KEY PLAN:

SCALE

1:200

+0.00 LVL

GENERAL NOTES:-

-1.00 LVL

-1.00 LVL

COMBINED WORK SHOP II - PLINTH BEAM/RAFT SLAB LAYOUT & DETAILS


-1.00 LVL

FOOTING LAYOUT

AT SUPPORT AT MIDSPAN AT SUPPORT AT MIDSPAN AT SUPPORT AT MIDSPAN

TYP C.S OF PLINTH BEAM - PB1 TYP C.S OF PLINTH BEAM - PB2 TYP C.S OF PLINTH BEAM - PB3
(300X700) (300X700) (300X700)

SECTION 1 - 1 SECTION 1 - 1
(FRAMING SECTION) (REINFORCEMENT SECTION)

NO. REVISION DATE

REVISION LOG
PROJECT

CONSTRUCTION OF CRRC
SECTION 3 - 3
(FRAMING SECTION)
SECTION 3 - 3
(REINFORCEMENT SECTION)
BASE PHASE I
INDIA MANUFACTURING
DRAWING TITLE

COMBINED WORK SHOP II


PLINTH BEAM/RAFT SLAB LAYOUT & DETAILS

OCEAN LIFESPACES PVT.LTD


SECTION 4 - 4 SECTION 5 - 5
SECTION 2 - 2
SECTION 2 - 2 (REINFORCEMENT SECTION) DATE DESIGN APPROVED
NORTH
(FRAMING SECTION) 19.03.2021
DRAWN ARUN ARUN
NITHIN
DRAWING No. REV
SECTION 6 - 6
WS-II / 3 R1