5 do sft 2 x 8.00 x x 5.00 80.00

6 1 9.00 5.00 45.00

7 do sft 3 x 9.13 x x 5.00 136.88 (18.25/2

8 Ded Doors Inside sft (3) x 3.00 x x 5.00 (45.00)

abolution H1-J/10-16,34-40
9 (2x2) sft 4 x 63.00 x x 7.50 1,890.00

10 Ded Doors Inside 2x3 sft (6) x 3.50 x x 7.00 (147.00)

11 Mid walls (4x2) sft 8 x 17.75 x x 5.00 710.00

12 Sils sft 4 x 17.75 x x 0.75 53.25

519532750.xls Page 1 of 29
CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

INTERIM PAYMENT CERTIFICATE NO.09


DETAILED MEASUREMENT SHEET: (CIVIL WORKS)
BoQ Item at Serial # 46 Ceramic Tiles Dado

Length Width
S.No Description of Location Unit Nos. (Ft) (Ft) D/H Qty (Sft) Remarks

13 do (4x2) sft 8 x 17.75 x x 1.00 142.00

14 do (1x2) sft 2 x 17.75 x x 1.00 35.50

15 do (6x2) sft 12 x 30.75 x x 1.00 369.00

16 H1-J/19-31 (2x2) sft 4 x 49.12 x x 7.50 1,473.60

17 less enterance sft (2) x 10.00 x x 7.50 (150.00)

18 Mid walls (1x2) sft 2 x 25.00 x x 5.00 250.00

19 1x2 sft 2 x 30.75 x x 7.50 461.25

20 sft 4 x 6.00 x x 7.50 180.00

21 4x2 sft 8 x 1.25 x x 7.50 75.00

22 Toilet Block ladies area 2x1 sft 2 x 41.25 x x 7.50 618.75

23 16,35/J sft 2 x 40.00 x x 7.50 600.00

24 2 10.00 7.50 150.00

25 2 30.00 7.50 450.00

26 8,18/H1-H5 2 31.50 7.50 472.50

27 2 11.00 7.50 165.00

28 less D2 (2) 4.00 7.00 (56.00)

29 D4 (4) 3.00 7.00 (84.00)

519532750.xls Page 2 of 29
CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

INTERIM PAYMENT CERTIFICATE NO.09


DETAILED MEASUREMENT SHEET: (CIVIL WORKS)
BoQ Item at Serial # 46 Ceramic Tiles Dado

Length Width
S.No Description of Location Unit Nos. (Ft) (Ft) D/H Qty (Sft) Remarks

30 D5 42 2.50 7.00 735.00

31 Ladies toilet 1x2 2 30.50 5.00 305.00

32 Do internal sides 1x2 2 19.00 5.00 190.00 17+31/2

33 less D3 (1) 3.50 5.00 (17.50)

34 less D5 2x2 (4) 2.50 5.00 (50.00)

Total Qty 9,733.18

519532750.xls Page 3 of 29
CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 02)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Cft) Remarks
o (Ft) (Ft) (Ft)

UGWT

1 Excavation Cft 1 35.500 35.500 9.250 11657.31

QTY AGAINST ITEM No. 02 11657.31 cft


CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 03)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Cft) Remarks
o (Ft) (Ft) (Ft)

UGWT

1 Anit Termite (Bed) Cft 1 35.500 35.500 1260.25

2 Anti Termite (Walls) Cft 4 35.500 9.250 1313.50

QTY AGAINST ITEM No. 03 2573.75 cft


CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Cft) Remarks
o (Ft) (Ft) (Ft)

PCC 1:4:8

1 Main Stairs Right Side (73.25x15.25) cft 1 73.250 15.250 0.750 837.80

2 -DO- sides cft 2 9.250 15.250 0.250 70.53

3 Stairs at Grid C/4 cft 1 15.000 13.000 0.250 48.75

4 UGWT cft 1 34.500 34.500 0.250 297.56

QTY AGAINST ITEM No. 6 1254.64 cft


558.53125

95508.84375

2234.125
CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 7)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Cft) Remarks
o (Ft) (Ft) (Ft)

Brick Masonry Work in


Foundation
1 73 15.00 0.5
1 Main Stairs Right side Cft 547.50

1 71 14.00 0.5
2 do Cft 497.00

3 do Cft 1 69 13.00 0.5 448.50

4 do Cft 1 67 12.00 0.5 402.00

5 do Cft 1 65 11.00 0.5 357.50

6 do Cft 1 63 10.00 0.5 315.00

7 do Cft 1 61 9.00 0.5 274.50

8 do Cft 1 59 8.00 0.5 236.00

9 Both Sides Cft 2 9.5 15.00 0.5 142.50

10 do Cft 2 9.5 14.00 0.5 133.00

11 do Cft 2 9.5 13.00 0.5 123.50

12 do Cft 2 9.5 12.00 0.5 114.00

13 do Cft 2 9.5 11.00 0.5 104.50

14 do Cft 2 9.5 10.00 0.5 95.00

15 do Cft 2 9.5 9.00 0.5 85.50

16 do Cft 2 9.5 8.00 0.5 76.00

17 At Grid B-2 (Right side) Cft 1 14.5 10.00 0.5 72.50

18 do Cft 1 14.5 9.00 0.5 65.25

19 do Cft 1 14.5 8.00 0.5 58.00

20 do Cft 1 14.5 7.00 0.5 50.75

21 do Cft 1 14.5 6.00 0.5 43.50

22 do Cft 1 14.5 5.00 0.5 36.25

23 do Cft 1 14.5 4.00 0.5 29.00

24 do Cft 1 14.5 3.00 0.5 21.75

25 do Cft 1 14.5 2.00 0.5 14.50

26 do Cft 1 14.5 1.00 0.5 7.25

27 Abloution Area 24-27/G2 Cft 1 21.25 5.00 0.5 53.13

28 Cft 1 21.25 4.00 0.5 42.50

29 Cft 1 21.25 3.00 0.5 31.88


CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 7)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Cft) Remarks
o (Ft) (Ft) (Ft)
30 Cft 1 21.25 2.00 0.5 21.25

31 Cft 1 21.25 1.00 0.5 10.63

32 5,44/G2 Cft 2 10.25 5 0.5 51.25

33 Cft 2 10.25 4 0.5 41.00

34 Cft 2 10.25 3 0.5 30.75

35 Cft 2 10.25 2 0.5 20.50

36 Cft 2 10.25 1 0.5 10.25

37

38 11,15,36,39/G2 Cft 4 3.875 5 0.5 38.75

39 Cft 4 3.875 4 0.5 31.00

40 Cft 4 3.875 3 0.5 23.25

41 Cft 4 3.875 2 0.5 15.50

42 Cft 4 3.875 1 0.5 7.75

43

44 18,21,30,33/G2 Cft 4 5.875 5 0.5 58.75

45 Cft 4 5.875 4 0.5 47.00

46 Cft 4 5.875 3 0.5 35.25

47 Cft 4 5.875 2 0.5 23.50

48 Cft 4 5.875 1 0.5 11.75

4,956.38
364
CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 10)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Cft) Remarks
o (Ft) (Ft) (Ft)

Water proofing on RCC walls

1 AT A,G2/4-46 Sft 2 178.000 4.000 1424.00

2 At 46/A-G2 Sft 1 178.000 4.000 712.00

QTY AGAINST ITEM No. 10 2136.00 cft


22759.407
94500
921375
CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Cft) Remarks
o (Ft) (Ft) (Ft)

Minaret

2 104'6'' to 125'-6'' cft 1 21.000 22.000 0.750 346.50

3 Slab cft 1 6.000 6.000 0.500 18.00

QTY AGAINST ITEM No. 20 364.50 cft


CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 22)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Cft) Remarks
o (Ft) (Ft) (Ft)

UGWT

1 Bed cft 1 34.500 34.500 1.500 1785.38

2 Walls 2 Nos cft 2 34.500 1.250 7.000 603.75

3 Walls 2 Nos cft 2 32.000 1.250 7.000 560.00

4 Slab cft 1 34.500 35.500 0.500 612.38


Area
5 Bed Haunch 12''x12'' cft 4 32.000 0.500 64.00 1/2x12''x12''
Area
6 Bed Haunch 12''x12'' cft 4 0.500 7.000 14.00 1/2x12''x12''

QTY AGAINST ITEM No. 22 3639.50 cft


CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 25)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Sft) Remarks
o (Ft) (Ft) (Ft)

Insulation and water proofing


on roof
2 208 4.00
1 1-48/A,K (Projection) Sft 1664.00

2 250 4.00
2 1,48/A-K (Projection) Cft 2000.00
3,664.00
CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 26)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Sft) Remarks
o (Ft) (Ft) (Ft)

Flooring
1 G4-J5/2-47 Cft 1.00 181.50 62.83 0.33 3763.20

3,763.20
CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 33)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Sft) Remarks
o (Ft) (Ft) (Ft)

Water Stopper 9''


1 UGWT Rft 4.00 34.50 138.00

OHWT 2 Nos Rft 4.00 28.50 114.00

OHWT 2 Nos Rft 4.00 18.13 72.50

324.50
CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 34)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Sft) Remarks
o (Ft) (Ft) (Ft)

Marble Flooring 24x24


1 8-42/G1-G4 Sft 154.50 5.00 - - 772.50

LANDING E2-F2/8-12,38-42
2 BASEMENT+ GROUND FLOOR Sft 8.00 8.00 8.00 - 512.00
(4X2)

Landing A4-B2/8-12,38-42 (4x2)


3 Sft 8.00 8.00 8.00 - 512.00
BF+GF

4 Landing A4-B2/38-42 (1x2) Sft 2.00 8.00 8.00 - 128.00

5 Landing ladies stair (1x3) Sft 3.00 5.16 5.16 - 79.88

2,004.38
CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 35)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Sft) Remarks
o (Ft) (Ft) (Ft)

Marble Flooring 12x24


(Abolution)
1 4-45/G3-H1 Sft 1.00 178.00 16.00 - 2848.00

2 17-22,29-34/H1-H2 2.00 32.25 14.50 935.25

3 22-29/H1-H5 1.00 39.25 32.25 1265.81

4 15-36/H5-J4 1.00 1.00 100.00 11.92 1192.00

5 Gate 27-24/J4-K 1.00 21.92 10.75 235.64

6 15-17,34-36/J3-J5 2.00 7.33 3.25 47.65

7 Terrace Abolutionn area G-2-H1/5-45 1.00 176.00 14.42 2537.92

8 2-47/H-J5 1.00 186.00 49.50 9207.00

9 24-27/J5-K 1.00 5.50 21.92 120.56

Deductions 0.00

1 17-24,34-37/J2-J5 -2.00 32.25 4.00 -258.00

18,131.83
38048
CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 42)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Sft) Remarks
o (Ft) (Ft) (Ft)

Marble on Steps (Treads)


E2-F2/8-12,38-42 BASEMENT+
1 Sft 136.00 8.00 1.00 - 1088.00
GROUND FLOOR (4X31)

2 A4-B2/8-12,38-42 (4x31) BF+GF Sft 136.00 8.00 1.00 1088.00

3 A4-B2/38-42 (1x29) Sft 29.00 8.00 1.00 232.00

4 Ladies Stairs (1x25) Sft 25.00 5.50 1.00 137.50

5 Mehrab Stair (1x18) Sft 18.00 5.50 1.00 99.00

6 do (1x8) Sft 8.00 5.50 1.33 58.52 (Avg width)

7 Right side stair B1-B2/47 (1x10) Sft 10.00 14.50 1.00 145.00

8 2/G5-D5,E5-G (2x27) Sft 54.00 5.67 1.00 306.18

Abolution area stairs

1 5,45/G2 (2x5) Sft 10.00 12.25 1.00 122.50

2 11,15,36,39/G2 (4x5) Sft 20.00 3.88 1.00 77.50

3 18,21,31,33/G2 (4x5) Sft 20.00 5.87 1.00 117.40

4 24-27/G2 (1x5) Sft 5.00 21.25 1.00 106.25

5 Main Stairs (right side) Sft 1 73 1.00 73.00

6 do Sft 1 71 1.00 71.00

7 do Sft 1 69 1.00 69.00

8 do Sft 1 67 1.00 67.00

9 do Sft 1 65 1.00 65.00

10 do Sft 1 63 1.00 63.00

11 do Sft 1 61 1.00 61.00

12 do Sft 1 59 1.00 59.00


CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 42)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Sft) Remarks
o (Ft) (Ft) (Ft)

13 Both Sides (Right side main stair) Sft 2 21.5 1.00 43.00

14 do Sft 2 20.5 1.00 41.00

15 do Sft 2 19.5 1.00 39.00

16 do Sft 2 18.5 1.00 37.00

17 do Sft 2 17.5 1.00 35.00

18 do Sft 2 16.5 1.00 33.00

19 do Sft 2 15.5 1.00 31.00

20 do Sft 2 14.5 1.00 29.00

21 do Sft 2 13.5 1.00 27.00

22 Main Stair Podium Step Sft 1 59 7.00 413.00

23 Both Sides podium step Sft 2 9.5 7.00 133.00

4,966.85
38048
CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 43)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Sft) Remarks
o (Ft) (Ft) (Ft)

Marble on Steps (Risers)


E2-F2/8-12,38-42 BASEMENT+
1 Sft 136.00 8.00 0.50 - 544.00
GROUND FLOOR (4X31)

2 A4-B2/8-12,38-42 (4x31) BF+GF Sft 136.00 8.00 0.50 544.00

3 A4-B2/38-42 (1x29) Sft 29.00 8.00 0.50 116.00

4 Ladies Stairs (1x25) Sft 25.00 5.50 0.50 68.75

5 Mehrab Stair (1x18) Sft 18.00 5.50 0.50 49.50

6 do (1x8) Sft 8.00 5.50 0.50 22.00 (Avg width)

7 Right side stair B1-B2/47 (1x10) Sft 10.00 14.50 0.50 72.50

8 2/G5-D5,E5-G (2x27) Sft 54.00 5.67 0.50 153.09

Abolution area stairs

1 5,45/G2 (2x5) Sft 10.00 12.25 0.50 61.25

2 11,15,36,39/G2 (4x5) Sft 20.00 3.88 0.50 38.75

3 18,21,31,33/G2 (4x5) Sft 20.00 5.87 0.50 58.70

4 24-27/G2 (1x5) Sft 5.00 21.25 0.50 53.13

5 Main Stairs (right side) Sft 1 73 0.50 36.50

6 do Sft 1 71 0.50 35.50

7 do Sft 1 69 0.50 34.50

8 do Sft 1 67 0.50 33.50

9 do Sft 1 65 0.50 32.50

10 do Sft 1 63 0.50 31.50

11 do Sft 1 61 0.50 30.50

12 do Sft 1 59 0.50 29.50


CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 43)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Sft) Remarks
o (Ft) (Ft) (Ft)

13 Both Sides (Right side main stair) Sft 2 21.5 0.50 21.50

14 do Sft 2 20.5 0.50 20.50

15 do Sft 2 19.5 0.50 19.50

16 do Sft 2 18.5 0.50 18.50

17 do Sft 2 17.5 0.50 17.50

18 do Sft 2 16.5 0.50 16.50

19 do Sft 2 15.5 0.50 15.50

20 do Sft 2 14.5 0.50 14.50

21 do Sft 2 13.5 0.50 13.50

2,203.17
38048
CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

Detailed Measurement Sheet (Item No. 62)


S.N Length Width Heigth
Description of Item Unit Nos. Qty (Sft) Remarks
o (Ft) (Ft) (Ft)

Aluminium Windows/
Ventilators
1 Ground Floor

2 W-1 sft 49.00 9.00 2.50 1102.50

3 W-1 (Head) sft 49.00 0.75 1.00 36.75

4 1st floor

5 W-2 sft 50.00 6.75 2.50 843.75

6 W-2 (Head) sft 50.00 0.75 1.00 37.50

2,020.50
CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

INTERIM PAYMENT CERTIFICATE NO.07


DETAILED MEASUREMENT SHEET: (CIVIL WORKS)
BoQ Item at Serial # 71 RCC Jali

S.No Description of Location Unit Nos. Length Width Depth Qty (Sft) Remarks
(Ft) (Ft) (Ft)

1 left side wall sft 10 14.000 10.670 1,493.80

2 Arch 1/E1-E2 sft 1 18.670 10.670 199.21

3 4/C3-D1,F3-G2 sft 2 18.500 10.670 394.79

4 24-27/K ARCH sft 1 18.500 10.670 197.40

5 REAR SIDE A sft 6 14.000 10.670 896.28

6 17-19,31-34/A2 sft 2 9.500 10.670 202.73

7 19-24,27-31/A2 sft 2 18.500 10.670 394.79

8 1/D5-E2,E2-E5 sft 2 9.580 10.670 204.44

9 1-4/D5,E5 sft 2 8.000 10.670 170.72

10 G2/10,40 sft 2 12.250 10.670 261.42

11 G2/12,17,23,28,34,38 sft 6 9.170 10.670 587.06

12 G2/19,31 sft 2 13.750 10.670 293.43

13 G2/27-27 sft 1 18.500 10.670 197.40

14 F4-G2/8,42 sft 2 13.750 10.670 293.43

15 F4/7-15,36-42 sft 4 9.500 10.670 405.46

16 E2-F4/15,36 sft 4 9.500 10.670 405.46

17 E2/15-19,31-36 sft 2 18.500 10.670 394.79

18 E2/24-27 sft 1 18.500 10.670 197.40

GROUND FLOOR

AROUND THE BUILDING COLUMN TO


20 COLUMN sft 120 4.500 3.500 1,890.00

Total 9,079.98

519532750.xls Page 28 of 29
CONSTRUCTION / UP-GRADATION OF MOSQUE AT PAK SECRETARIATE, ISLAMABAD

INTERIM PAYMENT CERTIFICATE NO.07


DETAILED MEASUREMENT SHEET: (CIVIL WORKS)
BoQ Item at Serial # 71 RCC Jali

S.No Description of Location Unit Nos. Length Width Depth Qty (Sft) Remarks
(Ft) (Ft) (Ft)

1 left side wall sft 10 14.000 10.670 1,493.80

2 Arch 1/E1-E2 sft 1 18.670 10.670 199.21

3 4/C3-D1,F3-G2 sft 2 18.500 10.670 394.79

4 24-27/K ARCH sft 1 18.500 10.670 197.40

5 REAR SIDE A sft 6 14.000 10.670 896.28

6 17-19,31-34/A2 sft 2 9.500 10.670 202.73

7 19-24,27-31/A2 sft 2 18.500 10.670 394.79

8 1/D5-E2,E2-E5 sft 2 9.580 10.670 204.44

9 1-4/D5,E5 sft 2 8.000 10.670 170.72

10 G2/10,40 sft 2 12.250 10.670 261.42

11 G2/12,17,23,28,34,38 sft 6 9.170 10.670 587.06

12 G2/19,31 sft 2 13.750 10.670 293.43

13 G2/27-27 sft 1 18.500 10.670 197.40

14 F4-G2/8,42 sft 2 13.750 10.670 293.43

15 F4/7-15,36-42 sft 4 9.500 10.670 405.46

16 E2-F4/15,36 sft 4 9.500 10.670 405.46

17 E2/15-19,31-36 sft 2 18.500 10.670 394.79

18 E2/24-27 sft 1 18.500 10.670 197.40

GROUND FLOOR

AROUND THE BUILDING COLUMN TO


20 COLUMN sft 120 4.500 3.500 1,890.00

Total 9,079.98