Professional Documents
Culture Documents
FMGD23 Introduction To Operations Management
FMGD23 Introduction To Operations Management
FMGD23 Introduction To Operations Management
UNIVERSITY
SCHOOL OF BUSINESS AND MANAGEMENT
ADMINISTRATION
Operation Management
group Assignment II
1. The fifth unit job took 14.5 hours to complete. If a 90% learning curve is appropriate:
a. How long should it take to complete the last unit?
= 14.5.0
2. Amy Xia’s plant was designed to produce 7,000 hammers per day but is limited to making 6,000 hammers per day
because of the time needed to change equipment between styles of hammers. What is the utilization?
Actual output
Utilization=
designcapacity
¿ 0.8771 ×100 %
= 85.71
= 85.7%
Therefore, its Utilization is 85.7 %
3. If a plant has an effective capacity of 6,500 and efficiency of 88%, what is the actual output?
Actual output
efficiency =
effective capacity
x
88 %= × 100
6500
x
0.88=
6500
x = 0.88 x 6500
= 5720
Therefore the Actual Output is 5720.
4. A plant has an effective capacity of 900 units per day and produce 800 units per day with its products mix; what is
its efficiency?
Actual output
efficiency =
effective capacity
800
=
900
= 0.8888 x 100 %
= 88.9 %
Therefore its efficiency is 88.9 %
Costs 0.25 50 80 30
Traffic 0.20 40 80 60
density
Neighbourho 0.15 40 70 40
od income
Zoning laws 0.10 80 20 90
a. At which site should Telekom open the new centre? Show calculations.
Neighbourhoo
d income 0.15 0.15 x 40 = 6 0.15 x 70 = 10.5 0.15 x 40 = 6
Answer: Therefore Telekom should open its new centre at Aligegeo School.
2. The fixed and variable costs for three potential manufacturing plant sites for a rattan chair weaver are shown:
Site Fixed cost per year ($) Variable cost per unit ($)
1 500 11
2 1,000 7
3 1,700 4
Total costs
5000
4500
4000
3500
3000
1000
500
0
0 50 100 150 200 250 300 350 400
A lumber Yard in Ranadi has four jobs on order, as shown in the following table. Today is day 205 on the yards schedule.
1. In what sequence would the jobs be ranked according to the following decision rules.
a. FCFS
job work
processing time
Job (days) flow time job due date Job lateness
A 212 212 6 206
B 209 421 3 418
C 208 629 3 626
D 210 839 8 831
839 2101 2081
Sequence A, B, C, D
b. SPT
job work
processing time
Job (days) flow time job due date Job lateness
C 208 208 3 205
B 209 417 3 414
D 210 627 8 619
A 212 839 6 833
839 2091 2017
Sequence C, B, A, D
c. EDD
job work
processing time
Job (days) flow time job due date Job lateness
C 208 208 3 205
B 209 417 3 414
A 212 629 6 623
D 210 839 8 831
839 2093 2073
Sequence C, B, D, A
d. LPT-
job work
processing time
Job (days) flow time job due date Job lateness
A 212 212 6 206
D 210 422 8 414
B 209 631 3 628
C 208 839 3 836
839 2104 2084
Sequence- D, A, C, B
e. Critical ratio
Sequence D, C, A, B
2. Which is the best and why? Which has the minimum lateness?
the results of these floor rules are summarized in the following table;
Average
completion Utilizations Average number of
Rule time metric (%) jobs in system Average lateness (days)
Therefore, the shortest processing time is the best technique for minimizing job flow and minimizing the average
job in the system. In minimum lateness, critical ratio tends to perform better than FCFS, SPT, EDD or LPT on the
average job – lateness criterion. This is because it gives priority to jobs that must be done to keep on schedule.
However in between the other four, SPT, has the minimum lateness?
b) What is the average inventory if the economic order quantity is used?
Jay Heizer, Barry Render. (2014). Operation Management. Essex: Personal Education Limited.