Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)

SATIP No. APPROVED DATE DISCIPLINE:


SAUDI ARAMCO TYPICAL INSPECTION PLAN
Hydrostatic Testing of Pipelines SATIP-A-004-03 25-May-05 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

1.1 Hydrostatic testing Procedure SAIC-A-2001 RH1 RH1

1.2 Review of Test Package Preparation SAIC-A-2003 RH1 R2 * See Note 1 (General Notes)

1.3 Lay-Up Procedure SAIC-A-2007 RH1 RH1

2.0 MATERIAL RECEIVING

Verification of water chemistry and


2.1 SAIC-A-2008 SATR-A-2014 RH1 R1
corrosion inhibitor

3.0 APPLICATION

SAIC-L-2139 In conjunction with Pipeline SATIP-L-450-03,


3.1 Pre-Test Punchlisting-PIPELINES SAIC-L-2139 H1 H1
SATR-A-2007 SATIP-L-450-04.
Cleaning/Flushing (Scraping) prior to SAIC-A-2017 In conjunction with Pipeline SATIP-L-450-03,
3.2 SAIC-A-2017 H1 W1
hydrotest SATR-A-2008 SATIP-L-450-04.

SATR-A-2002
SATR-A-2003
SATR-A-2004 Forms SATR-A-2003 shall be used for 24-hr
Test Preparation & Verification of Testing
SAIC-A-2009 SATR-A-2005 recorded hydrostatic test, Ie; underground piping or
3.3 equipment (including safety H1 W1
SATR-A-2006 piping whose joints are covered before pressure
requirements)
SATR-A-2001 testing.
(for test
Manifold)

Filling & Pressurization


3.4 a. Strength Test Pressure SAIC-A-2013 W1 S
b. Tightness Test Pressure
Form SATR-A-2001 is a modified version or
3.5 Visual Inspection at Test Pressure SAIC-A-2015 SATR-A-2001 H1 H1
merging of Forms SA-2642ENG & SA-2642-1
Pneumatic Testing of Reinforcing
pads/sleeves covering pressure SAIC-A-2016
3.6 SAIC-A-2016 W1 W1
containing Welds and Weld+ End SATR-A-2001
Couplings

4.0 POST- TEST

Page 1 of 3
SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Hydrostatic Testing of Pipelines SATIP-A-004-03 25-May-05 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

4.1 De-Pressurization & Water Disposal SAIC-A-2017 W1 S

4.2 Lay-up SATR-A-2009 SATR-A-2009 H1 W1

Page 2 of 3
SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Hydrostatic Testing of Pipelines SATIP-A-004-03 25-May-05 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust
1 the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization.
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3 organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4 attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
W1 100% Witness Inspection/Test H2 Sample Hold Point for QC Inspection or Test RH1 100% Review and Approval of Documents
W2 Sample Witness Inspection/Test R1 100% Review of Documents RH2 Sample Review and Approval of Documents
H1 100% Hold Point for QC Inspection or Test R2 sample Review of Documents S Surveillance

Page 3 of 3

You might also like