Professional Documents
Culture Documents
Anaylsis of Rates
Anaylsis of Rates
3.1 INTRODUCTION
of materials,
The determination of rate per unit of of work, from the cost of quantities
a particular item
cost of labourers and other miscellaneous petty expenses require for its completion is known as the analysis
the
ate. A reasonable protit, usually 10% for the contractor is also included in the analysis of rate. Rates of materai
the rates delivered at the site of work and include the first cost (cost at origin), cost of transport,
usually taken as
e
are
railway freight
if any, taxes, etc.
work could
For the purpose of analysis, the details about all the operations
involved in carrying out the De
known and the number of different categories
available, the quantities of materials required and their costs should be known. These
labourer and their wages per day should be
oflabourers required and the capacity of doing work per
be known only from experience of practical works.
can
he rates ofa particular item of work depends on the following
constructional
of materials, proportion of mortar method of
(a) Specifications of workS and materials, quality
operation, etc.
of labourer and their rates.
(b) Quantities of materials and their rates, number of different types
the rate of transport,
Location of the site of work and its distances
from the s o u r c e s of materials and
(c)
availability of water.
of contractor.
(d) Profits and miscellaneous and overhead expenses
these factors affect the cost per unit of work done at site.
3.5.1 Task
of work per day in known as the task-wom
Thecapacity of doing_work by skilled labour in the form of-quantity
or out-turn of the labour.
artisan varies to extent according the nature, size, height, situation, locatio
to
The out-turn of work per some
where specialised and experienced labour is available the out-turn is greater than small towns a
etc. In bigger cities
country sides. In well organised work less labour is required.
task for an average artisan per day.
The foilowing may be taken as the approximate quantity of work or
out-turn or
-Do-in superstructure
per mason
arches 0.55 cu mn
5. Brick in cement or lime mortar in
0.55 cu m per mason
-Do- in jack arches
6.
5.00 sq m per mason
hor Output constant in Days (8 working hours) following allI India Schedule of Rate. This
3.5.2
up labour contract rates.
i s is helpful to fix
SI. Description of work
Unit Labour in days (8 working hrs.)
No.
(A) Earthwork
14; Bhisti -
2
in superstructure ground floor
12. First class brickwork 10 cu m Head Mason
: Mason -8
First-class brickwork for 1st. Floor (The rate of ground
Mazdoor -
15 Bhisti -
2
13. 10 cu m
floor + 1% for each addition Iloor av. 3m ht. as extra Head Mason Mason -
9
over) Mazdoor -
18; Bhisti -
2
Half brick wall (without hoop iron reinforcement)
14 10.sq m Mason -
1.2 Mazddor -
20
Bhisti 0.3
ISHAN'S Quantity Surveying and
146
aluaion
SI.
Description of work Unit Labour in days (8 working hry,
No.
15 -do-do- with H.B. wire netting
10 sq m Mason 1.4 Mazddor 15
Bhisti -0.3
6. Random rubble stone masonry in foundation and plinth 10 cu m Head Mason Mason Io
in lime or cement mortar Mazdoor- 17 5,Bhisti - 1
Polisher -9.8
10 sq m Head mason- Mason -2
Precast terrazzo tiles to floor Bhisti -
0.1:
23 Mazdoor 2;
Polisher-65
Mason -l:
(F) Roofing 10 sq m Head Mason -
at Ist. floor
1Ocm (av.) thick limne terracing -1.9; Bhisti 0.3
24 Mazdoor
Mazdoor (female)- 65
i0 sq m Carpenter - ;
Tile layer
batterns
roofing with
25. Mangalore Tile Mazdoor-3
Blacksmit
10 sq m Carpenter
-
1;
Galvanised iron roofing Mazdoor-2
Corrugated
26.
20 Mason :
Plastering
and pointing 10 sq m Head Mason
(G) brickwork 1.4;
Bhisti
-
0.10
to Mazdoor-
)Finishing
hite washing or colour washing 2 coats with a coat of | 100 sq m Painter- 1: Mazdoor-2
mer coat
m Stone...
..12.5 cu m
5.CoursedRubble per 10 cu. ..4.0 cum
Dry cement mortar..
STone Masonry- 2cu m
Drylime mortar
X 10 cm x 10 cm ...425 noos.
10 sq. m Bricks 20 cm
6.Sing.e brick. fiat soling- per
X 12.7 cm x 7.6 em..320 nos.
Bricks 25.4 cm
X 11.4 em x 7.ó cm..425 nos.
Bricks 22.9 cm
10 cm x 10 ..500 nos.
10 sq. m Bricks 20 cm x cm
3 . 5 cu m
Dry mortar..
148 ISHAN'S Quantity Surveying and Valuatio.
ation
S.
Name of work
Materials
Quantity
No
100 sq. Cement... ..27 bags
8. 20mm thick D.P.C. with per m
cement mortar
..1.8 cu m
Sand..
Water-proofing compound. .27 kg
.. 12.8 sq m
9
C.G.l. sheet roofing per 10 sq. m. G.I. sheet
A.C. sheet
...1.50 sq m
10. A.C. Corrugated sheetroofing per 10 sq. m. |Dry mortar
...1.92 cu m
12mm thick per 100 sq.m.
11. cement plaster ...5.5bags
12. Neat cement punning (abut | per 100 sq. m. Cement
1.5 mm)
|Dry mortar
...0.7 cum
13. Flush pointing in cement per 100 sq. m.
mortar ..10 kg
Stone lime (unslaked)
14. Single coat white-washing to per 100 sq. m.
old work
15. Two coats white-washing on a per 100 sq. m. Stone lime (unslaked) 30 kg
coat of primer to new work
100 sq. Tropic dry distemper
16. Distempering two coats to per m.
19. Primer coat on steel work per 100 sq. m Primer ..5.5 litres
with ready mixed primer
...7.5 litres
20. Primer coat on wood work per 100 sq. m. Primer
with ready mixed primer
21. Painting two coats on new|do- Ready mixed paint ... 12.5 litres
work with ready mixed paint
. 2 litres
22. Water-proofing cement per 10 sq. m. Mixed cement pain
painting two coats to new
plaster to exterior walls
painting with wall per 100 sq. m. .8.1 litres
23 | Spray Priming coat primer
paints on new work including Wall paint
under coat .11 litres
24. Painting with synthetic per 100 sq. m. Enamel paint ...11.6litres
enamel paint on new work|
(excluding primer coat)
25. Varnishing with 7.0 litres
Copal per 100 sq. m. Under coat varnishing
varnish on new work
Copal varnish
| including under coat ..11.6 lires
Analysiso fR a t e s
149
labour. To this add charge and 10% contractor's profit. The total of all these
terial and
material.
1% as water
Let cost of
=B
Let cost of labours A+B
labour and material
Total cost of 1.5
Add 1% water charges
=
(A + B)X 100
10
Add 10% contractor's profit 10A+B)
100
T.15 (A +B)
Grand total = 1.115 (A +B)
item
Rate per unit of the Standard Table
for Rate Analysis
Cost
Qty. or No's
Rate
Particulars Rs. P.
(A) Materials
1. Cement ---=-=*
Total
Sand etc.
(B) Labour:
1 Head Mason
2. Mason Total
3. Mazdoor etc.
and Labour
Total of Material
or
per sq.m.
150 SHAN'S Quantity Surveying and Valuati.
Example 1. Analysis of Rates for Earth work in excavation hard/ordinary soil and filling with a concent
lead and
lift.
) E a r t h work in excavation in foundation in ordinary soil not exceeding 1.5m depth, lead up to 30m
Unit 1 cu.m.
Consider for 10 cu.m.
Total 325-00
32.50
Add 10% contractor's Profit
357.50
357.50
'.Rate per cu.m.
10
= Rs/35.75
(ii) Earth work in excavation of hard soil (unit Im*) consider for 10m
Total 775-00
Add 10% contractor's Profit 77.50
852.50
852.50
Rate per cubic meter
10
= Rs/85.25
ii) Earth work in filling in foundation and print etc. in layers not exceeding 20 cm including dresin
Im).
Consider for 10M*
Total 233-00
Add 10% contractor's Profit 23.30
256.30
256.30
Rate per m=
10
= Rs/25.63
151
alysiso fR a t e s
every additional lead of 30 m beyond the initial lead add labour and for every additiona
Note: Fon
2
nd the initial lift add labour for working are analysis ofrates.
illing)bey
CALCULATION OF QUANTITIES
OF RATES
ANALYSIS OF FOR CONCRETE WORKS AND
3.8
ANALYSIS
(MATERIALS) he f
be taken as 152
cum.
materials may
Calculation of Materials
15.2
Cement= Summation of proportion
:4:8
proportion 1 =30 bags]
Forcement concrete of 15.2 = 1.2 cu-m = 36 bags
[ cu-m
of cement
Cement =
1+4+8
1.2=4.8 cu.m
Sand =4 x
Aggregate
size of aggregate surkhi mortar.
depends upon lime and 2
vol. i.e. 50-55% ballast with 1
Note : Increase in dry 40 m m size
brick
f o u n d a t i o n with
c o n c r e t e in
Lime
Example 1.
Proportion 1: 2:6-unit
- 1 cu.m
concrete
of lime
Consider, 10 c u . m
Calculation of Materials
15.5 =1.73 cu.m (say)
Lime =
1+2+6 =
6 X 1.7= 10.2 cu. m =10 cu.m
Surkhi =2 x unit 1
Brick Ballast
with 40mm gauge approx.)
Lime Concrete
in
Foundation
100, i.e. 1 : 2:6
1. (Proportion-16:32:
1:2
surkhi
(a) With white lime and Rate Cost
Qty or Nos.
P. Rs. P.
Particulars
Rs.
4000.00
400.00 cu m
Materials-
10 cu m
1120.00
guage.. 700.00 cu m
Brick ballast 1 class 40
mm L.6 cu m
1120.00
White lime slaked... 3.2 cu mn
350.00 cu m
6240.00
Surkhi... Total.
152 ISHAN'S Quantity Surveying and Valuation
Labour
Mistri (Head mason).. % no. 160.00 per day 80.00
Mason.. I no. 150.00 per day 150.00
Mazdoor (Beldar)... 12 nos. 80.00 per day 960.00
Boy or woman coolie.. 12 nos. 70.00 per day 840.00
Bhishti (water-man)... 2 nos. 70.00 per day 140.00
Sundries T. and P. etc (Misc., Petty things)... Lump sum
45.00 L.S. 45.00
Total 2215.00
Total of materials and labour 8455.00
Add 1% Water charges 127.00
Add 10% Contractor's profit . 845.00
Grand Total . 9427.00
9427.50 for 10 cu
Rate per cu m= =
Rs. 942.00
m
10