Flow Chart Hoisting Work and Placement Loadbank & Cable
Flow Chart Hoisting Work and Placement Loadbank & Cable
NO
PERMIT TO WORK FROM 21.30 PM - 05.30 AM
YES
END WORK
PROCESS
DECISION
TERMINATOR
TIME SCHEDULE FOR LIFTING
APRIL
NO ACTIVITY
24 25
1 MOBILISATION CRANE 160 T TO SITE 17.00 - 20.00
2 CLEARING AREA LOADBANK & LIFTING AREA 19.00 - 20.00
3 INSTALL ROAD SIGN/WARNING 19.00 - 21.00
4 MOBILE CRANE ENTERS TO LOCATION 21.00
5 SPREAD STEEL PLATE ON AREA OUTRIGGER 21.30 - 22.00
6 MOBILE CRANE PREPARATION FOR HOISTING AREA LOADING 22.00 - 24.00
7 PREPARE HOISTING LOADBANK 00.00 - 00.30
8 HOISTING LOADBANK1 00.30 - 01.00
9 HOISTING LOADBANK2 01.00 - 01.30
10 HOISTING LOADBANK3 01.30 - 02.00
11 HOISTING CABLE 02.00 - 03.00
12 MOBILE CRANE PREPARARATION LEAVING AREA AND STEEL PLATE REMOVE AREA 03.00 - 05.00
13 CLEARING LIFTING AREA 05.00 - 05.30