Professional Documents
Culture Documents
Method Statement For Installation & Insulation of Buried Chilled Water Piping
Method Statement For Installation & Insulation of Buried Chilled Water Piping
HPGRDC
PROJECT
EMPLOYER HPCL
PMC EIL
VKBS EIL
Signature:
Date:
INDEX
1. PURPOSE
2. REFERENCE
3. MATERIALS USED
4. TOOLS & EQUIPMENTS
5. HUMAN RESOURCES
6. SAFETY REQUIREMENTS
7. SURVEY AND SETTING OUT WORKS
8. STORAGE OF PIPES
9. PIPE TRENCH
10. INSTALLATION OF CHILLED WATER PIPES
12. HYDRO TESTING OF CHILLED WATER PIPES
13. INSULATION OF CHILLED WATER BURIED PIPES
14. RECORDS
1.0 Purpose
2.0 References
Welding machines
Impact drilling machine
Angle grinders
Tool box with spanner sets, hammers, Spirit levels, markers, Pipe wrench, measuring tape
Gas cutting equipment
Hydra crane
Chain Pulley
Excavator
De-watering system
Project Engineer
Project supervisor
Pipe fitter / Welder
HSE Personnel
Civil labours
All workers involved must be equipped with necessary PPE including hard hats, safety
boots, safety goggles and harnesses.
All workers must attend safety awareness and inductions.
A toolbox talk will be a part of all operatives prior to commencement of each phase.
Safety precautions shall be implemented to control hazards and prevent incidents to the
public.
Operations adjacent to public access shall be reviewed and monitored by the safety
officer throughout the duration of works.
Safety barriers, sign boards, first aid kits and fire extinguishers shall be used in the
location of works.
The surveyor shall ensure that the survey equipment be calibrated and have valid
calibration certificate.
Survey check points and other relevant data shall be recorded.
Work shall be commenced in areas surveyed and where survey sheet is jointly signed.
Existing services shall be located by use of cable detectors and trial excavations. They
shall be clearly marked at site.
13.0 Records
Signed off installation check list for chilled water pipe and
clearance for hydro test.
Signed off hydro test report and clearance for insulation works.
Signed off checklist at each stage of insulation process and
clearance for back filling.