Professional Documents
Culture Documents
Cost and TIme Using Sketchup As BIM
Cost and TIme Using Sketchup As BIM
Practice Report
Cost and Time Management
Budget Planning
By:
Christian Aldo Chandra
181317150
ii
1 LIST OF FIGURES
iii
2 LIST OF TABLES
iv
3 LIST OF EQUATIONS
v
1 CHAPTER I
INTRODUCTION
1.1 Background
1.2 Objective
2
1.4 Project Description
The author uses project data from SDN 15 Dangin Puri, JL. Letnan
Dua Reta No.60, Dangin Puri Klod, Kecamatan Denpasar Timur,
Denpasar – Bali. An elementary public-school expansion consists of a
three-floor building with an area of 510 m2. PT. Mahkota Karya Marga from
Samarinda will be the contractor with the total project cost
Rp2.876.997.016,68 (Dua miliyar delapan ratus tujuh puluh enam juta
sembilan ratus sembilan puluh tujuh ribu enam belas Rupiah dan enam
puluh dua sen) in 2018 with a period of 32 weeks.
3
1.5 Methodology
The cost estimation of this report are conduct using Sketchup 2019 with
Quantifier Pro plugin from mind.sight.studios . for the schedule development will
be used Microsoft Project and Microsoft Excel spreadsheet to develop the S-curve.
4
2 CHAPTER II
QUANTITIY TAKEOFF
his chapter will discuss and compare the volume of the work from
the data with the author's calculation. The author determines not only
calculating the volume manually using a calculator or the help of a
spreadsheet application but also with the addition of BIM (Building
Information Modeling) Software Sketchup with Quantifier Pro add-on by
mind.sight.studios to help volume reading after modeling is done on the
software. The author will be modeling the construction project or manually
calculated the volume of work then compare the result with the construction
data or manual calculation.
Modeling of the project using BIM will simplify and compress time
and effort to planning the project, not only 3 dimensional of visualization
but also higher dimension, this particular configuration of application and
addon the author can achieve until the 4D of the Building Information
Modeling itself, which are :
6
Table 2.1 Continue Volume comparison
No Deskripsi Unit Consultant Computer Manual
I.3 PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Pasang batako 1pc : 3ps m2 339.7 335.4 339.7
4 Pek. Plesteran dinding 1pc : 5ps m2 638.8 630.1 638.8
Pengurangan pas. Bata di Ornament pintu m2
Pengurangan pas. Bata di Ornament dinding m2
Pengurangan pas. Bata di Ornament dinding m2
Pek. Pasang batako peninggian toilet m2 20.5 20.5
Pek. Kolom praktis m' 42.1 42.1
Pek. Plesteran pinggir pondasi dan ram 1pc : 6ps m2 68.1 68.1
Pek. Acian m2 721.2 721.2
7
Table 2.1 (Continue) Volume comparison
No Description Unit Consultant Computer Manual
PEKERJAAN PASANGAN DAN PLESTERAN
Pek. Pasang batako 1pc : 5ps m2 431,40 425,74
Pek. Plesteran dinding 1pc : 6ps m2 780,49 769,16
Pengurangan pas. Bata di Ornament pintu
Pengurangan pas. Bata di Ornament dinding
Pengurangan pas. list di Ornament dinding bawah jendela
PEKERJAAN ATAP DAN PLAFOND
Pek. Pasangan kap baja ringan Profil UK 75 m2 437,50 450,97 443,64
2.3 Analysis
The result is not 100%, all the same, this difference is expected to
happen. The lack of information on 2D drawing, other changes that apply
that were not updated on the drawing, or human error on calculation are
some errors that we can found in this project.
8
Figure 2.3 Column K2 volume in BIM
2.4 Attachments
9
3 CHAPTER III
UNIT COST ANALYSIS
In this chapter, we will find the comparison of the Unit cost of Denpasar
2018 (the project date and location) with the new price of Denpasar 2020. The
price shall be higher than in 2018, due to inflation that occurs each year. The
standard that is used by the contractor and this along with the coefficients is
taken in SNI (Standar Nasional Indonesia).
The BIM software does not have the code, so the coefficient of each work
can be manually inputted in the application or using a spreadsheet template,
there are third parties that selling SNI code spreadsheet template, but in this
report the author input the data using a spreadsheet manually.
1. Once the designer has all the code in the template, they can use it in
another project, so no need to build up all the code again.
2. The price list data can be stored in independent sheet data, so
changes in the price also affected the BIM software.
3. The report is generated automatically
4. Minimizing the error in calculation
5. Minimizing time to calculate
6. Minimizing manpower
11
Figure 3.1 Quantifier in-app coefficient input
In Figure 3.1 the software able to be input by any Unit cost analysis code,
in Indonesia we use SNI. The downside of using in-app as input interface is
there are no such tools as price library, so the user must manually type the price.
12
Figure 3.3 Price list sheet data (price library)
Figure 3.2 shows the template that can be filled in the spreadsheet
application, the BIM will read the specific Colom as the code, price,
coefficient, tax, or waste. This template does not come with the application, so
the user must make it by themself or by a third-parties template that is available
online.
13
Figure 3.4 Unit cost of the concrete column in BIM analysis for 2018 price
Figure 3.5 Unit cost of the concrete column in BIM analysis for 2020 price
Error! Reference source not found. and Error! Reference source not
found. are the report from BIM software by using the data of 2018 and 2020.
Those result is identical with the manual calculation in PART II : Unit price
Detail AnalysisError! Reference source not found. This software not only can
generate the Unit cost of each work but also capable to generate the whole price
in the project (volume*Unit cost). The result in BIM analysis can be generated
as spreadsheet to furthered data calculation.
14
3.4 Analysis
Almost all the Unit cost are higher in 2020, this increase of Unit cost are
caused by the inflation of the material and increase of labor cost. The BIM
software produce identical data, figure 3.4 and figure 3.5 price of Membuat 1
m3 kolom beton bertulang (300 kg besi + bekisting) in 2018 and 2020 in order,
has the same value as the traditional Unit cost calculation. The Unit cost in the
BIM software can be directly used and apply to the layer in the modeling
software to generate the Unit cost, cost of production, and the recapitulation.
The downside is the free template of SNI is not available on the internet, so the
designer must buy or makes the entire SNI code.
The price of material or workers in 2020 at Denpasar is higher than the 2018
price, thus almost all the Unit costs are increasing, however, some of the prices
in the mechanical-electrical are relatively the same.
3.5 Attachments
The 3.5.1 Unit cost detail analysis was calculated by the author on this practice.
The 3.5.2 contractor Unit cost analysis and 2020 analysis, the 2020 calculation
on that part were calculated by updating the price in the spreadsheet. The
recapitulation is the summary of the two attachment before.
15
4 CHAPTER IV
TOTAL BUDGET
This chapter is aimed to produce and compare the final price in 2020 with
the contactor price of Denpasar in 2018. This chapter will calculate the final
price of the structure by volume times the Unit cost. The volume calculated in
this chapter using the volume proposed by the consultant in the project. The
calculation using the help of a spreadsheet application.
The 2020 concrete work cost estimate have a significant difference to 2018
because, 2020 using a simple approach that assumes with a higher content of
the material, see Error! Reference source not found.. The cost estimation can b
e seen in the attachment at the end of this report (4.4.1 Cost Estimation).
Conncrete work
2018 Cost 2020 Cost Diffrence
on Level
Level 1 Rp627.235.443,22 Rp992.760.113,12 58,28%
Level 2 Rp425.730.353,06 Rp589.356.699,98 38,43%
Level 3 Rp132.467.409,45 Rp201.547.014,64 52,15%
4.3 Analysis
The final estimation price (2020) is higher than the 2018 price. The biggest
difference is on the concrete work, these significant differences up to 58%
higher, caused by a different approach to calculating the project. The contractor
calculates detailed volume that needed to construct, the do not attach the RAP
they just attach the RAB. To simplify this report, we are using the RAB
The cost estimate of the concrete from the contractor has a different method
of calculation from this practice, the contractor using RAP, this report using
RAB (they do not send the RAB). The contractor using the detailed calculation
by dividing the code for the concrete, reinforcement steel, and the formwork.
This practice using simplified code that takes the estimated steel and formwork
per m3, the result of this calculation prospected has a higher content of steel,
formwork, or concrete needed than detailed calculation.
4.4 Attachment
17
5 CHAPTER V
RECAPITULATION
This chapter is the summary from Chapter IV Cost estimation. But this
chapter is focused on discussing the final cost recapitulation, along with the cost
per m2 of the project. The data from Chapter IV will be categorized into a group
of work items.
The total cost recapitulation can be seen in Error! Reference source not f
ound. and below, the detailed calculation can be seen in attachment Error!
Reference source not found. Cost Recapitulation Data at the end of this report.
Lantai 2
II.1 PEKERJAAN PASANGAN DAN PLESTERAN Rp122,646,645.93 Rp132,140,692.30
II.2 PEKERJAAN BETON Rp425,730,353.06 Rp589,356,699.98
II.3 PEKERJAAN PASANG KERAMIK LANTAI & DINDING
Rp58,904,414.30 Rp63,061,725.83
II.4 PEK. PASANG KUSEN, PINTU DAN JENDELA Rp53,010,707.46 Rp57,290,160.02
II.5 PEKERJAAN PENGECATAN Rp39,502,448.73 Rp42,829,746.21
II.6 Pekerjaan alat-alat sanitary Rp9,008,052.21 Rp9,715,011.70
II.7 PEKERJAAN ELEKTRIKAL Rp22,887,000.00 Rp23,368,000.00
Continue to the next table…
Lantai 3
III.1 PEKERJAAN BETON Rp129.191.412 Rp139.232.737
III.2 PEKERJAAN BETON Rp132.467.409 Rp201.547.015
III.3 PEKERJAAN PASANG KERAMIK LANTAI & DINDINGRp55.256.300 Rp59.146.928
III.4 PEK. PASANG KUSEN, PINTU DAN JENDELA Rp46.225.490 Rp49.946.041
III.5 PEKERJAAN ATAP DAN PLAFOND Rp236.785.207 Rp253.338.460
III.6 PEKERJAAN PENGECATAN Rp53.431.845 Rp58.275.165
III.7 Pekerjaan alat-alat sanitary Rp10.732.479 Rp11.587.127
III.8 PEKERJAAN ELEKTRIKAL Rp29.047.000 Rp29.558.000
Total Rp2.615.451.833 Rp3.309.347.098
PPN 10% Rp261.545.183 Rp330.934.710
Total Payment Rp2.876.997.017 Rp3.640.281.808
Area (m2) 510 510
Pirece/m2 Rp5.641.171 Rp7.137.807
5.3 Analysis
From the data above the price in 2020 increase 26,53% than 2018 price.
Total price in 2020 increase from Rp 2.876.997.016 (Dua miliyar delapan ratus
tujuh puluh enam juta sembilan ratus sembilan puluh tujuh ribu enam belas
Rupiah) in 2018 to Rp3.640.281.807,54(Tiga miliyar enam ratus empat puluh
juta dua ratus delapan puluh satu ribu delapan ratus tujuh rupiah ) The result
of that, price/m2 in the 2020 increase to Rp7.137.807,47 from Rp5.641.170,62
in 2018 price.
19
6 CHAPTER VI
SUMMARY OF COST ESTIMATION
6.1 Summary
Unit cost in Denpasar 2018 between Denpasar 2020 indeed increase due to
a higher price in the material and the labor. Some of the prices in the
mechanical- electrical found to be almost no difference. The unit cost can be
calculated manually or using the help of the BIM software.
The total budget between 2018 and 2020 is a difference due to the different
approaches that this report method and the contractor method to calculate the
project. The contractor using RAP and this report using RAB, as the result the
concrete work is much higher than the contractor was calculated before.
The recapitulation of this project that the price/m2 in 2018 was Rp 5.641.171
and the 2020 Rp 7.137.807. The price is significantly increase caused by the
increase of material, labor cost, and the difference of the method of calculation
with the contractor.
The use of BIM software can reduce the error and time to calculate an
project. Beside of that the changes of price are almost certainly happened every
year, thus the BIM software also need to be flexible so that the price can be
easily adjusted into new price.
7 CHAPTER VII
DURATION OF EACH ACTIVITY
The purpose of this chapter to find the needs of the workers on each activity
to get the specific duration that already state in the beginning. The calculation
of the workers needs gathered from AHSP (Analisis Harga Satuan Pekerjaan)
from the various SNI code respectively to the category of the work. The duration
of each project will be calculated using spreadsheet application with Microsoft
Excel. With targeted 28 weeks or 196 days of working, from32 weeks by the
contractor in 2108.
The duration of each project depends on the volume of the project, amount
of the workers, and the logic in construction method. At the beginning the
authors must guest and plot the duration of each activity and the simple
relationship between of it. Between each activity can start at the same time if
not contradict to the logic of construction method.
Equation 2 Duration
Coeficient of Man Hour Number of worker × Duration
=
1 Volume of work
21
The Coefficient of Man Hour can be seen on SNI and the volume of work
information can be seen in the Attachment PART I : Volume Calculation from
Consultant. The duration and or the number of workers can be calculated
simultaneously based on the targeted finish date and method of the
construction.
Number of workers
Task Name Duration
Mandor K.Tukang T.Batu T.Kayu T.Besi T.Cat Pekerja
PEKERJAAN PERSIAPAN 196 days
Lansir & Persiapan bersih 196 days Ls Ls Ls Ls Ls Ls Ls
Pek. Bongkaran bangunan lama 5 days 20
Pek. Pengukuran dan bouwplank 2 days 1 1 2 4
Pek. Papan nama proyek 1 day 2
1 PEKERJAAN TANAH DAN PONDASI 21 days
1 Galian 7 days 1 24
1 Batu kali+ batu kosong 7 days 1 1 10 20
1 Urugan + Pasir +Peninggi lantai 7 days 1 12
1 PEKERJAAN BETON 49 days
1 Rabat +Sloof + Pondasi 14 days 2 2 2 8 34
1 Kolom 14 days 1 1 1 4 5 15
1 Plat lantai balok 14 days 2 2 2 9 7 33
1 Curring 7 days N.A N.A N.A N.A N.A N.A N.A
1 PEKERJAAN PASANGAN DAN PLESTERAN 56 days
1 Pasangan Tembok+kolom+toilet 14 days 1 1 1 3 1 9
1 Plesteran 18 days 1 1 6 12
1 Pek. Acian 24 days 1 1 3 6
1 PEKERJAAN KUSEN 56 days
1 Persiapan Kusen 14 days 1 1 Est. 5
1 Finnishing Kusen 28 days 1 1 Est. 5
1 PEKERJAAN PLUMBING 56 days
1 Persiapan Plumbing 14 days 1 1 Est.3
1 Finnishing Plumbing 14 days 1 1 Est.3
1 PEKERJAAN ELEKTRIKAL 56 days
1 Persiapan elektrikal 14 days 1 1 Est.4
1 Finnishing elektrikal 14 days 1 1 Est.4
1 PEKERJAAN KERAMIK 21 days
1 Keramik Dinding+lantai+plint 21 days 1 1 6 11
1 PEKERJAAN PENGECATAN 21 days
1 Cat dinding Kusen 21 days 1 1 4 4
2 PEKERJAAN BETON 35 days
2 Kolom 14 days 1 1 1 3 3 10
2 Plat Lantai+balok 14 days 2 2 2 6 7 33
2 Curring 7 days N.A N.A N.A N.A N.A N.A N.A
2 PEKERJAAN PASANGAN DAN PLESTERAN 35 days
2 Plesteran Listplank 7 days 1 1 2 4
2 Pasangan Tembok+kolom+toilet 14 days 1 1 4 1 1 10
2 Plsteran+Acian 14 days 2 2 15 29
2 PEKERJAAN KUSEN 56 days
2 Persiapan Kusen 14 days 1 1 Est. 5
2 Finnishing Kusen 28 days 1 1 Est. 5
2 PEKERJAAN PLUMBING 56 days
2 Persiapan Plumbing 14 days 1 1 Est.3
2 Finnishing Plumbing 14 days 1 1 Est.3
2 PEKERJAAN ELEKTRIKAL 56 days
2 Persiapan elektrikal 14 days 1 1 Est.4
2 Finnishing elektrikal 14 days 1 1 Est.4
22
Table 7.1 (Continue) Duration and worker needs
Number of workers
Task Name Duration
Mandor K.Tukang T.Batu T.Kayu T.Besi T.Cat Pekerja
2 PEKERJAAN KERAMIK 21 days
2 Keramik Dinding+lantai+plint 21 days 1 1 6 11
2 PEKERJAAN PENGECATAN 21 days
2 Cat dinding Kusen 21 days 1 1 4 4
3 PEKERJAAN BETON 14 days
3 Ring balok +Kolom 14 days
3 PEKERJAAN PASANGAN DAN PLESTERAN 35 days
3 Plesteran listplank 7 days 1 1 2 4
3 Pasangan Tembok+kolom+toilet 14 days 1 1 4 1 1 10
3 Plesteran + Acian 14 days 2 2 15 29
3 PEKERJAAN ATAP PLAFOUND 42 days
Atap 7 days LS LS LS LS
Plafond lt1 14 days 1 1 10
Plafond lt2 14 days 1 1 10
Plafond lt3 14 days 1 1 10
3 PEKERJAAN KUSEN 56 days
3 Persiapan Kusen 14 days 1 1 Est. 5
3 Finnishing Kusen 28 days 1 1 Est. 5
3 PEKERJAAN PLUMBING 56 days
3 Persiapan Plumbing 14 days 1 1 Est.3
3 Finnishing Plumbing 14 days 1 1 Est.3
3 PEKERJAAN ELEKTRIKAL 56 days
3 Persiapan elektrikal 14 days 1 1 Est.4
3 Finnishing elektrikal 14 days 1 1 Est.4
3 PEKERJAAN KERAMIK 21 days
3 Keramik Dinding+lantai+plint 21 days 1 1 6 11
3 PEKERJAAN PENGECATAN 21 days
3 Cat dinding Kusen 21 days 1 1 4 4
Note:
Mandor : Foreman
23
7.3 Analysis
24
8 CHAPTER VIII
RELATATIONSHIP OF ACTIVITIES
This chapter will discuss the connection of each activities. Also, will be
refer the determination of the order and requirement of each activity before it is
start and or finish. This step also developed together with the duration of each
activity, bar chart or S-curve. The relationship of each activity can be divided
into: Finish-Start, Start-Finish, Start-Start, and Finish to Finish.
The setting in the Microsoft Project 2013 are set to start on 1 January 2020,
holidays are not considered, and to simplify the report we use 7 days of work.
The determination of 7 days a week for working due to unfamiliar use of the
Project Management Software for the first time. Also form the CHAPTER VII
Duration of Each Activity already stated that 7 days and it multiples already
include off day for 1 day in Sunday (7days= 6 days working+1day for off day).
These mistakes result that data for labor Microsoft Project for the worker are
not able to use directly and need to be configure with a removal of one day
charge for the worker. The targeted 28 weeks are achieved on this stage and
presented in network diagrams.
The network diagrams are derived from the Microsoft Project as seen on the
attachment at the end of this chapter, the red colored is the critical path.
25
8.3 Relationship of Each Activities
A. Preparation Work
1. Lansir material & bersih bersih is work that carrying material from
borrow site to the site and or carrying material from the ground floor
to upper floor, so there is dependance on specific task just follow
when the project start and finish.
2. Pek. Bowplank is can be start if Pek. Bongkaran bangunan lama is
finish.
3. The other can be started as soon as the project start.
C. Concrete Works
1. Rabat, Sloof, and Foundation can be start together with Batu kali
and Batu kosong works, with assumption the first task is making
reinforcement or formworks
2. Column on the first floor works only start after Sloof and
Foundation works already finish.
27
3. Slab, and beam on first and second floor can be start after column
works are done.
4. Curing of the slab are estimated 1 (one) week to have minimum
hardness to resist another load from another construction above it.
The curing actually finishes on the 28th days after the pouring.
5. Column works on the second and third floor can be start after the
curing of the last concrete work is done so that it can carry some of
the additional stress form construction work above it.
28
6. The initial work on each floor can be start after the initial work
on the last floor is finished or simultaneously.
7. The final work on the first floor can be start after the initial work
on the third floor is finished.
8. The final work on each floor can be start after the final work on
the last floor is finished or simultaneously.
F. Plumbing
1. This works will be done by specific team worker
2. The work is separated as two task that gaped by the Masonry
Works and Wall Finishing.
3. The initial works are preparing and installation of the network of
the plumbing
4. The final work is the installation of the water tab, toilet, and other
equipment in the toilet.
5. The initial work on the first floor start together with the plesteran
work on the first floor
6. The initial work on each floor can be start only after the initial
work on the last floor is finished.
7. The final work on the first floor can be start after the initial work
on the third floor is finished.
8. The final work on each floor can be start only after the final work
on the last floor is finished.
G. Electrical
1. This works will be done by specific team worker
2. The work is separated as two task that gaped by the Masonry
Works and Wall Finishing.
3. The initial works are preparing and installation of the network of
the electrical
4. The final work is the installation of electric equipment
29
5. The initial work on the first floor start together with the plesteran
work on the first floor
6. The initial work on each floor can be start only after the initial
work on the last floor is finished.
7. The final work on the first floor can be start after the initial work
on the third floor is finished.
8. The final work on each floor can be start only after the final work
on the last floor is finished.
H. Painting
1. To get the best result on the painting task, normally use specific
teams that expert on this field.
2. After this work is done on specific floor then it is allowed to move
to the next floor.
3. This work can be start after acian works is done or do it
simultaneously.
I. Ceramic
1. To get the best result on the painting task, normally use specific
teams that expert on this field.
2. After this work is done on specific floor then it is allowed to move
to the next floor.
3. This work can be start after acian works is done or do it
simultaneously with assumption of 3 days of delay to give lead
time for the acian work, these lead time purpose to eliminate the
spill of cement to the ceramic if it is installed together.
J. Roof and Platform
1. The roof works can be start after the concrete work on the last
floor is finished. 14 days lag are determined to give more strength
on the concrete so that after the roof work is finished so do the
removing of the scaffolding for the ring beam.
30
2. The work of the platform started together with the roof work
and start from the first floor then move to the upper floor after it
is finished.
8.5 Analysis
The use of Project Management software is very helpful to see the task
detail. We can see when it is start or finish, we can add holiday, we can add the
task person in charge and can develop cost that we need to pay for the worker
by hour or day automatically. This application appropriate to medium to large
scale of project.
31
9 CHAPTER IX
SCHEDULE DEVELOPMENT
This chapter will explain the Gantt chart or the bar chart of the project. The
project Gantt chart is a different form from the network diagram, the network
diagram and Gantt chart are developed together. The Gantt chart is developed
using project management project by Microsoft Project 2013. The requirement
of every bar needs to have at least one arrow input and one output.
All the schedule development indeed was made together with the network
diagram in the Microsoft Project 2013. All the setting for date, target date, and
others are the same. The only different is how the Gantt chart or bar cart is
representing. Gantt chart allows the engineer to see when the activities running
simultaneously together and the relation to other activities.
The Gantt chart are developed using Microsoft Project 2013, and can be
seen on the attachment in the end of this chapter.
9.3 Analysis
From the Gantt chart, as we can see it is achieved the target of 28 weeks,
the Gantt chart, or the bar chart tells there are some series works but mostly the
works are do simultaneously together. The architectural works are the type of
work that can done. With 510 m2 of working area we can conclude that the
speed of the construction is 3.84 days/10 m2.
32
10 CHAPTER X
S-CURVE DEVELOPMENT
This chapter will discuss the development of S-curve from the bar chart. S-
curve represent the flow of the money in the project compare with the time in
X axis. The S-Curve are developed using Microsoft Excel. A good construction
graph when the graph is shows that the flow of the money in the beginning and
the end of the project is lower than in the middle.
The steeper the graph the higher cash out in the project at that time, and so
the opposite. The S-Curve of construction project normally follows the letter
“S” as the result of the different weight of the construction cost in the middle,
preparation, and finishing. The weight of each task can be obtained by the
formula below:
Task Cost
Task Weight = × 100%
Total Project cost
In simple term weight of each task is the percentages from the total project cost.
The S-Curve also had a bar chart for the cost, this bar chart is different with
the previous Chapter, this bar chart represents project duration, project weight
and task that is done in simultaneously. To develop the S-curve bar chart we
just divide the weight of each task with the duration (weeks) then the
percentages put in the horizontal cell the same number as the number of
durations, as seen on the Figure 10.1.
33
Figure 10.1 Bar Chart in S-Curve
Task Weight
Weight in a week =
Duration (weeks)
In the Figure 10.1 the duration of the Pekerjaan Tanah dan Pondasi are
following the Equation 4, the task was planned to be done in 5 weeks with
the weight of each week of 0.74% and the total of 3.69% from the total of
the project. Sometimes the task that has more weight compare to the other
calculated more detail by considering the specific task that were in that week
to the whole task Equation 5, normally the concrete work are the highest so
it was not divided equally into the duration but by the percentages of that
week cost to the whole concrete task in that floor (see Figure 10.1 Concrete
work bar chart, the red ones are not equal).
34
The S-curve or graph obtained by the accumulation of project weight in
every week. So, at the last week or the targeted 28th week will be 100%. The
100% represent the project cost already reached the total cost or in other
meaning it is finished from perspective of the project cost.
The S-Curve are developed using Microsoft Excel and can be seen on
the attachment in the end of this chapter.
10.3 Analysis
The steeper the graph of S-curve the higher is flow rate of the money in
the project. Normally the highest cost in building construction is the
concrete work that is why the graph move are like letter “S” because before
we enter the concrete work we must prepare the area, project, foundation
and others then after the structural or in this case is concrete is finished we
entered the architectural works. Thus, the preparation and architectural
works are relatively small to the structural works.
The S-Curve represent how the money affect the project progress by
duration of the project. at the beginning the project are slow because the
preparation work is relatively small compare to the structural. The finishing
or architectural works also relatively small and slow compare to the
structural works that has small duration and high cost. To get more detailed
S-Curve we can detailed the cost of the task, usually the concrete work is
divided not equally but based on the cost in detailed (Equation 5)
35
11 CHAPTER XI
SUMMARY OF SCHEDULE ESTIMATION AND S-CURVE
11.1 Summary
The Schedule and S-Curve in this report are achieved the target of 28
weeks of duration. The project is assumed to be start on 1st January 2021
and 15th of July 2021 from the contractor 32 weeks. The working area of
510 m2 and 28 weeks or 196 days, the speed of the construction is 3.84
days/10 m2. This part of the report needs knowledge of construction method
to connect each task so that the project can be performed efficiently.
The development of duration of each task, bar chart and the Gantt chart
are developed simultaneously and from each along the way we must revise
based on the logic of the construction method. The development of the S-
Curve itself shows the speed of construction based on the money that goes
through, the middle part is steeper means the flow of money is higher, this
middle part normally consists of the structural works that are have higher
cost than the other.
The Project Management Software are not only use by large company
but also starting to be used widely by small and medium company. The
contractor behind this project only use Spreadsheet and the S-Curve to
develop the schedule, this is risky as the project get bigger. The use of
Project Management Software like Microsoft Project 2013 and Spreadsheet
Application are very useful for contractor to easily see the connection of
each task, minimizing error during schedule development, and control the
flow of the construction.
36
12 CHAPTER XII
CONCLUSION AND SUGGESTION
12.1 Conclusion
12.2 Suggestion
From this report the authors suggest that the reader that wants to
develop cost and time for a construction project need to learn and try to use
BIM software and Project Management Software. The use of those software
nowadays are crucial for a medium to small project. the government also
planned to use BIM software as the standard of project in the future for
government building in the future. In other United Kingdom BIM software
mandate to be use by the contractor and the consultant in government
building to speed up the project and minimize error of volume and or the
cost calculation. The project Management Software in the future also seems
can be integrated with BIM software in the future. So, the use of those
software is expected to be normal in the future.
37
ATTACHMENT