Professional Documents
Culture Documents
Planning & Design For Construction of Bridges
Planning & Design For Construction of Bridges
PVS Sarma
Vice President / Railways
Aarvee Associates
architects engineers & consultants pvt. ltd
Structure of Presentation
➢Bridges – Types
2
Bridges – Types
• Based on function
• Highway, Railway, Metro
• Based on Material
• Concrete, PSC, Steel, Composite, timber, Masonry
• Culverts
• Box, Pipe
Planning for Construction
Requirements of good planning:
- Design decisions effect:
- -Buildability
- Cost
- time
- Modern Methods of Construction to save time & cost of
construction.
➢ Knowledge of Construction process
➢ Knowledge of Equipment & construction Techniques
➢ Knowledge of Interface issues
➢ Planning should also address Health & Safety aspects
4
Planning for Construction
• Benefits of Good Planning
➢ Considerable saving in time and cost is feasible with proper planning
5
Planning for Construction
• Actions in Planning
➢ Carryout thorough investigation
➢ Levels, utilities, adjacent structures, space available for cranes, access, geotech
➢ Plan for essential site production requirements
➢ Site access requirement, material handling, construction programme
➢ Plan for a practical sequence
➢ Construction sequence to maintain stability of structure at all stages. Assumed Method of
erection to be indicated in Design basis.
➢ Plan for Simplicity of assembly
➢ Standard simplified connections should be used wherever possible. Repetitious, automated
procedures increase speed of construction and reduce cost.
➢ Recognise complexity of Design process
➢ Supercomputers are available for complex designs, however, qualitative feel of structural
behaviour is essential.
➢ Agree information and programme
➢ Manage Design development
Bridge components
SUPERSTRUCTURE
PIER ABUTMENT
DROP WALL
Planning for River Bridges
➢ Linear Waterway
➢ Span arrangement
➢ Type of foundation
➢ Type of Superstructure
➢ Bearings
➢ River Protection – Guide bunds, toe walls, etc.
Linear Waterway
➢ Depends on Estimated flood
discharge, bed profile,
presence/absence of rigid banks, etc.
35
⚫ Model analysis 30
25
Discharge in Cumecs
15
10
0 1 2 3 4 5 6 7 8 9 10
Time in Hours
Planning for River Bridges
• Span arrangement, foundation, Substructure & Superstructure types:
➢ Cost Economics
➢ Construction feasibility
➢ Construction time
➢ Foundations:
➢ Piles (vertical/Raker), Wells/Caissons, Open
➢ Based on Scour, water depth during construction
➢ Substructures:
➢ Solid Abutments, Spill through abutments, multiple columns for abutments & piers, wall type
piers, etc.
➢ Superstructures:
➢ Slab, Girder, voided slab, box, various forms and materials
➢ Bearings
➢ To transfer loads to substructures, allow rotations, movements
➢ Sliding, Roller/Rocker, Elastomer, Pot/PTFE, Spherical
➢ Protection works
➢ Toe walls, Guide bunds, curtain & drop walls
Toe Wall
& Pitching
FLOORING
Spurs
Planning for Bridges in Urban
environment
• Issues:
➢Traffic congestion / traffic diversions
➢Underground Utilities (Sewer, Gas pipe lines, cables,
etc.,)
➢Safety of adjacent buildings/structures
• Solutions:
➢Precast & Prestressed concrete
➢Steel / Composite
➢RE walls
Interchange — Existing Structures
Proposed Improvement
Completed Interchange
Elevated Metro structures- Precast elements
Planning for Bridges in Hilly regions
Construction feasibility –
Deep Gorges, rivers with
boulder beds, accessibility
for plant & equipment
Slip form construction for
tall piers
Key technical data of
Chenab Bridge:
Bridge length: 1,315 m
including the 650 m long
viaduct on the northern
side Chenab Bridge
Arch span: 467 m
Planning for Road Over Bridges
• Railway Requirements
• SOD
• Future expansion plans of Railway
• Railway ROW
• Train movement during construction
• Construction feasibility
SCHEDULE of DIMENSIONS
Kukatpally ROB
• Provision for future
track
• Steel composite
Girder for easy
erection
• Erection with
minimum blocking
of trains
movement
Road Over Bridge to cross 5 tracks
• ROBs in DFC Project:
➢ Maintenance:
➢ Bearings replacement
➢ Painting of Steel Bridges
Inspection Facilities
Ladders,
Cradles &
platforms
Sliding Platform
Inspection Arrangements
Inspection using crane in progress
Planning for Interfacing with other other
Departments
Viaduct design & construction Considering future flyover & future subway
• Land availability:
• Land for sufficient working access and space to simplify and speed up
construction, with required use of large lifting equipment
• Utilities:
• Significant influence on the construction programme, but their impact
can be minimised by avoiding the need for diversion.
• Traffic Management:
• Road closures, lane closures, rail or waterway possessions can affect the
speed of bridge construction.
• Off-site fabrication:
• Erection time on site can often be reduced through the prefabrication of
elements in a workshop or alongside the bridge.
• Repetition:
• Standardisation of details and dimensions within and between different
bridges will reduce construction time.
Planning for Fast Construction
• Permanent formwork.
• Precast Concrete
• Use of Couplers
• Travelling Falsework
• Reinforce Earth Walls
• Precast concrete Box Sections
• Precast arches
• Precast Concrete Beams
• Precast Segmental Bridges
• In situ Balanced Cantilever Bridges
• Incrementally launched Bridges
• Transversely slid or rolled bridges
• Jacked boxes
• Use of steel instead of concrete will definitely reduce construction time, but will be
costly.
Construction of RUB- Pendurthi - Kothavalasa
➢ International Codes
-Euro, AASHTO, UIC, etc.,
➢ IS codes
- IS 456, IS 800, IS 2911, etc.,
Concrete Bridges
4. Cannot be used for very large Can be used for longer spans
spans
CASTING OF SEGMENTS
44
ERECTION OF SEGMENTS
45
Durga flyover- spine segment erection &
attachment of wings.
Lucknow Metro Viaduct required to cross 12
tracks
➢ Crossing 12 Indian Railway tracks In
Charbagh yard of Lucknow Railway
Station (9 tracks of NR & 3 tracks of NER)
49
Casting segment
50
Casting segment
51
Top levels
136.740 136.740
136.740 136.740 136.740 136.740
52
Design Aspects
➢ Prestressing:
➢ 4 Phases:
Phase 1 After casting of each segment
(Two numbers for each
segment : 64 nos)
➢ Design Criteria:
Approved DBR
Anchorage Zone
•Maximum stresses
during stressing
operation
Structure on MONO PILE Piers
Steel Bridges
• For Railways
• Plate Girders for small spans & Truss Bridges for Long spans
• Less weight compared to concrete Bridges
• Issues - Corrosion & Fatigue
• Checking of Quality of field weld
• Cost Vs Concrete to be checked.
• Maintenance cost is more
Traditional Steel Superstructures
Black Bolts:
usually Gr.4.6,
made snug tight,
ductile and cheap,
only static loads
HSFG Bolts:
Gr.8.8 to 10.9,
less ductile,
excellent under dynamic/fatigue loads
76
TIGHTENING OF HSFG BOLTS
¾ turn
1) Turn-of-nut Tightening position
2) Calibrated Wrench Tightening snug-tight
3) Alternate Design Bolt Installation position
4) Direct Tension Indicator Method
77
Corrosion Resistance Steel Bridge
Camber of Steel truss Bridges
79
Steel Bridges- Erection Methods
➢ Erection by Incremental lunching method
86
Erection by Launching Gantry
Composite Bridges
Rapid Metro-Gurgaon
48m Span Composite Girder under
construction
Cable Stayed Bridges
VIDYASAGAR SETU
91
Extradosed bridges
Arch Bridges
Bow String Arch Bridge ROBs
• ROBs in DFC Project:
Naihati Bandel
SPAN - 2
SPAN - 1 SPAN - 3
Before
After
Bridge Aesthetics
• Bridges are seen on the move.
• Overall proportions when seen from large distance.
• Shape and integration when seen from medium
distance
• Surface finish, texture & weathering when seen from
close
• Harmony of the bridge with surroundings is
important.
• Joints & Bearings effect aesthetics. Integral &
continuous bridges are generally aesthetic & also
durable.
Bridge Aesthetics
Design for safety
• Designer shall foresee safety measures required during construction,
maintenance and repair works. (Lifting of heavy girders, space for
inspection, replacement of bearings, etc).
• Risk assessment to be carried. Risks shall be avoided, reduced or
controlled.
• To avoid working at Height, Prefabrication may be considered.
• Site cutting & welding – Provision of access platforms.
• Risk of Fire – Use of alternative product / Protective coatings.
Sustainable Bridge Design
• Less carbon print. Has become increasingly popular.
Sustainable Bridge Design
Development of Concrete Technology
108
High Strength Concrete
➢ Test on Piles:
➢ Tests on Bearings