ABSAL PAUL CONTRACTING COMPANY

Method Statement SMS - SF 4.4.6.6.1


MS No SAMAFFE-001 Rev 0 Date 14-Jul-19

Method Satement for


Double Glazed Partitions

Prepared By Date Revision Status Reviewed by Date Review Status


Ali Sahibzada 7/20/2020

Review Comments
Comment By Date Comment
Section 1 Description of the work / activity
Install double glazed partitions and doors in accordance with approved drawings on Level 2.

Section 2 Sequence of the task


1 Identify location glass size and type required for each area - (Zone-wise ideally)
2 Call-off two days of supply in advance
3 Offload glass A-frames from the duty cab via a forklift; banksman to faciliate maneuvre
4 Arrange A-frames in the designated area in the delivery way
5 Using a jack palet to transfer A-frames (one by one) into the hoist to shift to workfloor

6 During lateral transport within the workfloor use jack palets; ensure palet is moving under supervision at both ends

7 At the workfloor, aptly arrange A-frames in a designated area ensuring no damage to surrounding items or passerbys

8 Inspect glass crates for external damage


9 Open relevant crates and retrieve glass panels required
10 Inspect each glass for damage
11 Place glass panel on tresles for cleaning and application of edge tape
12 Ensure that framework is complete and level
13 Glaziers to wear vinyl gloves throughout installation
14 Glaziers to use glass catchers to hold glass; as safety measure against finger trapping
Position glass in designated location on floor track inner groove, align with vertical track and
15 insert retaining clips

16 Position second glass panel in second profile outer groove and proceed in the same way as the
first panel already in place
17 Proceed with installing adjacent panels or corner panels with the same procedure and bonding to
vertical edges using the pre-installed tape
18 Unterminated double glazing to be sealed from dust and dirt using plastic cling wrap

19 Complete each partition run working from corners or three way junctions and leave allocated
space for door opening.
20 Installation of door frames to encapsulate glass edges

21
Install glass doors using top and bottom pivot fixings per manufacturer instructions
After installation glass to be cleaned from either side; door frames to be covered with appropriate protection
21

22
23
Section 3 Associated forms, authorizations & drawings
Document Ref Entity Description Date granted
Client
Occupier
Designer
Resident Engr
Local Authority
Police
Sub-contractor

Section 4 Temporary works


Is a temporary works certificate / authorization required? Yes No
If Yes please state:
Name of temporary works supervisor: Contact Number
Drawing references:

Description of temporary works

Section 5 Planning and co-ordination


Describe the interfaces between other contractors or members of the public that must be suitably controlled, these controls must be
included in the risk assessment
1. Construction area must be hoarded with a single controlled access point
2. Signage must be placed on the hoarding and at the entrance prohibiting unauthorised entry
Section 6 Resources
Personnel Inspection / Permits Y/N Operator
technician Trained Y/N
Project manager Induction Crane operator
Project engineer Ali Sahibzada Excavation Rigger NA
Foreman Intazar Ahmad Buried services Scaff inspector
Scaffolding Forklift operator Y
Elevated positions
Confined space NA
Live electricity
Hot works
Cranes
Other
Other
Plant and equipment required Materials to be used MSDS Y/N
Section 7 Associated Risks
Drowning Collapse of structure Collapse of excavation Fragile roof trips fall from height Slips falling objects Head injury Electricity Noise

Y Y Y Y Y Y Y Y Y Y Y

harmful
Low temp Fire / hot work Explosive atmosphere Biological hazard Spills Laser radioactivity trapping Cuts Use of crane
substances

Y Y Y Y Y Y Y Y Y Y Y

Confined space Foot injuries Unauthorised entry Moving vehicles Flammable liquids ladders Use of machinery Toxic fumes Inhalation General hazard Low oxygen

Y Y Y Y Y Y Y Y Y Y Y

Associated risk assessments


Risk assessment description Number Date Prepared by Approved by

Section 8 Personal protective equipment


Hi vis vest Overall Safety glasses Welding mask Face shield Ear protection Dust mask Respirator Gas mask Gloves Life jacket

Y Y Y N Y N Y Y Y Y nana

Y Y Y
Safety harness Safety shoes Hard hat

Permits to work required


Type of permit Y/N Type of permit Y/N
Excavation permit Permit to work in electrical rooms
Confined space permit Pressure test permit
Hot work permit Permit to work of roofs
Live electrical circuits Other specify
Access permit Other specify

Section 9 Fire & emergency co-ordination


Fire equipment required for this task

Water DCP CO2 Foam


Yes No Yes No Yes No Yes No

Emergency contacts
Position Contact number Emergency Contact number
Project manager Ambulance
Site Manager Fire
Engineer 053 940 3656 Police
Safety Nearest hospital
Client Security
Special fire and emergency arrangements

Section 11 Associated docments / attchements


Document name Attachment No. Document name Atachment No.
Traffic management plan
Emergency plan
Training certificates
Project safety plan
RAMS

Record of communication of method statement


Name Signature Name Signature