LAMPIRAN G

FAKTOR KOREKSI

TABEL G.1
EFISIENSI KERJA

Sumber : Specification & Application Hanbook Komatsu Edition 28

TABEL G.2
BUCKET FILL FACTOR

Bucket Fill
Backhoe Kondisi
Factor
Mudah Tanah yang alami, clay dan tanah yang 1,1 ̴ 1,2
soft
Sedang Misalnya tanah berpasir dan tanah kering 1,0 ̴ 1,1
Agak Sulit Tanah berpasir dan gravel 0,8 ̴ 0,9
Sulit Blasted rock 0,7 ̴ 0,8
Sumber : Specification & Application Hanbook Komatsu Edition 28

TABEL G.3
FAKTOR KOREKSI EXCAVATOR

G-2

Sumber : Specification & Application Hanbook Komatsu Edition 28

TABEL G.4

G-1
ROLLING RESISTANCE

Sumber : Specification & Application Hanbook Komatsu Edition 28

TABEL G.5
WAKTU DUMP TRUCK HINGGA SIAP DIISI EXCAVATOR

Sumber : Specification & Application Hanbook Komatsu Edition 28

TABEL G.6
DUMPING TIME

G-3

Sumber : Specification & Application Hanbook Komatsu Edition 28

TABEL G.7
SPEED FACTOR

G-2
Distance of each
When making a When running into
section of haul road,
standing start each section
m
0 - 100 0,25 - 0,5 0,5 - 0,7
100 - 250 0,35 - 0,6 0,6 - 0,75
250 - 500 0,5 - 0,65 0,7 - 0,8
500 - 750 0,6 - 0,7 0,75 - 0,8
750 - 1000 0,65 - 0,75 0,8 - 0,85
1000 - up 0,7 - 0,85 0,8 - 0,9
Sumber : Specification & Application Hanbook Komatsu Edition 28