Construction Management

Submitted to:
Sir Touseef
Submitted by:
Areej Fatima
Registration #:
2017-TE-10

Department of Transportation Engineering &


Management
University of Engineering & Technology Lahore

1
Faisalabad to Multan Motorway (M-4)

1. Project Description

Project Name
Faisalabad to Multan Motorway (M-4)
Cost of Project
80 billion rupees
Duration

2003-2019
Length of road
309km
North end
Pindi Bhattian, M2
South end
Multan, M5
Status
Operational
Contractors
 China railway first group co..LTD
 Xianjiang beixin road and bridge group co. LTD
 Pakistan national highway authority (NHA)
Implementers
 NHA
Funders
 Pakistan
 China
 Asian Development Bank (ADB)

2
The M4 Motorway (Faisalabad to Multan section) was inaugurated in parts, first being
Faisalabad to Gojra, second was Multan to Khanewal (Shamkot), third being Gojra to Shorkot,
fourth was Shorkot to Abdul Hakeem ( Shorkot to Abdul Hakeem became operational almost
together with Lahore Abdul Hakeem (Darkhana) Motorway) & finally Abdul Hakim (Deen Pur)
to Khanewal (Shamkot). The last section of M4 Motorway (Abdul Hakeem to Khanewal) was
inaugurated by Foreign Minister of Pakistan Mr. Makhdoom Shah Mahmood Qureshi. It is a 4 to
6 lane motorway. The length of 6 lane is 5 km from Shorkot to WaryamWala on Railway Line.
The M4 begins near the M2 Pindi Bhattian Interchange and continues on a southwest course
connecting the cities of Faisalabad, Gojra, Toba Tek Singh, Shorkot, Abdul Hakeem, Khanewal
and Multan. And ends at Sher Shah Interachange giving exit to Multan Cantt over Shujabaad
Road & itself continues as M5 Multan-Sukkur Motorway. It is connected to M3 Motorway
(Lahore to Abdul Hakeem Motorway) near a village named Darkhana a few kilometers northeast
of Abdul Hakeem Interchange. There is a separate Toll Plaza for Entrance/ Exit to/ from M3
Motorway.

3
2. Microsoft project description:
Microsoft Project is a project management software product, developed and sold by Microsoft. It
is designed to assist a project manager in developing a schedule, assigning resources to tasks,
tracking progress, managing the budget, and analyzing workloads.
Microsoft Project was the company's third Microsoft Windows-based application. Within a few
years after its launch, it became the dominant PC-based project management software.[3]
It is part of the Microsoft Office family but has never been included in any of the Office suites. It
is available currently in two editions, Standard and Professional. Microsoft Project's proprietary
file format is .mpp.
Microsoft Project and Microsoft Project Server are the cornerstones of the Microsoft Office
enterprise project management (EPM) product.

Features
Project creates budgets based on assignment work and resource rates. As resources are assigned
to tasks and assignment work estimated, the program calculates the cost, equal to the work times
the rate, which rolls up to the task level and then to any summary tasks and finally to the project
level. Resource definitions (people, equipment and materials) can be shared between projects
using a shared resource pool. Each resource can have its own calendar, which defines what days
and shifts a resource is available. Resource rates are used to calculate resource assignment costs
which are rolled up and summarized at the resource level. Each resource can be assigned to
multiple tasks in multiple plans and each task can be assigned multiple resources, and the
application schedules task work based on the resource availability as defined in the resource
calendars. All resources can be defined in label without limit. Therefore, it cannot determine how
many finished products can be produced with a given amount of raw materials. This makes
Microsoft Project unsuitable for solving problems of available materials constrained production.
Additional software is necessary to manage a complex facility that produces physical goods.
The application creates critical path schedules, and critical chain and event chain
methodology third-party add-ons also are available. Schedules can be resource leveled, and
chains are visualized in a Gantt chart. Additionally, Microsoft Project can recognize different
classes of users. These different classes of users can have differing access levels to projects,
views, and other data. Custom objects such as calendars, views, tables, filters, and fields are
stored in an enterprise global which is shared by all users.

4
Microsoft Project 2007 showing a simple Gantt chart

Interoperability
Microsoft Project's capabilities were extended with the introduction of Microsoft Office Project
Server and Microsoft Project Web Access. Project Server stores Project data in a central SQL-
based database, allowing multiple, independent projects to access a shared resource pool. Web
Access allows authorized users to access a Project Server database across the Internet, and
includes timesheets, graphical analysis of resource workloads, and administrative tools.
User controlled scheduling
User-controlled scheduling offers flexible choices for developing and managing projects.
Timeline
The timeline view allows the user to build a basic Visio-style graphical overview of the project
schedule. The view can be copied and pasted into PowerPoint, Word, or any other application.
Inactive tasks
Helps experiment with project plans and perform what-if analysis
The Team Planner view
The new Team Planner shows resources and work over time, and helps spot problems and
resolve issues.
Planning and Scheduling
Planning and scheduling arguably constitute the most important stage of project management.
They form the backbone of the entire project and can either make or break the whole thing.

5
What does this stage entail? For starters, it specifies how and when each task should be
completed. Then, these tasks are assigned to various team members and allocated any necessary
resources. This makes the entire process smooth and transparent, with everyone aware of their
duties and responsibilities. This is precisely what Microsoft Project is good at. It utilizes the
following to ensure accurate project management:
• Prioritization: Helps you prioritize your project’s tasks, eliminating surprises and allowing
your team to focus on addressing the most important matters first.
• Task management: Allows project managers to define the activities involved in the project
and decide how they should be assigned to different members.

Reporting
Reporting is one of the most important means of tracking a project’s progress, as it allows you to
monitor how much work has been completed and how much remains. Fortunately, Microsoft
Project excels at this task, allowing you to generate great reports with little effort. . Best of all,
you can even customize the data and the structure according to your requirements. The features
include burn down reports; an overview of the entire project on one page; the conditions of
available resources and their utilization; a cost overview; a list of pending tasks; and a list of
targets achieved and any upcoming goals.

6
Resource Management
Microsoft Project offers project managers a great deal of flexibility when it comes to managing
project resources and availability. The resources for a project could be monetary (such as the
allocated budget), the people involved (team members), meeting and work rooms, raw materials,
and much more. Obviously, a project is going to come with certain limitations on the number of
resources that can be used. Microsoft Project’s resource management tools help you track and
monitor all available resources and the potential ways in which they can be used for your
project(s). The project management tool also lets you assign costs to individual resources,
allowing you to later analyze whether certain valuable resources are being overused, underused,
and so on.
Multiple Projects
Microsoft Project also allows project managers to work on multiple projects on the same
platform, making it easier to deal with different projects in the same company or team. This is
defined by the Master Project Plan. Basically, when you’re working with many different project
plans, you can combine all of them to form one master plan to use as you move forward. This
proves extremely beneficial to project managers, especially if they are juggling multiple projects
at once.
Different Views
Microsoft Project is quite a unique project management tool in that it offers a number of different
views. For instance, you can make use of a Gantt Chart, a resource usage chart, a calendar, and
much more. Essentially, it allows a manager to view the project from different perspectives and
representations, all from one platform. But the best aspect about this feature is that all of these

7
views can be customized together according to the project requirements and combined to form
one big project plan.

3. Project overview
% Complete

100%

% COMPLETE

Status for all top-level tasks. To see the status for subtasks, click on the chart and update the
outline level in the Field List.

8
project status
120%

100%

80%

60%

40%

20%

0%

actual work

166440hrs

9
remaining work

0hrs

work status
10,000 hrs
9,000 hrs
8,000 hrs
7,000 hrs
Work (hrs)

6,000 hrs
5,000 hrs
4,000 hrs
3,000 hrs
2,000 hrs
1,000 hrs
0 hrs

Actual Work Baseline Work

10
4. Cost overview
Total cost: 80 billion rupees

Chart Title

120% 12000000

100% 10000000

80% 8000000
CUMULATIVE COST
% COMPLETE

60% 6000000

40% 4000000

20% 2000000

0% 0
4/4/21

9/19/21
3/7/21

5/2/21
5/30/21
6/27/21
7/25/21
8/22/21

10/17/21
11/14/21
12/12/21
1/9/22
2/6/22
3/6/22
4/3/22
5/1/22
5/29/22

Cumulative Percent Complete Cumulative Cost

11
cost status
12000000

10000000

8000000

6000000

4000000

2000000

0
ROAD WORKS

Remaining Cost Actual Cost Baseline Cost

Name Actual Cost Remaining Baseline Cost Cost Variance


Cost Cost
Laying Out $297.60 $0.00 $0.00 $297.60 $297.60
and Surveying
Work
Obtain $0.00 $0.00 $0.00 $0.00 $0.00
Building NOCs
from All
Concerned
Authorities
Trial Trenches $1,987.20 $0.00 $0.00 $1,987.20 $1,987.20
and Location

12
Check Of
Current
Facilities
Established $262.80 $0.00 $0.00 $262.80 $262.80
Utilities Must
Be Moved
The $350.40 $0.00 $0.00 $350.40 $350.40
Installation of
New Utilities
Send Shop $0.00 $0.00 $0.00 $0.00 $0.00
Drawings for
Road Work
Clearance
Approve the $0.00 $0.00 $0.00 $0.00 $0.00
subcontractors
Subcontractors $0.00 $0.00 $0.00 $0.00 $0.00
Must Be
Approved
Approve $0.00 $0.00 $0.00 $0.00 $0.00
Materials
Submittals
Approve $0.00 $0.00 $0.00 $0.00 $0.00
Material
Submittals
Material
Procurement
Clear and $350.40 $0.00 $0.00 $350.40 $350.40
Grubbing
Earth Shifting $0.00 $0.00 $0.00 $0.00 $0.00
Drainage $5,440.80 $0.00 $0.00 $5,440.80 $5,440.80
Fine-tuning $492.22 $0.00 $0.00 $492.22 $492.22
Noise $0.42 $0.00 $0.00 $0.42 $0.42
Reduction
Barriers
Installation of $0.42 $0.00 $0.00 $0.42 $0.42
Guardrails
Base granular $885.90 $0.00 $0.00 $885.90 $885.90
Conduits for $0.00 $0.00 $0.00 $0.00 $0.00
Electricity
Installation of $0.00 $0.00 $0.00 $0.00 $0.00
Drains
Final Granular $1,245.82 $0.00 $0.00 $1,245.82 $1,245.82
Base
Walls of $0.22 $0.00 $0.00 $0.22 $0.22
Protection
Paving on Base $8,251.42 $0.00 $0.00 $8,251.42 $8,251.42

13
Symbolism $1,051.62 $0.00 $0.00 $1,051.62 $1,051.62
(Foundations)
Installation of $526.02 $0.00 $0.00 $526.02 $526.02
Signage
Laying bricks $262,752.00 $0.00 $0.00 $262,752.00 $262,752.00
(Wearing
Course)
Granular on $263.10 $0.00 $0.00 $263.10 $263.10
the Shoulders
Marking of $0.00 $0.00 $0.00 $0.00 $0.00
lanes
Landscape $876.00 $0.00 $0.00 $876.00 $876.00
design
Acceptance $0.00 $0.00 $0.00 $0.00 $0.00
and Checkout
Demobilization $9,076.80 $0.00 $0.00 $9,076.80 $9,076.80
Earthworks $2,102.40 $0.00 $0.00 $2,102.40 $2,102.40
Prepare the $525.60 $0.00 $0.00 $525.60 $525.60
Layer of
Formation
Sub-base Layer $525.60 $0.00 $0.00 $525.60 $525.60
Layout
Laying the $525.60 $0.00 $0.00 $525.60 $525.60
Base Layer of
the Road
Bituminous $700.80 $0.00 $0.00 $700.80 $700.80
Prime Coat
Laying of $330,108.00 $0.00 $0.00 $330,108.00 $330,108.00
Asphalt
Foundation
Course
Spray Tack $264,086.40 $0.00 $0.00 $264,086.40 $264,086.40
Coat
Laying of $3301071.0 $0.00 $0.00 $330,108.00 $330,108.00
Asphalt
Wearing
Course
Roadway $1,226.82 $0.00 $0.00 $1,226.82 $1,226.82
Signage
Putting up $700.80 $0.00 $0.00 $700.80 $700.80
Traffic Signs
Lane marking $0.00 $0.00 $0.00 $0.00 $0.00
Cleaning the $9,427.20 $0.00 $0.00 $9,427.20 $9,427.20
general site

14
Preparing the $0.00 $0.00 $0.00 $0.00 $0.00
project for
handover
Turn Over the $0.00 $0.00 $0.00 $0.00 $0.00
Project
total $519200000.00 $0.00 $0.00 $519200000.00 $519200000.00

COST STATUS
$350,000.00

$300,000.00

$250,000.00

$200,000.00

$150,000.00

$100,000.00

$50,000.00

$0.00

Actual Cost Baseline Cost

15
Task sheet:
% Cost
Durat Predec Finish S
Task Name Start Finish Resource Names Complet Varia CPI
ion essors Slack PI
e nce
Setup and Wed Tue
30 Supervisor,Site
Mobilizatio 08/05/ 18/06/ 100% 1922 days Rs0 0 0
days Engineer
n 13 13
Laying Out
Wed Tue
and 60 Surveyor,Assistant
14/08/ 05/11/ 1 100% 2503 days Rs0 0 0
Surveying days Surveyor
13 13
Work
Obtain
Building
Thu Tue
NOCs from 24
10/10/ 12/11/ 2 NHA,FWO 100% 1841 days Rs0 0 0
All days
13 13
Concerned
Authorities
Trial
Trenches
and Thu Wed
15
Location 07/11/ 27/11/ 2 Dumper Truck,Digger 100% 2372 days Rs0 0 0
days
Check Of 13 13
Current
Facilities
Established
Tue Mon
Utilities 45 Labour (Work
19/11/ 20/01/ 4 100% 2479 days Rs0 0 0
Must Be days Force),Supervisor
13 14
Moved
The
Wed Tue Labour (Work
Installation 60
04/12/ 25/02/ 5 Force),Site 100% 2368 days Rs0 0 0
of New days
13 14 Engineer,Supervisor
Utilities
Send Shop
Drawings Tue Mon
30
for Road 10/12/ 20/01/ 4 NHA,FWO 100% 1822 days Rs0 0 0
days
Work 13 14
Clearance

16
Approve
Tue Mon
the 30
24/12/ 03/02/ 3 HMA 100% 2469 days Rs0 0 0
subcontract days
13 14
ors
Subcontract
Mon Tue
ors Must 7
06/01/ 14/01/ 8 FWO 100% 1833 days Rs0 0 0
Be days
14 14
Approved
Approve Wed Tue
15
Materials 08/01/ 28/01/ 7 NHA,FWO 100% 2473 days Rs0 0 0
days
Submittals 14 14
Approve
Material
Mon Fri
Submittals 15
13/01/ 31/01/ 10 Supervisor 100% 1835 days Rs0 0 0
Material days
14 14
Procureme
nt
Wed Tue
Clear and 60 Labour (Work
29/01/ 22/04/ 7 100% 2388 days Rs0 0 0
Grubbing days Force),Supervisor
14 14
Dresser
Earthwork,Supervisor,
Wed Tue Labour (Work
Earth 45
05/02/ 08/04/ 12 Force),Excavators and 100% 2303 days Rs0 0 0
Shifting days
14 14 Earth Moving
Machine,Tractor
Trolley
Cranes,Labour (Work
Wed Tue
30 Force),Mason,Site
Drainage 12/02/ 25/03/ 20 100% 2433 days Rs0 0 0
days Engineer,Supervisor,P
14 14
ipes
Aggregate[1%],Comp
Tue Mon
25 actors,Labour (Work
Fine-tuning 18/02/ 24/03/ 13 100% 2434 days Rs0 0 0
days Force),Earthwork
14 14
Dresser
Noise Thu Wed
25
Reduction 27/02/ 02/04/ 12 Steel[1%] 100% 2097 days Rs0 0 0
days
Barriers 14 14
Installation Mon Fri
60
of 03/03/ 23/05/ 12 Steel[1%] 100% 2300 days Rs0 0 0
days
Guardrails 14 14
Mon Fri Aggregate[1%],Comp
Base 45
17/03/ 16/05/ 14 actors,Earthwork 100% 2320 days Rs0 0 0
granular days
14 14 Dresser,Labour (Work

17
Force),Sand[1%],Supe
rvisor
Conduits Mon Fri
90
for 04/06/ 05/10/ 42 100% 1220 days Rs0 0 0
days
Electricity 18 18
Pipes,Labour (Work
Mon Fri
Installation 45 Force),Concrete
01/05/ 30/06/ 12 100% 990 days Rs0 0 0
of Drains days Mixers and Pumping
17 17
Equipment
Aggregate[1%],Comp
Final Mon Fri
90 actors,Dresser
Granular 06/03/ 07/07/ 18 100% 1575 days Rs0 0 0
days Earthwork,Labour
Base 17 17
(Work Force)
Mon Thu
Walls of 150
3/20/1 9/28/1 17 Aggregate[1%] 100% 260 days Rs0 0 0
Protection days
7 7
Fri Thu
Paving on 45 Aggregate[1%],Pavers
9/29/1 11/23/ 21 100% 0 days Rs0 0 0
Base days (Asphalt)
7 17
Earthwork,Labour
Symbolism Fri Sat
180 (Work
(Foundatio 11/24/ 6/30/1 23 100% 410 days Rs0 0 0
days Force),Mason,Steel[1
ns) 17 8
%]
Mon Fri
Installation 90 Labour (Work
13/05/ 13/09/ 39 100% 960 days Rs0 0 0
of Signage days Force),Steel[1%]
19 19
Laying Asphalt & Cement
Mon Fri
bricks 120 Plant,Labour (Work
12/30/ 5/22/2 35 100% 470 days Rs0 0 0
(Wearing days Force),Pavers
19 0
Course) (Asphalt)
Aggregate[1%],Asphal
Granular on Sat Thu t,Labour (Work
45
the 5/23/2 7/16/2 26 Force),Earthwork 100% 545 days Rs0 0 0
days
Shoulders 0 0 Dresser,Sand[1%],Sup
ervisor
Mon Wed
Marking of 180 Road Marking
6/27/2 1/25/2 39 100% 410 days Rs0 0 0
lanes days Machine,Distemper
2 3
Fri Wed Labour (Work
Landscape 300
10/15/ 6/14/2 39 Force),Supervisor,Tru 100% 290 days Rs0 0 0
design days
21 3 cks
Acceptance Tue Mon
15
and 15/11/ 05/12/ 39 100% 1729 days Rs0 0 0
days
Checkout 16 16

18
Mon Fri
Demobiliza 60 Cranes,Supervisor,Tru
06/08/ 26/10/ 42 100% 755 days Rs0 0 0
tion days cks
18 18
Wed Tue
540 Supervisor,Digger,Lab
Earthworks 07/02/ 03/03/ 24 100% 204 days Rs0 0 0
days our (Work Force)
18 20
Prepare the Sun Thu
90 Labour (Work
Layer of 02/06/ 03/10/ 32 100% 601 days Rs0 0 0
days Force),Supervisor
Formation 19 19
Sub-base Tue Sat
90 Labour (Work
Layer 09/07/ 09/11/ 33 100% 376 days Rs0 0 0
days Force),Supervisor
Layout 19 19
Laying the Mon Fri
90 Labour (Work
Base Layer 09/12/ 10/04/ 34 100% 555 days Rs0 0 0
days Force),Supervisor
of the Road 19 20
Labour (Work
Mon Fri Force),Supervisor,Asp
Bituminous 120
12/30/ 5/22/2 35 halt,Asphalt & Cement 100% 1 day Rs0 0 0
Prime Coat days
19 0 Plant,Asphalt &
Cement Plant engineer
Labour (Work
Laying of
Sat Fri Force),Supervisor,Asp
Asphalt 150
5/23/2 11/20/ 36 halt,Asphalt & Cement 100% 290 days Rs0 0 0
Foundation days
0 20 Plant,Asphalt &
Course
Cement Plant engineer
Labour (Work
Sat Thu Force),Supervisor,Asp
Spray Tack 120
11/21/ 4/15/2 37 halt,Asphalt & Cement 100% 121 days Rs0 0 0
Coat days
20 1 Plant,Asphalt &
Cement Plant engineer
Labour (Work
Laying of
Fri Thu Force),Supervisor,Asp
Asphalt 150
4/16/2 10/14/ 38 halt,Asphalt & Cement 100% 440 days Rs0 0 0
Wearing days
1 21 Plant,Asphalt &
Course
Cement Plant engineer
Mon Fri
Roadway 210 Labour (Work
03/10/ 21/07/ 39 100% 0 days Rs0 0 0
Signage days Force),Steel[1%]
22 23
Putting up Tue Sat
120
Traffic 22/03/ 03/09/ 39 Labour (Work Force) 100% 0 days Rs0 0 0
days
Signs 22 22
Fri Sat
Lane 210 Road Marking
10/15/ 6/25/2 39 100% 350 days Rs0 0 0
marking days Machine,Distemper
21 2

19
Cleaning Thu Wed
60 Cranes,Labour (Work
the general 10/13/ 12/21/ 19 100% 515 days Rs0 0 0
days Force),Trucks
site 22 22
Preparing
Thu Wed
the project 30
12/22/ 1/25/2 43 FWO,NHA 100% 560 days Rs0 0 0
for days
22 3
handover
Mon Fri
Turn Over 15
25/11/ 13/12/ 44 100% 940 days Rs0 0 0
the Project days
19 19

Resource sheet
Resource Name Type Initials Max. Std. Rate Accrue Base
Units At Calendar
Labour (Work Work L 100% $0.73/hr Prorated Standard
Force)
Project Manager Work P 100% $0.00/hr Prorated Standard
Contractor Work C 100% $0.00/hr Prorated Standard
Consultant Work C 100% $0.00/hr Prorated Standard
Mason Work M 100% $1.30/hr Prorated Standard
Machine Man Work M 100% $0.65/hr Prorated Standard
Site Engineer Work S 100% $1.73/hr Prorated Standard
Surveyor Work S 100% $0.62/hr Prorated Standard
Asphalt & Work A 100% $0.66/hr Prorated Standard
Cement Plant
engineer
Asphalt & Work A 100% $273.70/hr Prorated Standard
Cement Plant
Tractor Trolley Work T 100% $5.08/hr Prorated Standard
Cranes Work C 100% $18.91/hr Prorated Standard
Dumper Truck Work D 100% $16.56/hr Prorated Standard
Compactors Work C 100% $1.73/hr Prorated Standard
Concrete Mixers Work C 100% $2.01/hr Prorated Standard
and Pumping
Equipment

20
Excavators and Work E 100% $16.83/hr Prorated Standard
Earth Moving
Machine
Pavers (Asphalt) Work P 100% $22.92/hr Prorated Standard
Bitumen/Asphalt Material B $0.55 Prorated
Water Material W $6.52 Prorated
Aggregate Material A $0.22 Prorated
Cement Material C $3.42 Prorated
Steel Material S $0.42 Prorated
Sand Material S $0.08 Prorated
Supervisor Work S 100% $0.00/hr Prorated Standard
Site Engneer Work S 100% $0.00/hr Prorated Standard
Assistant Work A 100% $0.00/hr Prorated Standard
Surveyor
Digger Work D 100% $0.00/hr Prorated Standard
LDA Work L 100% $0.00/hr Prorated Standard
HMA Work H 100% $0.00/hr Prorated Standard
EPD Work E 100% $0.00/hr Prorated Standard
TEPA Work T 100% $0.00/hr Prorated Standard
NHA Work N 100% $0.00/hr Prorated Standard
FWO Work F 100% $0.00/hr Prorated Standard
Dresser Work D 100% $0.00/hr Prorated Standard
Earthwork
Pipes Work P 100% $0.00/hr Prorated Standard
Earthwork Work E 100% $0.00/hr Prorated Standard
Dresser
Earthwork Work E 100% $0.00/hr Prorated Standard
Asphalt Work A 100% $0.00/hr Prorated Standard
Road Marking Work R 100% $0.00/hr Prorated Standard
Machine
Distemper Work D 100% $0.00/hr Prorated Standard
Trucks Work T 100% $0.00/hr Prorated Standard

Resource usage:
Resource Name Work
Unassigned 0 hrs
Contract Award 0 hrs
providing of project laboratory 0 hrs

21
shift of control 0 hrs
project kickoff complition 0 hrs
Compaction of natural ground 0 hrs
eartwork complition 0 hrs
base and sub base work complition 0 hrs
cold milling 0 hrs
Aggregate 2 ft3
prepration of subbase 1 ft3
water bound macadam 1 ft3
Bitumen 3 kg
asphalt base course 1 kg
bituminous prime coat 1 kg
bituminous tack coat 1 kg
Cement 0 bags
Water 1 tank
water bound macadam 1 tank
Sand 1 ft3
water bound macadam 1 ft3
Steel 0 kg
Concrete Mixer 0 hrs
Tyre mounted crane 264 hrs
excavation of unsuitable material 80 hrs
formation of embankment from borrow excavator 80 hrs
disposal of existing unusable road apver 104 hrs
Excavator 344 hrs
excavation of unsuitable material 80 hrs
breaking of existing road pavement structure 160 hrs
disposal of existing unusable road apver 104 hrs
Dumper ( 18 Ton ) 560 hrs
excavation of unsuitable material 80 hrs
granular backfill 80 hrs
breaking of existing road pavement structure 160 hrs
prepration of subbase 240 hrs
Gantry 0 hrs
Tractors with trolley 504 hrs
clearing 240 hrs
excavation of unsuitable material 80 hrs
formation of embankment from borrow excavator 80 hrs
disposal of existing unusable road apver 104 hrs
Compactors 600 hrs

22
formation of embankment from roadway 120 hrs
formation of embankment from borrow excavator 80 hrs
prepration of subgrade 160 hrs
prepration of subbase 240 hrs
Pvt. Marking Macliie 0 hrs
Pavers 320 hrs
bituminous tack coat 160 hrs
asphalt wearing course 160 hrs
Protect Manger 160 hrs
prepration of subgrade 160 hrs
Geotechnical Engineer 160 hrs
prepration of subgrade 160 hrs
Site Engineer 584 hrs
preliminary joint survey 64 hrs
detailed joint survey 80 hrs
centre line marking 80 hrs
excavation of unsuitable material 80 hrs
formation of embankment from roadway 120 hrs
water bound macadam 160 hrs
Supervisor 144 hrs
Mobilization of Machinery and Equipment 80 hrs
preliminary joint survey 64 hrs
Surveyor 584 hrs
preliminary joint survey 64 hrs
detailed joint survey 80 hrs
centre line marking 80 hrs
formation of embankment from roadway 120 hrs
formation of embankment from borrow excavator 80 hrs
prepration of subgrade 160 hrs
Asistant Surveyor 0 hrs
Labour 360 hrs
detailed joint survey 80 hrs
breaking of existing road pavement structure 160 hrs
scarification of existing road apvemnet 120 hrs
Caner 0 hrs
Mechanic 0 hrs
cutter 120 hrs
scarification of existing road apvemnet 120 hrs
asphalt palnt 320 hrs
asphalt base course 160 hrs

23
asphalt wearing course 160 hrs
asphalt plant engineer 320 hrs
asphalt base course 160 hrs
asphalt wearing course 160 hrs
pneumetic tyre roller 440 hrs
bituminous prime coat 120 hrs
bituminous tack coat 160 hrs
asphalt wearing course 160 hrs

GANTT chart

24
25
26
27