Professional Documents
Culture Documents
Cvsadt BLN 12 Ok
Cvsadt BLN 12 Ok
HARGA SATUAN
NO JENIS MATERIAL SAT
( Rp )
1 2 3 4
I. URAIAN BAHAN
A PASIR, BATU DAN SEMEN
1. Pasir pasang M³ 270,000.00
2. Pasir beton M³ 270,000.00
3. Pasir urug M³ 210,000.00
4. Sirtu M³ 175,000.00
5. Tanah merah M³ 90,000.00
6. Batu belah 15/20 M³ 215,000.00
7. Batu pecah/split 1/2 M³ 330,000.00
8. Batu Gunung M³ 215,000.00
9. Bata merah BH 1,000.00
10. Batu alam M² 210,000.00
11. Paving Blok k- 300 T. 8 cm M² 175,000.00
12. Roster 10 x 20 cm BH 29,000.00
13. Semen portland KG 2,300.00
14. Semen warna/putih KG 12,500.00
B BAHAN KAYU
1. Kayu Balok Kls I ( Buluang ) M³ 6,500,000.00
Kayu Balok Kls I ( jati ) M³ 6,500,000.00
1 2 3 4
11. Sekrup gypsum BH 75.00
12. Compound gypsum 20kg/zak 78,000.00
13. Compound GRC 20kg/zak 78,000.00
14. Textile tape ROLL 7,500.00
15. Alkasit KG 7,500.00
D BAHAN BESI
1. Besi beton polos KG 17,000.00
2. Kawat beton KG 35,000.00
3. Kawat Harmonika M2 30,000.00
4. Kawat duri (10kg/60m/rol) KG 35,000.00
5. Kawat Las listrik KG 32,500.00
6. Besi pelat strip KG 32,000.00
7. Besi Siku KG 15,000.00
8. Skrup fixer BH 1,000.00
9. Sealant BH 37,500.00
10. Profil kaca TUBE 8,500.00
11. Profil Allumunium Kusen M' 115,000.00
12. Profil Allumunium Daun Pintu M' 125,000.00
13. Besi IWF 150 x 75 x 5 x 7 mm KG 13,200.00
14. Besi IWF 125x60x6x8 mm KG 12,500.00
15. Besi IWF 198 x 12 m KG 12,500.00
16. Besi IWF 248 x 12 m KG 12,500.00
17. Besi kanal C 150x50x20x3.2 mm KG 12,500.00
18. Besi Kanal C 125x50x20x3.2 mm KG 12,500.00
19. Besi Plat 10 mm.4'.8' KG 12,500.00
20. Besi pengikat kuda2 dia 16 mm KG 12,500.00
21. Besi pengikat gording dia 10 mm KG 12,500.00
22. Angkur baut 19 mm x 60 cm KG 50,000.00
23. Plat 12 mm KG 12,500.00
24. Besi Plat 9 mm KG 12,500.00
25. Besi Plat 6 mm KG 12,500.00
26. Besi Plat 3 mm KG 12,500.00
F BAHAN KERAMIK
1. Ubin keramik 40 x 40 cm KW 1 Asia Tile 15,166.67
2. Ubin keramik 40 x 40 cm KW 1 motif BH 15,500.00
3. Ubin keramik 20 x 20 cm KW 1 BH 5,616.00
4. Ubin keramik 20 x 25 cm KW 1 BH 7,500.00
5. Plint keramik 10x30 cm BH 4,500.00
6. lantai Granito 60 x 60 cm BH 115,000.00
1 2 3 4
12. Kuas BH 12,500.00
13. Kuas Roll BH 30,000.00
14. Lem kayu KG 32,500.00
15. Cumoir Water Proofing KG 35,000.00
16. Bak Cat BH 15,000.00
H PAKU
1. Paku biasa 2"-5" KG 32,000.00
2. Paku biasa 1/2"- 1" KG 42,500.00
3. Sekrup 6x1-1,5 KG 200.00
4. Paku beton KG 35,000.00
5. Paku asbes BH 150.00
6. Paku seng KG 35,000.00
I BAHAN PIPA
1. Pipa galvanis dia 2" M' 75,000.00
2. Pipa galvanis dia 3" M' 14,500.00
3. Pipa galvanis dia 4" M' 245,000.00
4. Pipa PVC dia 1/2" AW M' 10,200.00
5. Pipa PVC dia 3/4" AW M' 11,000.00
6. Pipa PVC dia 1" AW M' 23,000.00
7. Pipa PVC dia 1 ½" AW M' 52,500.00
8. Pipa PVC dia 2" AW M' 57,500.00
9. Pipa PVC dia 2" D M' 18,000.00
10. Pipa PVC dia 2 ½" AW M' 62,500.00
11. Pipa PVC dia 3" AW M' 65,000.00
12. Pipa PVC dia 3" D M' 25,000.00
13. Pipa PVC dia 4" AW M' 80,000.00
14. Pipa PVC dia 4" D M' 37,500.00
15. Buis beton 1/2 dia 20 panj. 100 cm BH 51,000.00
K BAHAN SANITASI
1. Kloset duduk standart BH 3,750,000.00
2. Kloset jongkok standart BH 220,000.00
3. Urinoir BH 775,000.00
4. Wastafel BH 525,000.00
5. Bak cuci stainless steel BH 280,000.00
6. Water drain + asesoris BH 95,000.00
7. Kran air BH 23,000.00
8. Kran Shower BH 500,000.00
9. Seal tape BH 5,500.00
10. Floor drain BH 45,000.00
L BAHAN KACA
- Kaca 5 mm M² 195,000.00
1 2 3 4
8. Tee dos BH 2,000.00
9. Inbow doos BH 2,000.00
10. Saklar tunggal BH 27,500.00
11. Saklar seri BH 32,500.00
12. Stop kontak BH 17,500.00
13. Lampu BH 55,000.00
14. pipa listrik Btg 4,150.00
15. Fitting Btg 17,000.00
16. Sock BH 2,500.00
17. Klem conduit BH 1,500.00
18. Lastdop BH 1,000.00
19. Pleksiblle Pipe M' 2,500.00
20. Elbow BH 500.00
N LAIN-LAIN
1. Sewa mesin las HR 450,000.00
2. Sewa mesin gilas HR 2,100,000.00
3. Solar LTR 12,500.00
4. Minyak Pelumas LTR 55,000.00
5. Beton K-275 slump 12 M³ 1,500,000.00
6. Plastik bening M³ 5,000.00
7. Aspal silent KG 3,500.00
8. Pompa air listrik Shimizu 125 W UNIT 710,000.00
II UPAH TENAGA
1. Pekerja OH 125,000.00
2. Tukang kayu OH 145,000.00
3. Tukang batu OH 145,000.00
4. Tukang besi OH 145,000.00
5. Tukang las OH 145,000.00
6. Tukang cat OH 145,000.00
7. Tukang alumunium OH 145,000.00
8. Tukang gypsum OH 145,000.00
9. Tukang pipa OH 145,000.00
10. Instalator OH 145,000.00
11. Tukang Aspal OH 145,000.00
12. Kepala tukang OH 150,000.00
13. Mandor OH 165,000.00
5
Harga bahan:
-
- 765,442.00
- Profil Allumunium Rangka Natural m' 4.4000 125,000.00 550,000.00
Kaca 5 mm m2 1.0500 195,000.00 204,750.00
UpahSealant tube 0.2700 39,600.00 10,692.00
-
8
- 22,790.00
- Pekerja Oh 0.0850 125,000.00 10,625.00
- Kepala tukang Oh 0.0850 125,000.00 10,625.00
Kepala tukang Oh 0.0080 125,000.00 1,000.00
Mandor Oh 0.0040 135,000.00 540.00
Jumlah Total 788,232.00
Jumlah Total + jasa 10% 867,055.20
G PEKERJAAN KONSTRUKSI LANGIT-LANGIT/PLAFON DAN PENUTUP
1. List Plafon kayu profil tiap 1m'
Harga bahan:
- 11,975
- Kayu list profil m' 1.0500 11,000.00 11,550.00
Paku biasa 1/2"- 1" kg 0.0100 42,500.00 425.00
Upah tenaga:
- 14,745.00
- Pekerja Oh 0.0500 125,000.00 6,250.00
- Tukang kayu Oh 0.0500 145,000.00 7,250.00
- Kepala tukang Oh 0.0050 150,000.00 750.00
Mandor Oh 0.0030 165,000.00 495.00
Jumlah Total 26,720.00
2. List Plafon Gypsum tiap 1m' Jumlah Total + jasa 10% 29,392.00
Harga bahan:
- 31,356.25
- List profil cornice gypsum lebih dari 10 cm m' 1.1000 26,000.00 28,600.00
- Compound gypsum zak 0.0350 78,000.00 2,730.00
Alkasit kg 0.0035 7,500.00 26.25
Upah tenaga:
- 14,745.00
- Pekerja Oh 0.0500 125,000.00 6,250.00
- Tukang kayu Oh 0.0500 145,000.00 7,250.00
- Kepala tukang Oh 0.0050 150,000.00 750.00
Mandor Oh 0.0030 165,000.00 495.00
Jumlah Total 46,101.25
3. Penutup plafon Calciboard 4 mm lengkap dgn rangka hollow tebal 0.Jumlah Total + jasa 10% 50,711.38
Harga bahan:
- 72,000.50
- Paku peluru ramset bh 0.3900 100.00 39.00
- Hollow 4x4 cm tbl 0.6 mm btg 0.4590 41,000.00 18,819.00
- Hollow 2x4 cm tbl 0.6 mm btg 0.4310 32,500.00 14,007.50
- Paku beton kg 0.0100 35,000.00 350.00
- Sekrup 6x1-1,5 bh 14.0000 75.00 1,050.00
- GRC-board 120x240 cm 4 mm lbr 0.3640 92,500.00 33,670.00
- Sekrup gypsum bh 21.0000 75.00 1,575.00
- Textile tape rol 0.0240 7,500.00 180.00
- Compound GRC zak 0.0200 78,000.00 1,560.00
Amplas lbr 0.1000 7,500.00 750.00
Upah tenaga:
- 84,245.00
- Pekerja Oh 0.2600 125,000.00 32,500.00
- Tukang alumunium Oh 0.2600 145,000.00 37,700.00
- Tukang gypsum Oh 0.0500 145,000.00 7,250.00
- Kepala tukang Oh 0.0310 150,000.00 4,650.00
Mandor Oh 0.0130 165,000.00 2,145.00
Jumlah Total 156,245.50
Jumlah Total + jasa 10% 171,870.05
4. Penutup plafon Gypsumboard 9 mm lengkap dgn rangka hollow tebal 0.5 mm / tiap 1 m²
Harga bahan:
- 76,550.50
- Paku peluru ramset bh 0.3900 100.00 39.00
- Hollow 4x4 cm tbl 0.6 mm btg 0.4590 41,000.00 18,819.00
- Hollow 2x4 cm tbl 0.6 mm btg 0.4310 32,500.00 14,007.50
- Paku beton kg 0.0100 35,000.00 350.00
- Sekrup 6x1-1,5 bh 14.0000 75.00 1,050.00
- Gypsumboard 120x240 cm 9 mm lbr 0.3640 105,000.00 38,220.00
- Sekrup gypsum bh 21.0000 75.00 1,575.00
- Textile tape rol 0.0240 7,500.00 180.00
- Compound gypsum zak 0.0200 78,000.00 1,560.00
Amplas lbr 0.1000 7,500.00 750.00
Upah tenaga:
- 84,245.00
- Pekerja Oh 0.2600 125,000.00 32,500.00
- Tukang alumunium Oh 0.2600 145,000.00 37,700.00
- Tukang gypsum Oh 0.0500 145,000.00 7,250.00
- Kepala tukang Oh 0.0310 150,000.00 4,650.00
Mandor Oh 0.0130 165,000.00 2,145.00
Jumlah Total 160,795.50
Jumlah Total + jasa 10% 176,875.05
H PEKERJAAN KONSTRUKSI ATAP KAYU
4. Pasang lisplank (2 x 20 x 2) cm Kayu Kls I tiap 1m'
Harga bahan:
- 65,720.00
- Kayu Kls I m³ 0.0088 7,250,000.00 63,800.00
Paku biasa 2"-5" kg 0.0600 32,000.00 1,920.00
Upah tenaga:
- 29,325.00
- Pekerja Oh 0.1000 125,000.00 12,500.00
- Tukang kayu Oh 0.1000 145,000.00 14,500.00
- Kepala tukang Oh 0.0100 150,000.00 1,500.00
9
Mandor Oh 0.0050 165,000.00 825.00
Jumlah Total 95,045.00
I Jumlah Total + jasa 10% 104,549.50
1.
PEKERJAAN BETON
Beton Non Struktur 1Pc : 3Ps : 5Kr - untuk rabatan/ beton tumbuk tiap 1m³
Harga bahan:
- 928,900.00
- Semen portland kg 218.0000 2,300.00 501,400.00
- Pasir beton m³ 0.5200 270,000.00 140,400.00
Batu pecah/split 2/3 m³ 0.8700 330,000.00 287,100.00
Upah tenaga:
- 259,450.00
- Pekerja Oh 1.6500 125,000.00 206,250.00
- Tukang batu Oh 0.2500 145,000.00 36,250.00
- Kepala tukang Oh 0.0250 150,000.00 3,750.00
Mandor Oh 0.0800 165,000.00 13,200.00
Jumlah Total 1,188,350.00
Jumlah Total + jasa 10% 1,307,185.00
2. Beton Struktur K-175 (1Pc : 2,5Ps : 3,5Kr) tiap 1m³
Harga bahan:
- 1,075,230.00
- Semen portland kg 300.0000 2,300.00 690,000.00
- Pasir beton m³ 0.5260 270,000.00 142,020.00
Batu pecah/split 2/3 m³ 0.7370 330,000.00 243,210.00
Upah tenaga:
- 259,450.00
- Pekerja Oh 1.6500 125,000.00 206,250.00
- Tukang batu Oh 0.2500 145,000.00 36,250.00
- Kepala tukang Oh 0.0250 150,000.00 3,750.00
Mandor Oh 0.0800 165,000.00 13,200.00
Jumlah Total 1,334,680.00
3. Beton Struktur K-225 (1Pc : 2Ps : 3Kr) tiap 1m³ Jumlah Total + jasa 10% 1,468,148.00
Harga bahan:
- 1,175,860.00
- Semen portland kg 350.0000 2,300.00 805,000.00
- Pasir beton m³ 0.4850 270,000.00 130,950.00
Batu pecah/split 2/3 m³ 0.7270 330,000.00 239,910.00
Upah tenaga:
- 322,500.00
- Pekerja Oh 2.0000 125,000.00 250,000.00
- Tukang batu Oh 0.3500 145,000.00 50,750.00
- Kepala tukang Oh 0.0350 150,000.00 5,250.00
Mandor Oh 0.1000 165,000.00 16,500.00
Jumlah Total 1,498,360.00
4. Jumlah Total + jasa 10% 1,648,196.00
Upah tenaga:
- 2,061.00
- Pekerja Oh 0.0070 125,000.00 875.00
- Tukang besi Oh 0.0070 145,000.00 1,015.00
- Kepala tukang Oh 0.0007 150,000.00 105.00
Mandor Oh 0.0004 165,000.00 66.00
Jumlah Total 20,436.00
Jumlah Total + jasa 10% 22,479.60
9. Pasang bekisting untuk pondasi 1 m²
Harga bahan:
- 82,100.00
- Kayu Balok Kls III m³ 0.0400 1,800,000.00 72,000.00
- Paku biasa 2"-5" kg 0.3000 32,000.00 9,600.00
Minyak bekisting Liter 0.1000 5,000.00 500.00
Upah tenaga:
- 110,890.00
- Pekerja Oh 0.5200 125,000.00 65,000.00
- Tukang kayu Oh 0.2600 145,000.00 37,700.00
- Kepala tukang Oh 0.0260 150,000.00 3,900.00
Mandor Oh 0.0260 165,000.00 4,290.00
Jumlah Total 192,990.00
Jumlah Total + jasa 10% 212,289.00
10. Pasang bekisting untuk sloof 1 m²
Harga bahan:
- 91,100.00
- Kayu Balok Kls III m³ 0.0450 1,800,000.00 81,000.00
- Paku biasa 2"-5" kg 0.3000 32,000.00 9,600.00
Minyak bekisting Liter 0.1000 5,000.00 500.00
Upah tenaga:
- 110,890.00
- Pekerja Oh 0.5200 125,000.00 65,000.00
- Tukang kayu Oh 0.2600 145,000.00 37,700.00
- Kepala tukang Oh 0.0260 150,000.00 3,900.00
Mandor Oh 0.0260 165,000.00 4,290.00
Jumlah Total 201,990.00
Jumlah Total + jasa 10% 222,189.00
11. Pasang bekisting untuk kolom 1 m²
Harga bahan:
- 229,300.00
- Kayu Balok Kls III m³ 0.0400 1,800,000.00 72,000.00
- Paku biasa 2"-5" kg 0.4000 32,000.00 12,800.00
- Minyak bekisting lt 0.2000 5,000.00 1,000.00
- Kayu Balok Kls II m³ 0.0150 3,500,000.00 52,500.00
Triplek 4x8 ft 9 mm lbr 0.3500 260,000.00 91,000.00
Upah tenaga:
- 140,745.00
- Pekerja Oh 0.6600 125,000.00 82,500.00
- Tukang kayu Oh 0.3300 145,000.00 47,850.00
- Kepala tukang Oh 0.0330 150,000.00 4,950.00
Mandor Oh 0.0330 165,000.00 5,445.00
Jumlah Total 370,045.00
12. Jumlah Total + jasa 10% 407,049.50
Upah tenaga:
- 1,027,595.00
- Pekerja Oh 5.6500 125,000.00 706,250.00
- Tukang kayu Oh 1.5600 145,000.00 226,200.00
- Kepala tukang Oh 0.3230 150,000.00 48,450.00
Mandor Oh 0.2830 165,000.00 46,695.00
Jumlah Total 1,607,395.00
Jumlah Total + jasa 10% 1,768,134.50
Upah tenaga:
- 31,090.00
- Pekerja Oh 0.15 125,000.00 18,750.00
- Tukang besi Oh 0.07 145,000.00 10,150.00
- Kepala tukang Oh 0.008 150,000.00 1,200.00
Mandor Oh 0.006 165,000.00 990.00
5. Jumlah Total 81,708.00
Jumlah Total + jasa 10% 89,878.80
Pasang talang datar (jurai dalam), seng BJLS 28 (0,28 mm) tiap 1m'
Harga bahan:
- 85,235.00
- Seng plat 3x6 ft BJLS 28 (0,28 mm) lbr 0.5000 65,000.00 1,235.00
- Paku biasa 1/2"- 1" kg 0.0150 42,500.00 21,250.00
- Kayu Papan Kls II m3 0.0190 3,500,000.00 52,500.00
Cat meni besi kg 0.2500 41,000.00 10,250.00
Upah tenaga: 122
- 66,956.25
- Pekerja Oh 0.0400 125,000.00 5,000.00 178
- Tukang kayu Oh 0.4000 145,000.00 58,000.00
- Kepala tukang Oh 0.0250 150,000.00 3,750.00 160.39
Mandor Oh 0.0013 165,000.00 206.25
8. Jumlah Total 152,191.25
Jumlah Total + jasa 10% 167,410.38
Pasang Roofmesh dan alumunium foil tiap 1m² 135
Harga bahan:
- 37,800.00 122
- Roofmesh (5 x 5) m² 1.05 15,000 15,750.00
Allumunium foil m² 1.05 21,000 22,050.00 108
Upah tenaga:
- 28,070.00 227.4
- Pekerja Oh 0.15 125,000 18,750.00
- Tukang besi Oh 0.05 145,000 7,250.00 171.64
- Kepala tukang Oh 0.005 150,000 750.00
Mandor Oh 0.008 165,000 1,320.00 97.28
K Jumlah 65,870.00
1. Harga Satuan 72,457.00 130.13
PEKERJAAN SANITASI
Memasang 1 buah kloset jongkok
12
Harga bahan:
- 236,500.00
- Kloset jongkok bh 1.0000 220,000.00 220,000.00
- Semen portland kg 6.0000 2,300.00 13,800.00
Pasir pasang m³ 0.0100 270,000.00 2,700.00
Upah tenaga: 157
- 391,400.00
- Pekerja Oh 1.0000 125,000.00 125,000.00 209
- Tukang batu Oh 1.5000 145,000.00 217,500.00
- Kepala tukang Oh 0.1500 150,000.00 22,500.00 132.6
Mandor Oh 0.1600 165,000.00 26,400.00
3. Jumlah Total 627,900.00
Jumlah Total + jasa 10% 690,690.00 225.5
Memasang 1 buah kloset duduk 240.5
Harga bahan:
- 3,766,500.00 118
- Kloset duduk bh 1.0000 3,750,000.00 3,750,000.00
- Semen portland kg 6.0000 2,300.00 13,800.00 178.8
Pasir pasang m³ 0.0100 270,000.00 2,700.00
141.29
Upah tenaga:
- 391,400.00
- Pekerja Oh 1.0000 125,000.00 125,000.00
- Tukang batu Oh 1.5000 145,000.00 217,500.00 174
- Kepala tukang Oh 0.1500 150,000.00 22,500.00
Mandor Oh 0.1600 165,000.00 26,400.00
Jumlah Total 4,157,900.00
Memasang 1 buah wastafel Jumlah Total + jasa 10% 4,573,690.00
Harga bahan: 66.2
- 604,500.00
- Wastafel bh 1.0000 525,000.00 525,000.00 99.22
- Perlengkapan (12% harga wastafel) % 12.0000 525,000.00 63,000.00
- Semen portland kg 6.0000 2,300.00 13,800.00
Pasir pasang m³ 0.0100 270,000.00 2,700.00
Upah tenaga:
- 399,250.00
- Pekerja Oh 1.2000 125,000.00 150,000.00
- Tukang batu Oh 1.4500 145,000.00 210,250.00
- Kepala tukang Oh 0.1500 150,000.00 22,500.00
Mandor Oh 0.1000 165,000.00 16,500.00
4. Jumlah Total 1,003,750.00
Jumlah Total + jasa 10% 1,104,125.00
Memasang pipa PVC tipe AW dia 1/2" tiap m'
Harga bahan:
- 15,810.00
- Pipa PVC dia 1/2" AW m' 1.2000 10,200.00 12,240.00
Perlengkapan (35% harga pipa) % 35.0000 10,200.00 3,570.00
Upah tenaga:
- 14,397.00
- Pekerja Oh 0.0360 125,000.00 4,500.00
- Tukang pipa Oh 0.0600 145,000.00 8,700.00
- Kepala tukang Oh 0.0060 150,000.00 900.00
Mandor Oh 0.0018 165,000.00 297.00
5. Jumlah Total 30,207.00
Jumlah Total + jasa 10% 33,227.70
Memasang pipa PVC tipe AW dia 3/4" tiap m'
Harga bahan:
- 17,050.00
- Pipa PVC dia 3/4" AW m' 1.2000 11,000.00 13,200.00
Perlengkapan (35% harga pipa) % 35.0000 11,000.00 3,850.00
Upah tenaga:
- 14,397.00
- Pekerja Oh 0.0360 125,000.00 4,500.00
- Tukang pipa Oh 0.0600 145,000.00 8,700.00
- Kepala tukang Oh 0.0060 150,000.00 900.00
Mandor Oh 0.0018 165,000.00 297.00
6. Jumlah Total 31,447.00
Jumlah Total + jasa 10% 34,591.70
Memasang pipa PVC tipe AW dia 1" tiap m'
Harga bahan:
- 35,650.00
- Pipa PVC dia 1" AW m' 1.2000 23,000.00 27,600.00
Perlengkapan (35% harga pipa) % 35.0000 23,000.00 8,050.00
Upah tenaga:
- 14,397.00
- Pekerja Oh 0.0360 125,000.00 4,500.00
- Tukang pasang pipa Oh 0.0600 145,000.00 8,700.00
- Kepala tukang Oh 0.0060 150,000.00 900.00
Mandor Oh 0.0018 165,000.00 297.00
7. Jumlah Total 50,047.00
Jumlah Total + jasa 10% 55,051.70
Memasang pipa PVC tipe AW dia 1 ½" tiap m'
Harga bahan:
- 81,375.00
- Pipa PVC dia 1 ½" AW m' 1.2000 52,500.00 63,000.00
Perlengkapan (35% harga pipa) % 35.0000 52,500.00 18,375.00
Upah tenaga:
- 14,397.00
13
- Pekerja Oh 0.0360 125,000.00 4,500.00
- Tukang pasang pipa Oh 0.0600 145,000.00 8,700.00
- Kepala tukang Oh 0.0060 150,000.00 900.00
Mandor Oh 0.0018 165,000.00 297.00
8. Jumlah Total 95,772.00
Jumlah Total + jasa 10% 105,349.20
Memasang pipa PVC tipe AW dia 2" tiap m'
Harga bahan:
- 89,125.00
- Pipa PVC dia 2" AW m' 1.2000 57,500.00 69,000.00
Perlengkapan (35% harga pipa) % 35.0000 57,500.00 20,125.00
Upah tenaga:
- 21,595.50
- Pekerja Oh 0.0540 125,000.00 6,750.00
- Tukang pasang pipa Oh 0.0900 145,000.00 13,050.00
- Kepala tukang Oh 0.0090 150,000.00 1,350.00
Mandor Oh 0.0027 165,000.00 445.50
9. Jumlah Total 110,720.50
Jumlah Total + jasa 10% 121,792.55
Memasang pipa PVC tipe AW dia 2 ½" tiap m'
Harga bahan:
- 96,875.00
- Pipa PVC dia 2 ½" AW m' 1.2000 62,500.00 75,000.00
Perlengkapan (35% harga pipa) % 35.0000 62,500.00 21,875.00
Upah tenaga:
- 14,129.70
- Pekerja Oh 0.0360 125,000.00 4,500.00
- Tukang pasang pipa Oh 0.0600 145,000.00 8,700.00
- Kepala tukang Oh 0.0060 150,000.00 900.00
Mandor Oh 0.0002 165,000.00 29.70
10. Jumlah Total 111,004.70
Jumlah Total + jasa 10% 122,105.17
Memasang pipa PVC tipe AW dia 3" cm tiap m'
Harga bahan:
- 100,750.00
- Pipa PVC dia 3" AW m' 1.2000 65,000.00 78,000.00
Perlengkapan (35% harga pipa) % 35.0000 65,000.00 22,750.00
Upah tenaga:
- 32,402
- Pekerja Oh 0.0810 125,000.00 10,125.00
- Tukang pasang pipa Oh 0.1350 145,000.00 19,575.00
- Kepala tukang Oh 0.0135 150,000.00 2,025.00
Mandor Oh 0.0041 165,000.00 676.50
11. Jumlah Total 133,151.50
Jumlah Total + jasa 10% 146,466.65
Memasang pipa PVC tipe AW dia 4" tiap m'
Harga bahan:
- 124,000.00
- Pipa PVC dia 4" AW m' 1.2000 80,000.00 96,000.00
Perlengkapan (35% harga pipa) % 35.0000 80,000.00 28,000.00
Upah tenaga:
- 32,401.50
- Pekerja Oh 0.0810 125,000.00 10,125.00
- Tukang pasang pipa Oh 0.1350 145,000.00 19,575.00
- Kepala tukang Oh 0.0135 150,000.00 2,025.00
Mandor Oh 0.0041 165,000.00 676.50
12. Jumlah Total 156,401.50
Jumlah Total + jasa 10% 172,041.65
Memasang pipa PVC tipe D dia 4" tiap m'
Harga bahan:
- 58,125.00
- Pipa PVC dia 4" D m' 1.2000 37,500.00 45,000.00
Perlengkapan (35% harga pipa) % 35.0000 37,500.00 13,125.00
Upah tenaga:
- 32,401.50
- Pekerja Oh 0.0810 125,000.00 10,125.00
- Tukang pipa Oh 0.1350 145,000.00 19,575.00
- Kepala tukang Oh 0.0135 150,000.00 2,025.00
Mandor Oh 0.0041 165,000.00 676.50
13. Jumlah Total 90,526.50
Jumlah Total + jasa 10% 99,579.15
Memasang 1 buah bak cuci piring stainless steel
Harga bahan:
- 375,000.00
- Bak cuci stainless steel bh 1.0000 280,000.00 280,000.00
Water drain + asesoris set 1.0000 95,000.00 95,000.00
Upah tenaga:
- 51,997.50
- Pekerja Oh 0.0300 125,000.00 3,750.00
- Tukang batu Oh 0.3000 145,000.00 43,500.00
- Kepala tukang Oh 0.0300 150,000.00 4,500.00
Mandor Oh 0.0015 165,000.00 247.50
14. Jumlah Total 426,997.50
Jumlah Total + jasa 10% 469,697.25
Memasang 1 buah kran 1/2"
Harga bahan:
- 23,137.50
- Kran air bh 1.0000 23,000.00 23,000.00
Seal tape bh 0.0250 5,500.00 137.50
Upah tenaga:
14
- 18,075.00
- Pekerja Oh 0.0100 125,000.00 1,250.00
- Tukang pipa Oh 0.1000 145,000.00 14,500.00
- Kepala tukang Oh 0.0100 150,000.00 1,500.00
Mandor Oh 0.0050 165,000.00 825.00
15. Jumlah Total 41,212.50
Jumlah Total + jasa 10% 45,333.75
Memasang 1 floor drain sederhana
Harga bahan:
- 45,000.00
Floor drain bh 1.0000 45,000.00 45,000.00
Upah tenaga:
- 18,075.00
- Pekerja Oh 0.0100 125,000.00 1,250.00
- Tukang batu Oh 0.1000 145,000.00 14,500.00
- Kepala tukang Oh 0.0100 150,000.00 1,500.00
Mandor Oh 0.0050 165,000.00 825.00
16. Jumlah Total 63,075.00
Jumlah Total + jasa 10% 69,382.50
Membuat 1 unit sumur air tanah bor manual dalam 10 m' + pompa air listrik
Harga bahan:
- 1,579,475.00
- Pipa PVC dia 3/4" AW m' 14.0000 11,000.00 154,000.00
- Pipa PVC dia 4" D m' 12.0000 37,500.00 450,000.00
- Pompa air listrik Shimizu 125 W unit 1.0000 710,000.00 710,000.00
Perlengkapan (35% harga pipa+pompa) % 35.0000 758,500.00 265,475.00
Upah tenaga:
- 792,536.50
- Pekerja Oh 3.1620 125,000.00 395,250.00
- Tukang pipa Oh 2.3200 145,000.00 336,400.00
- Kepala tukang Oh 0.2320 150,000.00 34,800.00
17. Mandor Oh 0.1581 165,000.00 26,086.50
Jumlah Total 2,372,011.50
Jumlah Total + jasa 10% 2,609,212.65
Upah tenaga:
- 25,998.75
- Pekerja Oh 0.0150 125,000.00 1,875.00
- Tukang kayu Oh 0.1500 145,000.00 21,750.00
- Kepala tukang Oh 0.0150 150,000.00 2,250.00
Mandor Oh 0.0008 165,000.00 123.75
Jumlah Total 53,498.75
4.
- 4,840,691.38
17
- Tiang Listrik ( 9 M' ) bh 1.0000 2,090,000.00 2,090,000.00
- Kabel Twisted 4 x 70 mm m' 42.0000 58,000.00 2,436,000.00
- Cat Besi m² 1.4300 80,062.50 114,489.38
Cor Tiang m³ 0.1500 1,334,680.00 200,202.00
Jumlah Total 4,840,691.38
Jumlah Total + jasa 10% 5,324,760.51
Pasangan Pagar tembok tinggi 150 Cm
-
- Pekerjaan Galian Pondasi m³ 1.1000 97,875.00 107,662.50 926,112.93
- Pek. Urugan tanah kembali m³ 0.2750 32,619.50 8,970.36
- Pek. Pondasi Batu Kali m³ 0.2925 1,037,555.00 303,484.84
- Pek. Aanstamping m³ 0.1600 515,055.00 82,408.80
- Pek. Sloof 15/20 Cm m³ 0.0300 4,005,735.80 120,172.07
- Pek. Ring Balk 11/15 Cm m³ 0.0165 5,908,197.90 97,485.27
Pek. Kolom 20 X 20 Cm m³ 0.0400 5,148,227.26 205,929.09
- 495,051.04
- Pek. Pas. Batu Bata 1/2 Bata m² 1.1000 184,035.00 202,438.50
- Pek. Plesteran m² 2.2000 50,363.20 110,799.04
- Pek. Acian m² 2.2000 50,125.00 110,275.00
Pek. Pengecatan m² 2.2000 32,517.50 71,538.50
Pek. Paving blok warna abu + urugan sirtu 20 cm + urugan pasir 5 cm tiap m²
PLATE COMPACTOR
Kecepatan alat v 0.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 0.43 m'
Banyak lintasan (pass) n 6.00 lintasan 3 kali bolak-balik
Harga bahan:
- 251,600.00
- Sirtu m³ 0.2400 175,000.00 42,000.00
- Pasir urug m³ 0.0600 210,000.00 12,600.00
- Paving abu-abu segi enam, tebal 8 cm m² 1.1000 175,000.00 192,500.00
Abu batu m³ 0.0180 250,000.00 4,500.00
Harga pemakaian alat:
- 2,042.56
- TAMPER / HAND COMPACTOR jam 0.0165 39,620.74 653.74
PLATE COMPACTOR jam 0.0337 41,211.15 1,388.82
Upah tenaga:
- 37,360.00
- Pekerja Oh 0.2125 90,000.00 19,125.00
- Tukang batu Oh 0.1200 120,000.00 14,400.00
- Kepala tukang Oh 0.0120 130,000.00 1,560.00
Mandor Oh 0.0163 140,000.00 2,275.00
Jumlah Total 291,002.56
Jumlah Total + jasa 10% 320,100.00
18
7.
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
20
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
21
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
22
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
23
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
24
26.6666666667
160
281.32
20.1674666666667
37.1636363636 247.757575757576
297.309090909 16.6666666666667
184.331636364 105.333333333333
204.49910303
sloop 40 x 20
12.5
16 4 79.5 kg
12 6 85.44 kg
10 1.10 4.03
168.97
25
KOLOM 20 X 20 PAGAR
25
KOLOM 25 X 25 T. TERAS
16
SLOOP 20 X 20
25
25
6 12 92 0.89
6 0 16.5375
108
SLOOP 40 X40
6.25
22.25
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
26
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
27
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
28
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
29
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
30
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF! 25
#REF! 10.4
#REF! 0.045
1.62
#REF!
#REF! 0.27
#REF! 0.135
0.014
0.014
31
120,172.07
32
33
1 2 3 4 5 6
f. Pek. Lantai 26,409,601.74
1 Pas. Keramik 40 x 40 Cm 64.04 M2 224,499.00 14,376,915.96
2 Tegel plint keramik 74.90 M' 45,325.41 3,394,873.08
3 Tegel keramik KM (lantai) 3.00 M2 289,166.90 867,500.70
4 Tegel keramik KM (Dinding) 9.45 M2 324,280.00 3,064,446.00
5 Rabat beton (10 cm) 3.60 M3 1,307,185.00 4,705,866.00
B. AULA ( I BH ) Err:509
480 18
I. Pek. Persiapan 450 25,643,596.00
1 Perataan tanah 640.00 M2 22,825.00 14,608,000.00
2 Pas. Bouwplank 104.00 M' 106,111.50 11,035,596.00
1 2 3 4 5 6
11 Kusen Alumunium 4" 818.90 M' Err:509 Err:509
12 Pas. Pintu Double Tempered lengkap 220 x 90 5.00 Unit 16,000,000.00 80,000,000.00
13 Pintu Kaca Alumunium 200 x 80 Cm 8.00 Bh Err:509 Err:509
14 Pintu KM 200 x 70 CM Alumunium Lengkap 6.00 Set 850,000.00 5,100,000.00
15 Jendela kaca Alumunium 100 x 60 CM 44.00 Bh Err:509 Err:509
16 Jendela/BV kaca, rangka allumunium 121.20 M2 Err:509 Err:509
17 Jendela Alumunium ( Krapyak) 83.20 M2 400,000.00 33,280,000.00
18 Kunci Tanam 8.00 Bh 400,394.50 3,203,156.00
19 Engsel Pintu 18.00 Bh 78,098.63 1,405,775.25
20 Engsel Jendela 88.00 Bh 58,848.63 5,178,679.00
21 Gerendel Jendela 44.00 Bh 56,831.50 2,500,586.00
22 Kait Angin Jend. Aluminium 88.00 Bh 45,648.63 4,017,079.00
1 2 3 4 5 6
4 Panel Listrik + Instalasi 1.00 Unit 50,000,000.00 50,000,000.00
38
1 2 3 4 5 6
C. GUDANG 75 72 Err:509
1 2 3 4 5 6
VII. Sanitasi 14,943,874.00
1 Saluran Keliling Bangunan 55.00 M' 201,024.23 11,056,332.65
2 Kran Air 1.00 Bh 45,333.75 45,333.75
3 Kloset Jongkok 1.00 Bh 690,690.00 690,690.00
4 Pas. Pipa Ø 1/2'' 8.00 M' 33,227.70 265,821.60
5 Pas. Floor Drain 1.00 Bh 69,382.50 69,382.50
6 Pas. Septicktank / Peresapan 1 M3 1.00 Unit 2,816,313.50 2,816,313.50
1 2 3 4 5 6
V. Pek. Lantai 115,197,901.50
1 Lantai beton K 275 60.75 M3 1,792,978.00 108,923,413.50
2 Rabat beton (10 cm) 4.80 M3 1,307,185.00 6,274,488.00
1 2 3 4 5 6
14 Dinding batu alam 3.36 M2 495,522.50 1,664,955.60
15 Coating Batu alam 3.36 M' 28,591.75 96,068.28
16 List Profil 193.20 M' 55,000.00 10,626,000.00
II PRASARANA Err:509
Jumlah Err:509
PPN 10 % Err:509
Jumlah Err:509
20.00 Dibulatkan Err:509
162.00
Makassar , 2018
1 2 3 4 5 6
B. AULA ( I BH ) Err:509
480 18
I. Pek. Persiapan 540 25,643,596.00
1 Perataan tanah 640.00 M2 22,825.00 14,608,000.00
2 Pas. Bouwplank 104.00 M' 106,111.50 11,035,596.00
1 2 3 4 5 6
8 Pek Gordeng Kanal C 100 x 50 x 20 x 1,6 mm 1,178.55 KG Err:509 Err:509
9 Pek. Rangka pengikat kuda kuda pipa giv 2 '' 1,080.20 M' Err:509 Err:509
10 Pek. Skoor Kuda kuda L 70 x 70 x 7 mm 1,154.23 M' Err:509 Err:509
11 Pek. Skoor Kuda kuda Pipa giv 2'' 106.40 M' Err:509 Err:509
12 Perakitan 17,325.51 Kg Err:509 Err:509
13 Pengelasan 31,160.09 CM' Err:509 Err:509
14 Atap Zincalume 0,35 mm 531.50 M2 109,065.00 57,968,047.50
15 Pas. Lisplank (Wood Evlent ) 54.00 M' Err:509 Err:509
16 Pek. Besi Siku - Siku 30 x 30 x 3 mm 202.58 Kg Err:509 Err:509
17 Pas. Roof Mesh & Alumunium Foil 531.50 M2 72,457.00 38,510,895.50
18 Pas. Mur Baud skor kuda kuda 152.00 Bh 25,000.00 3,800,000.00
19 Dinding Alumunium 61.32 M2 400,000.00 24,528,000.00
20 Rangka Hollow Kanopi + penggantung 50.25 M2 600,000.00 30,150,000.00
21 Rangka Plafond Hollow + Calciboard 306.00 M' 176,875.05 54,123,765.30
22 List Plafond Gypsum 241.00 M' 50,711.38 12,221,441.38
1 2 3 4 5 6
C. GUDANG 75 72 Err:509
1 2 3 4 5 6
VII. Sanitasi 14,943,874.00
1 Saluran Keliling Bangunan 55.00 M' 201,024.23 11,056,332.65
2 Kran Air 1.00 Bh 45,333.75 45,333.75
3 Kloset Jongkok 1.00 Bh 690,690.00 690,690.00
4 Pas. Pipa Ø 1/2'' 8.00 M' 33,227.70 265,821.60
5 Pas. Floor Drain 1.00 Bh 69,382.50 69,382.50
6 Pas. Septicktank / Peresapan 1 M3 1.00 Unit 2,816,313.50 2,816,313.50
1 2 3 4 5 6
V. Pek. Lantai 115,197,901.50
1 Lantai beton K 275 60.75 M3 1,792,978.00 108,923,413.50
2 Rabat beton (10 cm) 4.80 M3 1,307,185.00 6,274,488.00
1 2 3 4 5 6
14 Dinding batu alam 3.36 M2 495,522.50 1,664,955.60
15 Coating Batu alam 3.36 M' 28,591.75 96,068.28
16 List Profil 193.20 M' 55,000.00 10,626,000.00
II PRASARANA Err:509
Jumlah Err:509
PPN 10 % Err:509
Jumlah Err:509
20.00 Dibulatkan Err:509
162.00
Makassar , 2018
A. FRANSISCA MAAHURY
DIREKTUR