4-Pile Foundation (Outer Diameter)
4-Pile Foundation (Outer Diameter)
MAR’2021
DEDICATED WATER SUPPLY SCHEME FOR MADURAI CORPORATION FROM MULLAI PERIYAR RIVER
PACKAGE - III CONSTRUCTION OF SERVICE RESERVOIR, FEEDER MAIN AND CLEAR WATER
TRANSMISSION MAIN FOR PROVIDING DEDICATED WATER SUPPLY TO MADURAI CITY MUNICIPAL
CORPORATION FROM MULLAI PERIYAR AT LOWER CAMP-PACKAGE 3 (AMRUT).LOCATION& SURVEY
NO : CHINTHAMANI VAZHAITHOPPU- T.S.NO.2597
DESIGN REPORT
OUTER DIAMETER
Submitted to :
M/s. KOYA & COMPANY CONSTRUCTION LIMITED,
12-2-831/38,72,MIGH,
Hyderabad-500028.
Submitted by,
COS CONSULTANCY SERVICES
ARCHITECTS, ENGINEERS & DESIGNERS
No. 6/13, Kamaraj Nagar, 4th Street,
Tallakulam, Madurai - 625002.
Ph No: (0452) 2538233,
Fax: (0452) 2538233
E-mail: cosconsultancy@gmail.com
DESIGN REPORT
Dedicated water supply scheme for Madurai Corporation from Mullai Job No.:
Periyar River Package - III Construction of Service Reservoir, Feeder Design by: K.Guru
Main and Clear Water Transmission Main for providing dedicated water
Name of Work: Date: 17-Mar-21
supply to Madurai City Municipal Corporation from Mullai Periyar at Lower
Camp-Package 3 (AMRUT).Location& Survey no : Chinthamani VazhaiThoppu-
T.S.No.2597 Approved
50
400 Pile Cap - 2700x2700x1050
RL (+)137.27
1200
1050
450 1800 450
RL(136.220)
750
Pile 600 Ф
600 600
RL(123.97)
Cross section of Transverse Direction
(-,+) (+,+)
2700
1800
1800
Summary of Maximum & Minimum load on plie without Selfweight of pilecap under pile
Max load on pile = 451.667 kN Min = 403.334 kN (Limit state Combination)
Max load on pile = 301.112 kN Min = 268.889 kN (Serviceability Combination)
Summary of Maximum & Mininum load on plie with Selfweight of pileunder under pile
Max load on pile = 515.937 kN Min = 467.604 kN (Limit state Combination)
Max load on pile = 365.382 kN Min = 333.159 kN (Serviceability Combination)
Dedicated water supply scheme for Madurai Corporation from Mullai Job No.:
Periyar River Package - III Construction of Service Reservoir, Feeder Design by: K.Guru
Main and Clear Water Transmission Main for providing dedicated water
Name of Work: Date: 17-Mar-21
supply to Madurai City Municipal Corporation from Mullai Periyar at Lower
Camp-Package 3 (AMRUT).Location& Survey no : Chinthamani VazhaiThoppu-
T.S.No.2597 Approved
if pile are Short Column or Long Column
Stiffness Factors ( IS 2911 (PartI /Sec 2) 2010 ( Annex - C-2.3 )
R = 4√ EI/ K1
Where E is the Young's Modulus of the pile material in KN/m2 Average N value From Max. scour
and I is the moment of inertia of the pile cross section in m4 level to founding level 15.2
2
Here E = 27.387 kN/m
4
I = π/64x d m4 = π/64x 60 4 = 636172.51 cm
4
SUMMARY OF FORCES AND MOMENTS FOR THE DESIGN OF PILE AT FIXITY LEVEL INCLUDING SELFWEIGHT OF PILE
Vertical Load Moment
Sl.No Description
Maximum Minimum Maximum Minimum
1 Serviceability Combination 365.382 333.159 31.656 31.656
2 Limit state Combination 515.937 467.604 34.408 34.408
Dedicated water supply scheme for Madurai Corporation from Mullai Job No.:
Periyar River Package - III Construction of Service Reservoir, Feeder Design by: K.Guru
Main and Clear Water Transmission Main for providing dedicated water
Name of Work: Date: 17-Mar-21
supply to Madurai City Municipal Corporation from Mullai Periyar at Lower
Camp-Package 3 (AMRUT).Location& Survey no : Chinthamani VazhaiThoppu-
T.S.No.2597 Approved
Design of Pilecap
case 1) Cantilever moment due to load on pile
In Longitudinal & Transverse direction
1050
1800
RL (+)137.270
400
1050
1450
RL(136.22)
Pile 600 Ф
600 600
RL(123.97)
Dedicated water supply scheme for Madurai Corporation from Mullai Job No.:
Periyar River Package - III Construction of Service Reservoir, Feeder Design by: K.Guru
Main and Clear Water Transmission Main for providing dedicated water
Name of Work: Date: 17-Mar-21
supply to Madurai City Municipal Corporation from Mullai Periyar at Lower
Camp-Package 3 (AMRUT).Location& Survey no : Chinthamani VazhaiThoppu-
T.S.No.2597 Approved
Effective width of load from Column = 0.4+2x1.05/2 = 1.450 m
Effective length of pilecap = 0.4+2x1.05/2 = 1.45 < 2.70 m
= 1.450 m
Calculation of stresses
A= Area 7.290 m2 ZL= 2.7x2.7^2/6 = 3.281 m3
ZT= 2.7x2.7^2/6 = 3.281 m3
The stress developed in the Pile cap is calculated using the calculation,
P ML MT
p=
A ZL ZT
Summary of Stresses (Factored)
Nd
R r
α β
N A
Step-2
Radius of equivalent Steel Ring, r (R-d') = 209 mm
Thickness of equivalent steel ring (t) At/(2πr) = 0.86 mm
Distance of Tensile Steel from Compression face,d = D-d' = 509
Distance of Neutralaxis from Compression face,Nd = x = 535
Hence N = 1.052
Step-3 X = 0.892
D
From fig.24.4(Pg:359) of Concrete bridge Practices-V.K Raina
A = 0.056
B = 0.731
C = 0.637
Distance of cg. Of segment from centre of circle
x' = AXR = 17 mm
2
Section area of Segment A1 = BXD = 263269.6403
4 4
Second Moment of area of Segment about its own Centroid,I= CXR = 5155946336 mm
STRESS IN PILE
Job No.:
Dedicated water supply scheme for Madurai Corporation from Mullai Periyar
River Package - III Construction of Service Reservoir, Feeder Main and Clear Design by: K.Guru
Name of 17-Mar-21
Water Transmission Main for providing dedicated water supply to Madurai City Date:
Work: Municipal Corporation from Mullai Periyar at Lower Camp-Package 3
(AMRUT).Location& Survey no : Chinthamani VazhaiThoppu- T.S.No.2597
Approved
75
O 535.2557
450 R r 600
α β
N A
Step-4
(Taking transformed area of Steel as (m-1)Ast, both in tensile &compressive zone)
Aeff = A1+(/m-1)As
2
= 273448.4 mm
Step-5 (Ordinates of C.Geff with respect to Physical Centroid)
Taking moments of effective area about TT and LL axes respectively
e' = A1X'
Aeff
e' = 16.26616 mm
e=(M/P) = 95 mm
e-e' = 79 mm
Step-6
2
Ieff = 5155946336 + 263269.6 X ( 17 - 16.2661604 )
2 2
+ ( 10 - 1 ) X 1130.97 225 + 16.2661604
2
= 5155946336 + 104126 + 260343045
4
= 5416393507 mm
Step-7 Distance of Neutral axis below Cgeff
Ieff = 25.15219 cm
Aeff(e-e')
Compared to 16.2661604 - 535 - 300 25.1521896 cm
10
Percentage error = 0.00
Step-8 (i)Max Compressive stress in Concrete
= P P(e-e')(D/2-e')
Aeff + Ieff
= 333.159 333 79 X 300 16.2661604
= 273448.4005 + ( )5.42E+09
( - )
= 0.00121836 + 0.001374 )
2
= ( 0.00259276 KN/mm 1000 = 2.59 N/mm2
X < 11.67 N/mm2 OK
(i)Max tensile stress in Steel
= m P P(e-e')( d-D/2+e')
Aeff - Ieff
= 10 333.159 333.159 79 509 300.0 16.27
X 273448.4005 - ( X ( ) X (
5.42E+09 - + )
= 10 0.001218361 - 0.001091
2 2
= 0.001272X KN/mm
( X 1000 ) = 1.27 N/mm
2
< 275 N/mm OK
STRESS IN PILE
DRAWINGS
CL OF PILE CAP
Y PILECAP
(e)
2700 2700x2700x1050
#10Ø@200c/c (d) 450 1800 450
450
450
896
600
X X
(c)
#8Ø-200c/c(Ties)(g)
SECTION "Y-Y"
+#16Ø stiffener
(a)
2700
2700
1800
1800
#10Ø@150c/c (e)
(b)
#16Ø@150c/c (b)
(d)
600
550
896
450
450
1050
#10Ø@200c/c (c) #16Ø@150c/c (a)
#8Ø ties -3Nos
Y
HALF PLAN AT TOP HALF PLAN AT BOTTOM
(d) PILECAP
(c)
(+)137.270m 2700x2700x1050
KEY PLAN
Ø 600 dia NOTES :-
#8Ø ties -3Nos
1050
1. All dimensions are in "mm" and all levels are in "m". 9. Lapping of reinforcement bars shall be avoided as far
(e)
as possible. However, if laps are required to be
550
#12Ø-10nos (f) 2. All design mix & nominal mix of concrete shall provided,the lap length shall be as per Cl.26.2.5.1of
(b)
(Main reinforcement) conform toCl.9.2 of IS:456-2000. IS:456-2000.
(+)136.220m 3. Grade of concrete mix shall be in vibrated R.C.C M35 10. Development length shall be as per Cl.26.2.1 of
(design mix) for Pile and R.C.C M30 (design mix) for IS:456-2000.
(a) Pile cap.
11. The bottom levels of foundations are tentatively fixed
TIES(g)
4. Clear cover to reinforcement shall be 75mm for Pile on the Light brown coloured sand based on the
#8Ø@200mmc/c
cap & Pile available bore particulars.The Maximum vertical load
on pile (excluding self wt) is 310kN. If there is any
#8Ø-200c/c(Ties)(g) 5. Precast mortar blocks of respective grades shall be variation in the subsoil particulars during confirmatory
+#16Ø stiffener used under the reinforcement to ensure the required boring, revised design has to be got approved from the
896
896
600 rings @1.5m c/c(h) 600 #16Ø Stiffness rings cover. Competent Authority before execution.
(+)123.970m @1.50mc/c (h)
6. Grade of steel shall be Fe-415 as per Cl.5.6 of 12. This drawing shall be read in conjunction with all
450 1800 450 SECTION ON PILE IS:456-2000& IS :1786-2008. other relevant drawings of this work.
2700
7. Welding of Reinforcement bars is generally not 13. Do not scale the drawing follow figured dimension
SECTION "X-X" recommended as per Cl.12.4of IS:456-2000. only.