Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

ID Task WBS Task Name Duration Start Finish Apr 17, '17 May 8, '17 May 29, '17

Start Finish Apr 17, '17 May 8, '17 May 29, '17 Jun 19, '17 Jul 10, '17 Jul 31, '17 Aug 21, '17
Mode T W T F S S M T W T F S S M T W T
1 1 200KWp Solar Project 44 days? Wed 5/10/17 Thu 8/17/17
2 1.1 project initiation 15 days Wed 5/10/17 Wed 5/31/17
3 1.1.1 Agreement /Contract 7 days Wed 5/10/17 Fri 5/19/17
4 1.1.2 Feasibility Report 8 days Fri 5/19/17 Wed 5/31/17
5 1.2 System Design 31 days? Wed 5/10/17 Fri 6/23/17
6 1.2.1 Basic Design 4 days Wed 5/31/17 Tue 6/6/17
7 1.2.1.1 Specification of PVC 3 days Wed 5/31/17 Mon 6/5/17
8 1.2.1.2 Specification of Inverters 3 days Wed 5/31/17 Mon 6/5/17
9 1.2.1.3 Specification of Environment 4 days Wed 5/31/17 Tue 6/6/17
and Monitoring System
10 1.2.2 Detail Design 31 days? Wed 5/10/17 Fri 6/23/17
11 1.2.2.1 Single Line Diagram 2 days Tue 6/6/17 Wed 6/7/17
12 1.2.2.2 Site layout 2 days Thu 6/8/17 Mon 6/12/17
13 1.2.2.3 civil layout 2 days Mon 6/12/17 Wed 6/14/17
14 1.2.2.4 Plant monitoring system 3 days Wed 6/14/17 Mon 6/19/17
15 1.2.2.5 Cable layout 1 day? Wed 6/14/17 Thu 6/15/17
16 1.2.2.6 Detail BOQ 5 days Thu 6/15/17 Thu 6/22/17
17 1.2.2.7 BOQ generate 0 days Wed 5/10/17 Wed 5/10/17 5/10
18 1.2.2.8 Submission to client 1 day? Thu 6/22/17 Fri 6/23/17
19 1.3 Procurment 13 days Tue 6/6/17 Fri 6/23/17
20 1.3.1 Solar Panels ordering and delviery 6 days Wed 6/14/17 Thu 6/22/17

21 1.3.2 Inverters ordering and delivery 7 days Wed 6/14/17 Fri 6/23/17
22 1.3.3 Cables ordering and delivery 5 days Wed 6/14/17 Wed 6/21/17
23 1.3.4 Frame ordering and delivery 4 days Wed 6/14/17 Tue 6/20/17
24 1.3.5 LV panels ordering and delivery 4 days Wed 6/14/17 Tue 6/20/17
25 1.3.6 Consumables ordering and delivery 5 days Tue 6/6/17 Tue 6/13/17

26 1.4 On site installation 13 days Tue 6/13/17 Thu 8/3/17


27 1.4.1 Civil works 12 days Wed 6/14/17 Thu 8/3/17
28 1.4.1.1 Demarcation 2 days Wed 6/14/17 Fri 6/16/17
29 1.4.1.2 Frame Foundations 10 days Fri 6/16/17 Thu 8/3/17
30 1.4.2 Mechanical works 7 days Tue 6/20/17 Wed 8/2/17
31 1.4.2.1 Mounting frame Installation 3 days Tue 6/20/17 Fri 6/23/17
32 1.4.2.2 Solar Panels Installation 7 days Tue 6/20/17 Wed 8/2/17
33 1.4.2.3 Panel alignments 2 days Tue 6/20/17 Thu 6/22/17
34 1.4.3 Electrical works 12 days Tue 6/13/17 Wed 8/2/17
35 1.4.3.1 Inverters installation 3 days Tue 6/20/17 Fri 6/23/17
36 1.4.3.2 LV panels installation 4 days Tue 6/20/17 Mon 6/26/17
37 1.4.3.3 AC and DC cable laying and 6 days Wed 6/21/17 Wed 8/2/17
termination

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Mon 6/4/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task WBS Task Name Duration Start Finish Apr 17, '17 May 8, '17 May 29, '17 Jun 19, '17 Jul 10, '17 Jul 31, '17 Aug 21, '17
Mode T W T F S S M T W T F S S M T W T
38 1.4.3.4 Grounding cabling and 4 days Wed 6/21/17 Mon 7/31/17
termination
39 1.4.3.5 Earthing Pits installations 3 days Tue 6/13/17 Fri 6/16/17
40 1.5 Commissioning 4 days Wed 8/2/17 Tue 8/8/17
41 1.5.1 Plant Start Up 2 days Wed 8/2/17 Fri 8/4/17 8/4
42 1.5.2 Functional test 1 day Mon 8/7/17 Mon 8/7/17
43 1.5.3 P/R TEST 1 day Tue 8/8/17 Tue 8/8/17
44 1.6 Handing over and close out 5 days Wed 8/9/17 Thu 8/17/17
45 1.6.1 Operation and Maintenance 2 days Wed 8/9/17 Thu 8/10/17
Manual
46 1.6.2 As built drawings 3 days Wed 8/9/17 Tue 8/15/17
47 1.6.3 Training of operation and 2 days Tue 8/15/17 Thu 8/17/17
maintenance staff

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Mon 6/4/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
Aug 21, '17 Sep 11, '17 Oct 2, '17 Oct 23, '17 Nov 13, '17 Dec 4, '17 Dec 25, '17 Jan 15, '18 Feb 5, '18 Feb 26, '18 Mar 19, '18 Apr 9, '18 Apr 30, '18
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Mon 6/4/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3
Aug 21, '17 Sep 11, '17 Oct 2, '17 Oct 23, '17 Nov 13, '17 Dec 4, '17 Dec 25, '17 Jan 15, '18 Feb 5, '18 Feb 26, '18 Mar 19, '18 Apr 9, '18 Apr 30, '18
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Mon 6/4/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 4

You might also like