Professional Documents
Culture Documents
PMP Daily
PMP Daily
Daily Question
There is a 10% probability that a given risk will occur during your new project. If it occurs, it will result in a loss of
$10,000. The insurance cost for this event is $700, with a deductible amount of US $250. Should a project manager
buy this insurance?
Daily Question
A project manager has just been assigned to a new project and has been given the completed project scope. The first
thing the project manager must do is:
Daily Question
A team member complains to the project manager that another team member has once again failed to provide
necessary information. The project manager meets with both team members to uncover the problem. This is an
example of:
withdrawal.
confronting.
compromising.
smoothing.
Daily Question
A project is seriously delayed. Earned value analysis shows the project needs to be completed 10% faster than the
work has been going. To get the project back on track, management wants to add 10 people to a task currently
assigned to one person. The project manager disagrees, noting that such an increase will not produce an increase in
speed. This is an example of:
Daily Question
Management has provided you with a project charter, and you are creating a scope statement. You have asked the
team for input to ensure the scope statement is complete. However, the team is struggling with defining the scope.
Which of the following describes the problem?
A WBS was not completed before the scope statement was begun.
The team is working on the scope statement without the benefit of product analysis and stakeholder agreement
on what the project will deliver.
The team is in the scope definition process and needs the scope statement as an input.
The project objectives were not identified before the scope statement was begun.
Daily Question
A project is defined as:
a coordinated undertaking of interrelated activities directed toward a specific goal that has a finite period of
performance.
a large, complex undertaking with many objectives, multiple sources of funding, and a not discernible end
point.
an undertaking of interrelated activities directed toward a specific goal that can be accomplished in less than
one year.
a group of activities headed by a project manager who has cradle-to-grave cycle responsibility for the end
product.
Metric: 3.4 Defects Per Million Opportunities. DPMO allows you to take complexity of product/process into
account. Rule of thumb is to consider at least three opportunities for a physical part/component - one for form,
one for fit and one for function, in absence of better considerations. Also you want to be Six Sigma in the
Critical to Quality characteristics and not the whole unit/characteristics.
Methodology: DMAIC/DFSS structured problem solving roadmap and tools.
Philosophy: Reduce variation in your business and take customer-focused, data driven decisions.
Six Sigma is a methodology that provides businesses with the tools to improve the capability of their business
processes. This increase in performance and decrease in process variation leads to defect reduction and vast
improvement in profits, employee morale and quality of product.
Daily Question
An organization is going through an evolution phase of restructuring the way it does projects. In a shift from a weak
matrix organization to a strong matrix organization, the power is shifted from the:
project manager to functional manager.
expeditor to coordinator.
functional manager to project manager.
functional manager to sponsor.
Daily Question
Your bolt production project is well underway. The requirements are clear that each bolt must weigh between .320
and .325 ounces. The first day of test production resulted in 15,000 bolts. Of the bolts inspected 47% fell within the
acceptable weight range. This is an example of?
Variable sampling
Attribute sampling
Control charting
Flow charting
Corrective action
Lessons learned
Scope verification
Scope planning
Daily Question
A project team is having difficulty communicating over long distances. There are 13 team members from two
countries when five people from Indiaare added. This is of concern to the project manager because:
When negotiating force majeure clauses, make sure that the clause applies equally to all parties
to the agreement--not just the licensor. In addition, it is helpful if the clause sets forth some
specific examples of acts that will excuse performance under the clause, such as wars, natural
disasters, and other major events that are clearly outside a party's control. Inclusion of examples
will help to make clear the parties' intent that such clauses are not intended to apply to excuse
failures to perform for reasons within the control of the parties.
Daily Question
You are about to begin negotiations with people from another country. Which of the following should provide
guidance on what business practices are allowed and not allowed?
Daily Question
A team member notifies you that she is about to add extra functionality to the project. She states there was no impact
on the cost or schedule. What is the initial action to perform by the project manager?
Understand what functionality is proposed, and if she is gold plating, halt her progress
Implement change control processes to track the change
Inform the customer of the change to the scope
Notify the functional manager that scope changes are not approved
Daily Question
A project manager is taking over a project from another project manager while the project is in
planning. If the new project manager wants to see what the previous project manager's plans for
managing changes to the schedule were, she would look at the:
communication plan.
project plan.
time management plan.
schedule management plan.
Daily Question
Your project schedule is tight and in danger of falling behind when two team members start disrupting status
meetings by arguing with each other. As project manager, which of the following is your best option?
Daily Question
The principal use of a Pareto diagram is to:
Daily Question
You are a project manager in a large organization that uses a matrix structure. You have been asked to investigate
what organizational structure your competitors use and how this affects their ability to manage projects successfully.
How would you describe the main difference between a matrix organization and a functional organization?
In a functional organization, project managers have more authority than they do in matrix organizations.
More people work full-time on projects in a functional organization than in a matrix organization.
Project team members usually report to two bosses in a matrix organization--the functional manager and the
project manager.
Most companies have found that functional organization structures provide the most flexibility for managing
projects.