SB CONSULTANT LTD.

Shear Wall at Grid No. (1-A) & (1-B):

Figure-1: New Shear wall-2.

New Shear Wall-2:


From Figure-1:
Moment of Inertia, I= 3,89,60,560 in4 (See Excel sheet for details Calculation).
Factored Dead Load =1436 kip ( Result taken from FEM model)
Factored Live load = 238 kip.
Total load =(1436 +238) kip = 1674 kip. C= 138.5"
Design Moment, M= 20061 kip-ft = (20061 *12) kip-in
Total Area ( A1+A2+A3) = 4178 in2

Stress calculation:
σt = P/A+ M*C/I
= (1674/4178) +(20061*12 *138.5) /3,89,60,560
= 0.401 +0.856
= +1.257 ksi (Compression)

σt = P/A - M*C/I
= (1674/4178) -(20061*12 *138.5) /3,89,60,560
= 0.401- 0.856
= -0.455 ksi (Tension).
Dhaka: Sapno Sargo (9th floor) , 46/C, Asad Avenue, Mohammadpur, Dhaka.
Tel: 01730300473, 01711075652 E-mail: saiful_bari2002@yahoo.com,
sbcl2002@gmail.com
SB CONSULTANT LTD.

Figure-2: Stress Diagram of Wall-2.

Stress at 32" from column end : 1.257/X = 203.4/171.4 (at compression side).
X = 1.059 ksi.
Force at compression end = (1.257 + 1.059)/2 * 32*32 +( 1.059 +0)/2 * 10* 171.4
= 2093 kip.
Stress at 32" from column end: 0.455/X = 73.6/41.6
X = 0.257 ksi ( at tension side).
Force at tension end = (0.455 +0.257)/2 * 32*32 + (0.257 +0)/2 * 10 * 41.6
= 418 kip (Tension)
Steel required at tension side, As = 418/ (0.9 * 60) =7.74 in 2
Provided re-bar = 46.3 in2 is greater than required amount. (OK).

Dhaka: Sapno Sargo (9th floor) , 46/C, Asad Avenue, Mohammadpur, Dhaka.
Tel: 01730300473, 01711075652 E-mail: saiful_bari2002@yahoo.com,
sbcl2002@gmail.com
SB CONSULTANT LTD.
Shear Wall at Grid No. (3-A) & (4-A):

Figure-3: New Shear wall-3.

From Figure-3:
Moment of Inertia, I= 5,78,78,784 in4 (See Excel sheet for details Calculation).
Factored Dead Load =1833 kip ( Result taken from FEM model)
Factored Live load = 381 kip.
Total load =(1833 +381) kip = 2214 kip. C= 180"
Design Moment, M= 18444 kip-ft = (18444 *12) kip-in
Total Area ( A1+A2+A3) = 4272 in2

Stress calculation:
σt = P/A+ M*C/I
= (2214/4272) +(18444*12 *180) /5,78,78,784
= 0.518 +0.688
= +1.206 ksi (Compression)

σt = P/A- M*C/I
= (2214/4272) -(18444*12 *180) /5,78,78,784
= 0.518 -0.688
= -0.17 ksi (Tension)
Dhaka: Sapno Sargo (9th floor) , 46/C, Asad Avenue, Mohammadpur, Dhaka.
Tel: 01730300473, 01711075652 E-mail: saiful_bari2002@yahoo.com,
sbcl2002@gmail.com
SB CONSULTANT LTD.

Figure-4: Stress Diagram of Wall-3.

Stress at 24" from column end : 1.206/X = 315.52/291.52 (at compression side).
X = 1.114 ksi.
Force at compression end = (1.206 + 1.114)/2 * 24*24 +( 1.114 +0)/2 * 10* 291.51
= 2291 kip.
Stress at 24" from column end: 0.175/X = 44.48/20.48
X = 0.081 ksi ( at tension side).
Force at tension end = (0.17 +0.081)/2 * 24*24 + (0.081 +0)/2 * 10 * 20.48
= 81 kip ( Tension)
Steel required at tension side, As = 81/ (0.9 * 60) =1.5 in 2
Provided re-bar = 18.24 in2 is greater than required amount. (OK).

Dhaka: Sapno Sargo (9th floor) , 46/C, Asad Avenue, Mohammadpur, Dhaka.
Tel: 01730300473, 01711075652 E-mail: saiful_bari2002@yahoo.com,
sbcl2002@gmail.com
SB CONSULTANT LTD.

Shear Wall at Grid No. (9-A) & (10-A):

Figure-5: New Shear wall-11.

From Figure-5:
Moment of Inertia, I= 5,78,78,784 in4 (See Excel sheet for details Calculation).
Factored Dead Load =1856 kip ( Result taken from FEM model)
Factored Live load = 442 kip.
Total load =(1856 +442) kip = 2298 kip. C= 180"
Design Moment, M= 14975 kip-ft = (14975 *12) kip-in
Total Area ( A1+A2+A3) = 4272 in2

Dhaka: Sapno Sargo (9th floor) , 46/C, Asad Avenue, Mohammadpur, Dhaka.
Tel: 01730300473, 01711075652 E-mail: saiful_bari2002@yahoo.com,
sbcl2002@gmail.com
SB CONSULTANT LTD.

Stress calculation:
σt = P/A+ M*C/I
= (2298/4272) +(14975*12 *180) /5,78,78,784
= 0.538 +0.559
= +1.097 ksi (Compression)

σt = P/A- M*C/I
= (2298/4272) -(14975*12 *180) /5,78,78,784
= 0.538 -0.559
= -0.021 ksi (Tension)

Figure-6: Stress Diagram of Wall-11.

Stress at 24" from column end: 1.206/X = 315.52/291.52 (at compression side).
X = 1.114 ksi.
Force at compression end = (1.206 + 1.114)/2 * 24*24 +( 1.114 +0)/2 * 10* 291.51
= 2291 kip.
Stress at 24" from column end: 0.175/X = 44.48/20.48 (Tension side)

Dhaka: Sapno Sargo (9th floor) , 46/C, Asad Avenue, Mohammadpur, Dhaka.
Tel: 01730300473, 01711075652 E-mail: saiful_bari2002@yahoo.com,
sbcl2002@gmail.com
SB CONSULTANT LTD.
X = 0.081 ksi ( at tension side).
Force at tension end = (0.17 +0.081)/2 * 24*24 + (0.081 +0)/2 * 10 * 20.48
= 81 kip (Tension)
Steel required at tension side, As = 81/ (0.9 * 60) =1.5 in 2
Provided re-bar = 6.08 in2 is greater than required amount. (OK).

Shear Wall at Grid No. (11-A) & (12-A):

Figure-7: New Shear wall-10.

From Figure-7:
Moment of Inertia, I= 4,57,10,604 in4 (See Excel sheet for details Calculation).
Factored Dead Load =1726 kip ( Result taken from FEM model)
Factored Live load = 435 kip.
Total load =(1726 +435) kip = 2161 kip. C= 165"
Design Moment, M= 12444 kip-ft = (12444 *12) kip-in
Total Area ( A1+A2+A3) = 3972 in2

Dhaka: Sapno Sargo (9th floor) , 46/C, Asad Avenue, Mohammadpur, Dhaka.
Tel: 01730300473, 01711075652 E-mail: saiful_bari2002@yahoo.com,
sbcl2002@gmail.com
SB CONSULTANT LTD.
Stress calculation:
σt = P/A+ M*C/I
= (2161/3972) +(12444*12 *165) /45710604
= 0.544 +0.539
= +1.083 ksi (Compression).

Stress calculation:
σt = P/A- M*C/I
= (2161/3972) -(12444*12 *165) /45710604
= 0.544 -0.539
= +0.005 ksi (Compression).

Shear Wall at Grid No. (1-E) & (1-F):

Figure-8: New Shear wall-1.

From Figure-8:
Moment of Inertia, I= 2,73,70,224 in4 (See Excel sheet for details Calculation).
Factored Dead Load =1319 kip ( Result taken from FEM model)
Factored Live load = 272 kip.
Dhaka: Sapno Sargo (9th floor) , 46/C, Asad Avenue, Mohammadpur, Dhaka.
Tel: 01730300473, 01711075652 E-mail: saiful_bari2002@yahoo.com,
sbcl2002@gmail.com
SB CONSULTANT LTD.
Total load =(1319 +272) kip = 1591 kip. C= 138.5"
Design Moment, M= 16592 kip-ft = (16592 *12) kip-in
Total Area ( A1+A2+A3) = 3410 in2

Stress calculation:
σt = P/A+ M*C/I
= (1591/3410) +(16592*12 *138.5) /27370224
= 0.467 +1.007
= +1.447 ksi (Compression).

Stress calculation:
σt = P/A- M*C/I
= (1591/3410) -(16592*12 *138.5) /27370224
= 0.467 -1.007
= -0.540 ksi (Tension).

Figure-9: Stress Diagram of Wall-1.

Stress at 32" from column end: 1.447/X = 201.72/169.72 (at compression side).
X = 1.214 ksi.
Force at compression end = (1.447 + 1.214)/2 * 32*20 +( 1.214 +0)/2 * 10* 169.72
= 1882 kip.
Stress at 32" from column end: 0.54/X = 75.25/43.25 (Tension side)

Dhaka: Sapno Sargo (9th floor) , 46/C, Asad Avenue, Mohammadpur, Dhaka.
Tel: 01730300473, 01711075652 E-mail: saiful_bari2002@yahoo.com,
sbcl2002@gmail.com
SB CONSULTANT LTD.
X = 0.31 ksi ( at tension side).
Force at tension end = (0.54 +0.31)/2 * 32*20 + (0.31 +0)/2 * 10 * 43.25
= 339 kip (Tension)
Steel required at tension side, As = 339/ (0.9 * 60) =6.28 in 2
Provided re-bar = 33.6 in2 is greater than required amount. (OK).

Shear Wall at Grid No. (7-H) & (6a-H):

Figure-10: New Shear wall-15.

From Figure-10:
Moment of Inertia, I= 3, 74, 25,212 in4 (See Excel sheet for details Calculation).
Factored Dead Load =353 kip (Result taken from FEM model)
Factored Live load = 141 kip.
Total load =(353 +141) kip = 494 kip. C= 149.2"
Design Moment, M= 8760 kip-ft = (8760 *12) kip-in
Total Area (A1+A2+A3) = 3970 in2

Dhaka: Sapno Sargo (9th floor) , 46/C, Asad Avenue, Mohammadpur, Dhaka.
Tel: 01730300473, 01711075652 E-mail: saiful_bari2002@yahoo.com,
sbcl2002@gmail.com
SB CONSULTANT LTD.
Stress calculation:
σt = P/A+ M*C/I
= (494/3970) +(8760*12 *149.2) /37425202
= 0.124 +0.419
= +0.543 ksi (Compression).

Stress calculation:
σt = P/A- M*C/I
= (494/3970) -(8760*12 *149.2) /37425202
= 0.124 -0.419
= -0.295 ksi (Tension).

Figure-11: Stress Diagram of Wall-15.

Stress at 32" from column end : 0.543/X = 183.4/151.4 (at compression side).
X = 0.448 ksi.
Force at compression end = (0.543 + 0.448)/2 * 32*32 +( 0.448 +0)/2 * 10* 151.4
= 845 kip.
Stress at 32" from column end: 0.295/X = 99.6/67.6 (Tension side)
X = 0.20 ksi ( at tension side).
Force at tension end = (0.20 +0.295)/2 * 32*32 + (0.20 +0)/2 * 10 * 67.6
= 321 kip ( Tension)
Steel required at tension side, As = 321/ (0.9 * 60) =6.13 in 2
Provided re-bar = 21.31 in2 is greater than required amount. (OK).

Dhaka: Sapno Sargo (9th floor) , 46/C, Asad Avenue, Mohammadpur, Dhaka.
Tel: 01730300473, 01711075652 E-mail: saiful_bari2002@yahoo.com,
sbcl2002@gmail.com
SB CONSULTANT LTD.

Shear Wall at Grid No. (11-H) & (12-H):

Figure-12: New Shear wall-14.

From Figure-12:
Moment of Inertia, I= 6,14,52,235 in4 (See Excel sheet for details Calculation).
Factored Dead Load =495 kip ( Result taken from FEM model)
Factored Live load = 145 kip.
Total load =(495 +145) kip = 640 kip. C= 169"
Design Moment, M= 10815 kip-ft = (10815*12) kip-in
Total Area ( A1+A2+A3) = 4568 in2

Stress calculation:
σt = P/A+ M*C/I
= (640/4568) +(10815*12 *169) /61452235
= 0.140 +0.347
= +0.497 ksi (Compression).

Dhaka: Sapno Sargo (9th floor) , 46/C, Asad Avenue, Mohammadpur, Dhaka.
Tel: 01730300473, 01711075652 E-mail: saiful_bari2002@yahoo.com,
sbcl2002@gmail.com
SB CONSULTANT LTD.

Stress calculation:
σt = P/A- M*C/I
= (640/4568) -(10815*12 *169) /61452235
= 0.140 -0.347
= -0.234 ksi (Tension).

Figure-13: Stress Diagram of Wall-14.

Stress at 32" from column end : 0.497/X = 229.8/197.8 (at compression side).
X = 0.428 ksi.
Force at compression end = (0.497 + 0.428)/2 * 32*32 +( 0.428 +0)/2 * 10* 197.8
= 897 kip.
Stress at 32" from column end: 0.234/X = 108.2/76.2 (Tension side)
X = 0.17 ksi ( at tension side).
Force at tension end = (0.17 +0.234)/2 * 32*32 + (0.17 +0)/2 * 10 * 76.2
= 207 kip ( Tension)
Steel required at tension side, As = 207/ (0.9 * 60) =3.83 in 2
Provided re-bar = 22.78 in2 is greater than required amount. (OK).

Dhaka: Sapno Sargo (9th floor) , 46/C, Asad Avenue, Mohammadpur, Dhaka.
Tel: 01730300473, 01711075652 E-mail: saiful_bari2002@yahoo.com,
sbcl2002@gmail.com
SB CONSULTANT LTD.

Shear Wall at Grid No. (D-H) & (C-H):

Figure-14: New Shear wall-12.

From Figure-14:
Moment of Inertia, I= 2,63,37,380 in4 (See Excel sheet for details Calculation).
Factored Dead Load =1404 kip ( Result taken from FEM model)
Factored Live load = 337 kip.
Total load =(1404 +337) kip = 1741 kip. C= 134.5"
Design Moment, M= 11784 kip-ft = (11784*12) kip-in
Total Area ( A1+A2+A3) = 3362 in2

Stress calculation:
σt = P/A+ M*C/I
= (1741/3362) +(11784*12 *134.5) /26337380
Dhaka: Sapno Sargo (9th floor) , 46/C, Asad Avenue, Mohammadpur, Dhaka.
Tel: 01730300473, 01711075652 E-mail: saiful_bari2002@yahoo.com,
sbcl2002@gmail.com
SB CONSULTANT LTD.
= 0.518 +0.722
= +1.24 ksi (Compression).

Stress calculation:
σt = P/A- M*C/I
= (1741/3362) -(11784*12 *134.5) /26337380
= 0.518 -0.722
= -0.204 ksi (Tension).

Figure-15: Stress Diagram of Wall-12.

Stress at 24" from column end : 1.24/X = 231/205 (at compression side).
X = 1.1 ksi.
Force at compression end = (1.24 + 1.2)/2 * 24*24 +( 1.1 +0)/2 * 10* 205
= 1800 kip.
Stress at 24" from column end: 0.204/X = 38/14 (Tension side)
X = 0.075 ksi ( at tension side).
Force at tension end = (0.075 +0.204)/2 * 24*24 + (0.075 +0)/2 * 10 * 14
= 85 kip ( Tension)
Steel required at tension side, As = 85/ (0.9 * 60) =1.57 in 2
Provided re-bar = 16.44 in2 is greater than required amount. (OK).

Dhaka: Sapno Sargo (9th floor) , 46/C, Asad Avenue, Mohammadpur, Dhaka.
Tel: 01730300473, 01711075652 E-mail: saiful_bari2002@yahoo.com,
sbcl2002@gmail.com
SB CONSULTANT LTD.

Limitations & Assumptions of the Report:


 All the footings could not be inspected
 Reinforcement of all the floors beams could not be ensured by ferro-scanner.
 Slab reinforcement was inspected at some portion of slab by breaking the slab at that
portion.
 Ferro scanning was performed at some points of the slab.
 Core samples were taken from columns.
 Yield strength of rebar 60 ksi. (See test report-Annexure -B).