01 - Method Statement of Mobilization
01 - Method Statement of Mobilization
AT BP LNG TANGGUH
SF Syukri Fitrialdi
i
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
TABLE OF CONTENT
1 DOCUMENT CONTROL & REVISION STATUS .............................................................................. i
TABLE OF CONTENT...................................................................................................................... ii
LIST OF FIGURES.......................................................................................................................... iii
LIST OF TABLE ............................................................................................................................. iii
1 INTRODUCTION ....................................................................................................................... 1
2 MOBILIZATION OF PERSONNELS .............................................................................................. 1
2.1 On-Site Personnels ................................................................................................................... 1
2.2 Personnel Mobilization Documents ......................................................................................... 1
2.3 Mobilization point for personnels ............................................................................................ 2
3 MOBILIZATION OF EQUIPMENTS ............................................................................................. 2
3.1 List of Equipments .................................................................................................................... 2
3.2 Equipment Mobilization Documents ....................................................................................... 2
3.3 Cargo Carrying Unit (CCU) ........................................................................................................ 2
3.3.1 ISO Container 20Ft .......................................................................................................... 3
3.3.2 Open Rack/Pipe Rack ...................................................................................................... 3
3.3.3 Flat Rack .......................................................................................................................... 5
3.3.4 Wooden Pallet................................................................................................................. 9
3.3.5 Dando Mintec 12.8 Drilling Rig ....................................................................................... 9
3.4 Cargo Manifest ....................................................................................................................... 10
3.5 Cargo Transport to Mobilization Point ................................................................................... 10
4 MOBILIZATION POINT FOR EQUIPMENTS ............................................................................... 12
5 LOADING & UNLOADING ....................................................................................................... 12
6 MOBILIZATION TO DRILL SITE ................................................................................................ 12
7 MOBILIZATION SCHEDULLE .................................................................................................... 13
Appendix A – List Of Equipment ...................................................................................................A
Appendix B – Time Schedulle........................................................................................................ B
ii
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
LIST OF FIGURES
Figure 1. ISO Container 20Ft (left) & ISO Container Lifting Frame (right) .............................................. 3
Figure 2. Open Rack/Pipe Rack Design ................................................................................................... 4
Figure 3. Material arrangement inside open rack and pipe rack ............................................................ 4
Figure 4. Open rack/pipe rack Design ..................................................................................................... 5
Figure 5. Open Rack for Water Tank ....................................................................................................... 6
Figure 6. Open Rack for Generator Set ................................................................................................... 7
Figure 7. Flat Rack for Mud Pump........................................................................................................... 8
Figure 8. Wooden Pallet .......................................................................................................................... 9
Figure 9. Drilling Rig .............................................................................................................................. 10
LIST OF TABLE
iii
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
1 INTRODUCTION
This document used as a guidance for THI personnel and as a control for BP during mobilization phase
to ensure that all the mobilization activities are executed properly and safely to achieve the optimum
performance.
2 MOBILIZATION OF PERSONNELS
No Position Qty
1 Site Manager 1 Person
2 Deputy Site Manager 2 Persons
3 Mud Engineer 1 Person
3 HSE Coordinator 2 Person
4 Logistic 2 Persons
5 QC/QA 2 Persons
6 Project Admin 1 Person
7 Drilling Supervisor 1 Person
8 HSE Officer 3 Persons
9 Wellsite Engineer 3 Persons
10 Driller 3 Persons
11 Assistant Driller 12 Persons
12 Mechanic and Electric 3 Persons
13 Helper (Local Workers) 4 Persons
1
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
3 MOBILIZATION OF EQUIPMENTS
To execute this project THI will bring and utilize some equipment including but not limited to: Drilling
Rig and Accessories, Mud Pump System, Well Construction Materials, Well Develompment Tools,
Pumping test Equipment, and material supply for Well completion and other supporting tools.
Equipment for Lifting and the lifting job during loading and loading equipment from and to Vessel
Cargo or Landing Craft Tank (LCT ), mobilization to drilling site, and seting up drilling equipment will
be conducted by BP Team.
List of equipments for groundwater well drilling project provided by THI are given in Appendix A
Inspection will be conducted several times by Sucofindo regarding to the availability of materials.
Some materials must wait to be inspected due to late of delivery time escpecially for imported
materials. Some materials also takes time for fabricated in-house by THI, such as open rack, flat rack,
etc.
2
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
ISO Frame container will be provided and used by BP to handling and lifting this kind of Cargo Carrying
Unit. Totally 4 (four0 containers is planned to be utilized.
Figure 1. ISO Container 20Ft (left) & ISO Container Lifting Frame (right)
There are 2 (two) type of racks fabricated by THI. Both of racks basically have typical design size (figure
3) but different in height. There is open rack having a size of 6058 mm x 2438mm x 1200m, then the
other one having a size of 6058 mm x 2438mm x 800m.
The example arrangement inside the open rack & pipe rack shown in figure 4. These open racks will
be lifted using spreader bar and two leg wire rope provided by THI.
3
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
4
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
Detail design especially related to the lifting method is still in discussion with BP and waiting for the
approval.
5
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
Detail design especially related to the lifting method still in discussion with BP and waiting for the
approval.
6
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
The size of fuel tank is 2000 liter and functioned as a main tank that supply the original tank inside the
generator. This arrangement will allow the generator running continuously during pumping test (10
days) without re-fueling.
The flat rack’s size is 6050mm x 2430 x 1900mm. Detail design especially related to the lifting method
is still in discussion with BP and waiting for the approval.
7
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
All of this flat rack is equipped with 4(four) dedicated pad eyes at bottom side to accommodate safe
and proper handling. For handling purposed all of this flat rack will use a spreader bar with single leg
wire rope or two leg wire rope.
Detail design especially related to the lifting method is still in discussion with BP and waiting for the
approval.
8
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
The pallet is equipped with 2 (two) way entry at the bottom for handling by forklift or Manitou. The
goods being loaded on the pallet will be wrapped and lashed to make sure it is fixed on the base of
pallet.
Totally almost 170 units of wooden pallet are prepared by THI to carry cement, filter pack (silica sand)
and mud fluid.
The drilling rig’s dimension is 10.92m x 3.30m x 4.45m and having the gross weight of 30 tons. The
detail of dimension of rig are shown in the figure 9.
9
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
THI will provide the manifest representing information related to the equipments (e.g. contract
number, weight, dimension, final destination, contact person in Tangguh LNG site, description,
quanties and identification number).
EMA (Equipment Moving Approval) issued and approved by BP and others inspection documents will
be attach with the manifest during hand over to BP at each mobilization point.
Safe and proper land transportation to reach the mobilization points will be provide by THI. During
the trip to mobilization point equipment also will be secure with weather protection and also tools for
equipment handling prior to handover to BP.
10
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
Several options of land transportations will be used by THI to Mobilization Point (Port) are displayed
in table 2. As below:
• Lenght : 1200 cm
• Width : 220 cm
• Height : 230 cm
• Capacity : 400 Ton
• Designation : ISO Container 20ft
• Lenght : 630 cm
• Width : 220 cm
• Capacity : 15 Ton
• Designation : Wooden Pallet
Note : The land transportations will be equiped also with driver checklist.
11
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
Since there are 2 (two) different mobiliziation points in Ciwandan Port, West Java and Lamongan Shore
Base Port, East Java, the routes will describe separately in the table 3 below:
Loading and unloading of all THI Cargo will be conducted and controlled by BP. The lifting method and
plan will be intensively communicated between THI and BP during the preparation of loading and
unloading.
All THI cargo will be transported from mobilization port using dedicated charted vessel or Landing
Craft Tank (LCT) provided by BP. After reach the LNG Tangguh Site Port, all cargo will be loaded on
dedicated land transport to to the drill site.
12
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
During the arrival of all cargo, THI personnel must keep the comunication with BP’s port representative
to ensure all cargo are completely mobilized to the drill site.
7 MOBILIZATION SCHEDULLE
The mobilization will be conducted partially into some batches that will be started in the mid of
September as presented in the APPENDIX B. It should be noted that the actual mobilization schedule
will be depend on the BP’s shipping schedule.
The first batch will be prioritized to the equipment, material, and tools which not require EMA
(Equipment Mobilization Approval) such as: chemical, parts, non-precision power hand tools (tool kit),
civil material, safety and PPE, electrical accessories (non-plan). Based on the requirement of EMA The
first batch will be:
• Annulus Filled Material: Cement, Silica Sand, and Bentonite Pellet. The material will be packed
on the wooden pallet, wrapped and lashed. It should be noted that not all annulus materials
will be mobilized at once.
• Parts, tool kits, safety and PPE, Electrical accessories, Biodegradable Oil etc. These stuff will
be put into the ISO containers have been inspected by BP. At least 1 (one) – 2 (two) containers
will be mobilized.
The second batch will be executed after trial or drilling simulation at THI workshop, Bandung
scheduled on third week of September 2018 and EMA for some equipment and materials have been
received from BP.
The second batch equipment and material will be prioritized on the minimum requirement to execute
the first and production holes, such as:
• Drilling Rig Dando Mintec 12.8. This is the crawler mounted rig, so that this rig can move by
themselves.
• Mud Pump system. The equipment is attached on the flat rack as figured out in the figure 7.
• Fuel Tank. The equipment is attached on the flat rack as figured out in the figure 4.
• Tower Lamp.
• Water Tank. The equipment is attached on the flat rack as figured out in the figure 5.
• Generator Set. The equipment is attached on the flat rack as figured out in the figure 6
13
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
• Surface Casing and Well Lining Materials for 1 production wells. These materials will be carried
by open rack as figured out in the figure 3.
• Submersible Pumps, Geophysical Well Logging, and other materials can be carried out by ISO
container.
The third batch will be the remaining materials to complete the whole drilling works:
14
METHOD STATEMENT
MOBILIZATION PLAN
Doc No : 01-MDP-GWTLNG_Rev.00
A
LIST OF EQUIPMENTS
GROUND WATER WELL DRILLING AT BP LNG TANGGUH
CONTRACT NO: 4420002230
B
Water Well Work Tangguh LNG Project
ID Task Name Duration Jul '18 Aug '18 Sep '18 Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 Ma
W1 W3 W5 W7 W9 W11 W13 W15 W17 W19 W21 W23 W25 W27 W29 W31 W33 W35 W37 W39 W41 W43
1 TANGGUH LNG WATER WELL PROJECT 298.89 days
2 CONTRACT 17 days
3 Contract Date 1 day
4 KOM 1 day
5 Contract Assigned by THI & BP 1 day
6 PREPARATION 45.89 days
7 Technical Documents 34 days
14 Personel and Equipment Preparation 45.89 days
15 Personnel Preparation 38 days
16 Entering Tangguh Site 31.89 days
19 Competency Training 31 days
25 Well Material procurement and machining 45 days
40 Equipment Preparation 45.89 days
49 MOBILIZATION 230.89 days
50 Equipment 27 days
51 1st Batch from Bandung to Ciwandan & Lamongan 2 days
52 1st Batch from Ciwandan/Lamongan to Tangguh Site 15 days
53 2nd Batch from Bandung to Ciwanda & Lamongan 2 days
54 2nd Batch from Ciwanda/Lamongan to Tangguh Site 15 days
55 Personel 216.89 days
56 1st batch (advanced team), +/‐ 5 person mobilization up to Halim 1 day
57 1st batch (advanced team), +/‐ 5 person mobilization up to Tangguh Site 2 days
58 2nd batch, +/‐ 25 person mobiliization up to Halim 13 days
59 2nd batch, +/‐ 25 person mobiliization up to Halim up to Tangguh Site 2 days
60 SITE PREPARATION 215.89 days
65 PRODUCTION WELL 1 (310 m) 34 days
91 PPRODUCTION WELL 2 (310 m) 34 days