Gambate Borehole Drilling

42 McCleary

Harare

info@gambateconstruction.com

Cell: +263771 562 039

+263774 491 578

+263773 530 454

SITE SURVEY REPORT


SITE NAME: Mt Hampden
Lat: -17.742 -Long: 30.939
SURVEY DATE: 28/03/2021
REPORT DATE: 29/03/2021
SURVEY TEAM: Brighton Magwizi and Arlyn Chiketa

BACKGROUND
Siting survey on an industrial property, Borehole to be used for industrial use so the survey was lined to
a point where there is the greatest possible yield.

FIELD WORK
Geophysical investigation, employing the electrical conductivity method, making use of magnetometric
mapping to locate flaws and soft zones in the earth’s crust were carried out. The results are as given
below:

DISCLAIMER
Our survey machine is 90% accurate, it shows ground formation by showing points with high
conductivity. It does not show the quantity of water that can be yielded after drilling. We therefore
we do not guarantee and or take liability of availability of water. This report is valid for 60 days due
to the changes in seasons
VIEW OF THE AREA
RESULTS OF SURVEY

Site C

RECOMMENDATIONS/COMMENTS

 We recommend drilling at point 12 on map line

 According to the waterline, we have the following water breaks: 20m, 45m, 54m, 65m.
Therefore, we recommend a minimum of 60m and a maximum of 100m.

 Class 9 casing may be required to avoid siltation and borehole from collapsing.
Site D

RECOMMENDATIONS/COMMENTS

 We recommend drilling at point 14 on map line

 According to the waterline, we have the following water breaks: 41m, 66m, 70m, 80m.
Therefore, we recommend a minimum of 70m and a maximum of 120m

 Class 9 casing may be required to avoid siltation and borehole from collapsing.
Site E

RECOMMENDATIONS/COMMENTS

 We recommend drilling at point 2 on map line

 According to the waterline, we have the following water breaks: 61m, 73m, 82m and 85m.
Therefore, we recommend a minimum of 65m and a maximum of 110m

 Class 9 casing may be required to avoid siltation and borehole from collapsing.
Site F

RECOMMENDATIONS/COMMENTS

 We recommend drilling at point 12 on map line

 According to the waterline, we have the following water breaks: 63m, 72m, 81m and 85m.
Therefore we recommend a minimum of 70m and a maximum of 118m.

 Class 9 casing may be required to avoid siltation and borehole from collapsing.