Professional Documents
Culture Documents
CH 13 Powering
CH 13 Powering
CHAPTER 13 – POWERING
1. The resistance and power were calculated across the range of ship
speeds at various stages throughout the design process so that it could be
seen what the ramifications of particular changes were for power requirement.
The resistance and speed power curves were calculated using the simple
Holtrop (1) method including a 10% sea margin and a 10% appendage margin
applied to resistance. It was also assumed that a 10% reduction in wave
making resistance could be achieved by placing our side hulls between the
transom and amidships. This resistance saving results from wave cancellation
between the side hulls and the main hulls which does not occur with trimarans
which have their side hulls centred at amidships.
a. Pods can be angled into the flow of water to allow the blades to
function at their optimum, design angle of attack.
b. The absence of shafts and A-frames in the flow field mean that the
flow is less turbulent as it enters the propeller.
c. The angling of the pod along with the absence of shaft lines means
that the after cut up can be faired more effectively thereby
achieving a more efficient hull.
d. The pods selected for LPD rotate and are connected to the hull by
a control surface comparable to a rudder which rotates with the
pod. This means that the ship should be more manoeuvrable and
the appendage resistance will be less than with shafted propulsion.
Data from the Alstom Mermaid Pods used on QM2 suggested the following
figures for percentage power saving are given in the table below. These pods
operate at a similar power and are similar weight to the LPD pod selection.
717.00
R e s is t a n c e ( k W )
716.00
715.00
714.00
713.00
712.00
711.00
710.00
709.00
0 5 10 15 20
projected are a of bulbous bow (m ^2)
These % power savings were applied to the speed power curves after the
calculations had been made for conventional shafted propulsion.
3. Because of the size and displacement of the LPD a bulbous bow was
included in the design to minimise the resistance of the hull. This was
originally estimated to be a 10 square metre projected area bulbous bow.
However, for the final speed power calculation an investigation was made into
the optimum size of the bulbous bow by keeping all other parameters constant
and repeating the Holtrop calculation with varying bulbous bow sizes. The
results are shown in figure 1 and as can be seen the benefit of increasing the
bulbous bow size tales off after 13 square metres bulbous bow projected area
and so this was selected.
4. The speed power curve was calculated using the simple Holtrop
method for trimarans. The power savings from the use of pods were applied
at their lower end (11%) thereby assuming the worst case. The final speed
power curve is shown below along with a table of the values. The two rows
highlighted in the table are the two most important speeds for our ship based
on the operating profile; loitering speed and cruise speed. The maximum
power in the water required at top speed of 24kts is 41.7MW.
2 0.4
4 0.7
6 1.1
8 1.7
10 2.7
12 4.1
14 6.2
16 9.5
18 14.2
20 21.0
22 29.7
24 41.7
Table 2: Power Speed Figures
45.0
40.0
35.0
Shaft Power (MW)
30.0
25.0
20.0
15.0
10.0
5.0
0.0
0 5 10 15 20 25 30
Speed (kts)
thinner. Also, the speed at which a ship of this displacement starts to save
power by being a trimaran was outside the LPDs operating profile as
discussed in CHAPTER 2.
7. Hull fouling has not been taken into account in this calculation but
through life this is not expected to be a problem. Roughness due to hull
fouling usually reaches it’s maximum after a year and can be cleaned off
during maintenance periods. It does not get progressively worse throughout
ship life.
8. The 10% appendage margin stated in paragraph 1 was not the result of
calculation. At this early stage of the design process the design of
appendages was not considered a priority for LPD. The appendage margin is
a generic number based on past designs but in a detailed design cycle it is
hoped that this 10% could be improved upon with the use of pods since they
eliminate the need for rudders. Also, the high block coefficient of LPD will
have a high roll damping coefficient when compared to the hull of a frigate.
The side hulls will display overall roll damping via their own local heave
damping. These two factors should mean bilge keels and stabilisers need only
be small if they are required at all.
10. The design drivers for propeller design on the LPD were not just a
trade off between propeller diameter and power or rpm required to achieve
the appropriate speeds. LPD is to operate in the littoral environment (and
dock down); hence the draught of the ship design was constrained by
requirements to 5.8m. Therefore the aim of the propeller design was to arrive
at a propeller size and pod configuration such that it would all fit between the
keel and the dock bottom, enveloped by the after cut up. It was known from
the percentage power savings available by the use of pods that a smaller
propeller would be possible to maintain an acceptable power requirement.
Consideration was also given to using three smaller pods but this was
discarded as the losses involved in the unavoidable opposition of propellers
was deemed to cancel out the power saving made by employing pods.
Another option was to fit large tractor pods on the side of the main hull with
two very small pods astern for steering however the Marine Engineer felt that
the technological risk inherent in this design was too great. Therefore the
purpose of the propeller design was to select the smallest propeller possible
11. The initial approach adopted to conduct propeller design was to use
the charts from the AEW Series Propeller Experiments ( 2). In order to do this
the following assumptions and estimations were made.
12. In order to make a propeller selection from the AEW data series some
initial estimates of BAR for various diameters were calculated. The calculation
process is outlined below.
The power required in the water was calculated previously via the Holtrop
method and this was the starting point for the calculation along with the
assumed parameters defined above. Velocity of advancement, Va, is given
by;
V A (V s (1 WT ))0.51444
1 t
H
1 WT
TR K T N s2 D 4V s (1 Wt ) 2 H
TM PEA
PEA
Thrust / propeller
V A H Z
Thrust / propeller
BAR
D 2 70000
4
All the different diameters gave results of Blade Area Ratio (BAR) close to 0.2
and this was the chart used for the propeller selection. However this is not a
K T ThrustPer Pr opeller
J2 V A2 D 2
Then by assuming values of J^2 a parabola of KT values was plotted for each
diameter on the BAR=0.2 AEW data series charts. Copies of these charts are
shown in Annex P. The results from the AEW charts are summarised in the
table below.
Shaft RPS and Shaft Power required for 14 kts with different diameter props
10.000
9.500
9.000
Shaft Power (MW)
8.500
8.000
7.500
7.000
1.000 1.200 1.400 1.600 1.800 2.000 2.200 2.400 2.600 2.800 3.000
Shaft Speed (RPS)
3.5m diameter prop 3.75m diameter prop 4m diameter prop 4.25m diameter prop 4.6m diameter prop
14. As previously mentioned, the initial calculation for estimating the BAR
turned out to be unreliable therefore it was necessary to validate these
selections of pitch ratio and diameter via a separate method. This was done in
two ways; a quick analysis using the Wageningen B (1) series; and using the
AEW series charts again but with a more sensible estimated BAR based on
similar ships.
15. The Wageningen B series data was used to check that the 3.5m
diameter propeller could provide the required ship speed for an achievable
RPM and power. Figure 4 shows that the smaller propeller does require
significantly faster shaft speed (130-300RPM to cover the ship speed range)
but this range is possible with LPD’s selected pod machinery fit. Any smaller
propellers would go beyond the 320RPM limit of this machinery fit.
350
300
250
Shaft Speed (RPM)
50
0
0 5 10 15 20 25 30
Ship Speed (kts)
Figure 5 shows that there is little difference in power requirement between the
various diameter propellers.
25000
20000
Power delivered to props (MW)
5000
0
0 5 10 15 20 25 30
ship speed (kts)
0.7
0.65
Propeller open water efficiency (%)
0.6
0.4
0.35
0.3
0 5 10 15 20 25 30
ship speed (kts)
Figure 7 shows that the optimum P/D ratio calculated via the Wageningen B
method is 1.1. However it was noted that there was less than1% difference in
propeller efficiency between P/D=1 and P/D=1.3.
0.75
300
0.70
0.65 250
Efficien cy
0.60
200 rp m
0.55
150
0.50
0.45 100
0.40
50
0.35
0.30 0
0.5 0.6 0.7 0.8 0.9 1 1.1 1.2 1.3 1.4
P/D
plot the KT parabola and read off the results for op-en water efficiency,
advancement coefficient and optimum pitch ratio. The results were P/D=1.2
which corresponded to an advancement coefficient of 0.85 and an open water
efficiency of 0.68 (68%). Therefore, based on these three sets of analyses a
final propeller selection was made;
17. The propeller design has thus far taken no account of cavitation, noise,
vibration and pressure on the hull. It was assumed that a 5 bladed propeller
would mean that there were no problems with pressure on the hull. In a
following design cycle it is recommended that 6 blades are considered with a
view to getting the propeller closer to the hull and also using a propeller even
smaller than 3.5m without having to exceed the 320RPM pod limit. With
respect to vibration, the pods would be carefully positioned so as not to
transmit excessive vibrations up through bulkheads. This shouldn’t be a
problem as the presence of the dock means there are no bulkheads directly
above the pods and their machinery. Cavitation and noise were not
considered a major issue for LPD with respect to signature as it is expected to
be escorted in most roles and with the pod machinery in the water LPD will
never be super quiet. However, cavitaion analysis should be carried out in
further design cycles as it can damage the propellers and the hull (cavitation
corrosion) if it is excessive.
18. The draught constraint set in the requirements was 5.8m, hence the
efforts to select the smallest possible propeller. However, this has not been
possible at this stage of design. Even with the 3.5m propeller, the azimuthing
machinery requires a minimum of 1.8m. The structural stiffeners around the
after cut up were designed to be up to 0.3m deep and the dock sill must be
above the water line so the minimum draught to the bottom of the propeller
with the current design is 6.7m. CFD analysis would be useful also to
determine the losses involved in using 3 pods with their opposing rotational
direction as this may be a feasible option for meeting the draught requirement.
It is also recommended that CFD and or model tests are carried out to
validate the theory of propeller selection for the specific case of pods with the
specific hull form.
pod and propeller configuration is required to predict the shaft power more
reliably.