PGP Global Patch Management Tool V0.91
PGP Global Patch Management Tool V0.91
___________________________________________________
Reference: (DGe\PGP-GPMT_V0.9)
Version: (PGP-GPMT_v0.9)
Date: (October 19, 2017)
© Copyright 2015 by Capgemini
Global Patch Management Tool / Project Governance Plan Page 2 of 46
TABLE OF CONTENTS
1 PROJECT GOVERNANCE PLAN OVERVIEW...........................................................5
1.1 Purpose Of The Project Governance Plan...........................................................5
1.2 Scope Of The Project Governance Plan...............................................................5
1.3 Control Of The Project Governance Plan.............................................................5
1.4 Deviations From Standard Structure....................................................................6
2 PROJECT OVERVIEW...............................................................................................7
2.1 Project Description...............................................................................................7
2.2 Project Objectives................................................................................................7
2.3 Project Critical Success Factors...........................................................................7
2.4 Project Scope and Services.................................................................................7
2.5 Deliverables......................................................................................................... 8
2.6 Project Milestones..............................................................................................11
2.7 Business Obligations..........................................................................................11
2.8 Assumptions.......................................................................................................12
2.9 Constraints.........................................................................................................12
2.10 Dependencies....................................................................................................13
3 PROJECT APPROACH.............................................................................................14
3.1 Phases............................................................................................................... 14
3.2 Development Methods and Standards...............................................................15
3.3 Ongoing Support................................................................................................15
4 PROJECT GOVERNANCE.......................................................................................16
4.1 Project Management Method.............................................................................16
4.2 Organisation.......................................................................................................16
4.3 Governance Roles and Responsibilities.............................................................17
4.4 Project Reporting................................................................................................18
4.5 Meetings.............................................................................................................18
4.6 Acceptance........................................................................................................ 19
4.7 Monitoring of Actions..........................................................................................19
4.8 Handover............................................................................................................ 19
4.9 Warranty.............................................................................................................19
5 PLANNING AND FINANCIAL MANAGEMENT.........................................................20
5.1 Estimating..........................................................................................................20
5.2 Project Plan........................................................................................................20
5.3 Project Cost and Budget Management...............................................................20
5.4 Invoicing............................................................................................................. 21
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Global Patch Management Tool / Project Governance Plan Page 3 of 46
6 RESOURCE MANAGEMENT....................................................................................22
6.1 Team Organisation.............................................................................................22
6.2 Team Roles and Responsibilities.......................................................................22
6.3 On Boarding.......................................................................................................24
6.4 Training and Coaching.......................................................................................24
6.5 Team Member Evaluations.................................................................................24
6.6 Team Member Release......................................................................................24
7 SCOPE AND REQUIREMENTS MANAGEMENT.....................................................25
7.1 Scope Baseline..................................................................................................25
7.2 Requirements Traceability..................................................................................25
8 CHANGE CONTROL.................................................................................................26
9 RISK MANAGEMENT...............................................................................................27
10 ISSUE MANAGEMENT.........................................................................................28
11 CLIENT RELATIONSHIP MANAGEMENT............................................................29
11.1 Business Steering Board Description.................................................................29
11.2 Business Kick-Off Meeting.................................................................................29
12 SUPPLIER AND PROCUREMENT MANAGEMENT.............................................30
12.1 Supplier Selection..............................................................................................30
12.2 Supplier Agreements..........................................................................................30
12.3 Supplier Management........................................................................................30
12.4 Supplier Acceptance..........................................................................................30
12.5 Supplier Audits/Reviews.....................................................................................30
12.6 Supplier Performance.........................................................................................30
13 COMMUNICATION MANAGEMENT.....................................................................31
13.1 Capgemini Communication Plan........................................................................31
14 INFRASTRUCTURE MANAGEMENT....................................................................32
14.1 Project Management Environment.....................................................................32
14.2 Project Delivery Infrastructure............................................................................32
14.3 Infrastructure Reviews........................................................................................32
14.4 Security Management........................................................................................32
14.5 Storage and Archiving........................................................................................33
15 CONFIGURATION MANAGEMENT......................................................................34
15.1 Configuration Identification.................................................................................34
15.2 Configuration Control.........................................................................................34
15.3 Document Configuration.....................................................................................34
15.4 Configuration Status Reporting..........................................................................34
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Global Patch Management Tool / Project Governance Plan Page 4 of 46
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Global Patch Management Tool / Project Governance Plan Page 5 of 46
1.3.2 Approval
The PGP has received ‘internal approval’ by the Capgemini Domain Manager / Regional
CIO and Group IT PMO and final approval by the SteerCo.
1.3.3 Updating
The Capgemini Engagement Manager is responsible for maintaining the PGP.
Once this PGP has been agreed, by signature Capgemini representatives in Appendix A
of this document, it may be deviated from by Capgemini only under internal change
control.
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Global Patch Management Tool / Project Governance Plan Page 6 of 46
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Global Patch Management Tool / Project Governance Plan Page 7 of 46
2 PROJECT OVERVIEW
2.1 Project Description
Currently there is no central uniform Global Patch Management tool, to patch the
Windows / Unix / Linux / Virtualization Production and Non Production environments,
either through automated or manual patch deployments or a combination of both.
Multiple tools at various regions, resulting in complex reporting and time consuming
processes. Current decentralized, manual patch management process is time
consuming, takes longer cycles to detect & report the gaps, roll out the patches.
The proposed Global patch management process will ensure a centralize control- in-time
alerting, effective patching, reporting on overall global computing platforms, are Patched
up to date & Secured, in line with vendor’s recommendations, reducing the risk of non-
compliance and compromises
With this project multiple teams within Global Infrastructure as well as representative
from the regional Capgemini BU’s are to be involved.
A summary for the Capgemini project team can be found below:
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Global Patch Management Tool / Project Governance Plan Page 8 of 46
2.5 Deliverables
The following table lists the Deliverables in scope showing those requiring Business
review and acceptance.
Any document identified during the course of the project that is not a Deliverable for
acceptance but requires formal acceptance by the Business, a change control must be
raised requesting it to become a formal project deliverable. The change control
procedure also needs to define the Acceptance Criteria for the new Deliverable but must
not contradict anything already defined in the PGP.
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Ref Deliverable Deliverable Description Acceptance Criteria Approved By Deliverable
Due Date
D01 PGP This Project Governance Plan Domain 10/31/2017
Content matches the deliverable
(PGP). Manager
description
Covers the scope of the Project
Sign off by Business Lead
D02 Project Schedule Details the tasks, duration, Domain 10/31/2017
The team members should first
dependencies and resources Manager
evaluate their task
required to deliver the scope and
deliverables of the Project. Provides sufficient detail in
All the tasks of the project and outlining the project schedule for
Milestone should be planned, and a the duration of project.
resource affected to each task. Part
of the PGP Covers the scope of the services.
Appropriate stakeholders have
been consulted in its production.
Sign off by Business Lead
D03 Staffing Plan and Budget Part of the PGP Domain 10/31/2017
Provides sufficient detail to
Manager
define the budget required to
deliver the project.
Covers the scope of the project.
Appropriate stakeholders have
been consulted in its production
Validate in Steering committee
D04 Decision and overall High Agreed and documented designs 11/09/2017
Level Design on Tooling per and decisions. Created and validated by Data Domain
Centre Technology Manager
technology.
Design is inline and agreed with
GIT Infrastructure compliance
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright 2014 by Capgemini. All rights reserved.
management team
Validate by the business Lead
D05 Detailed Design on Tooling Agreed and documented designs 11/17/2017
Created and validated by Data Domain
per technology. and decisions.
Centre Technology Manager
Design is inline and agreed with
GIT Infrastructure compliance
management team
Validate by the business Lead
D06 POC IBM BigFix and/or Document describing the POC Domain 11/17/2017
Validate by the business Lead
Lessons Learned results Manager
D07 Updated Roll-out plan per Document with a more detailed Roll- Domain 11/17/2017
Validate by the business Lead
technology / OS out plan per stream Manager
D08 SCCM client installed on Migration Reports, Dashboards & Domain 03/09/2018
Validate by the business Lead
Wintel servers statistics Manager
D09 IBM BigFix / installed on Migration Reports, Dashboards & Domain 03/16/2018
Validate by the business Lead
Unix and Linux servers statistics Manager
D10 Consolidated report / Overall Migration Reports, Domain 03/23/2018
Validate by the business Lead
findings Dashboards & statistics Manager
D11 Project Closure Report Closure Report with Observations, and Domain 03/30/2018
learnings. Validate by the business Lead
Manager
2.6
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright 2014 by Capgemini. All rights reserved.
2.7 Project Milestones
The milestones (M) and Tollgate milestones (TM) for the project are:
R2
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Ref. The Business Obligations Date Required By
R3
2.9 Assumptions
The following Assumptions have been made in connection with the Services and
Deliverables:
A5 The GPO’s required for the Windows servers will be in place on time.
Any new assumptions identified during the project will be recorded in the Project
Progress Report or the Monthly Status Report and jointly discussed with the Business.
An action plan will be agreed and documented in the Decisions Log.
If any of the assumptions prove to be incorrect, this will be reported in the Project
Progress Report and the impact will be managed using the change control process.
2.10 Constraints
The following constraints have been identified and apply to this Project:
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
2.11 Dependencies
The following dependencies have been identified and apply to this Project:
These and other known external dependencies associated with this project i.e.
dependencies this project has with other projects, areas of work, people or events
outside of this project are included in the projects Dependency Log.
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
3 PROJECT APPROACH
The general approach to the Project will conform to the Capgemini standards defined in
DELIVER Unified Project Management methodology (UPM v6.5).
Below is a summary of the project approach:
3.1 Phases
The Waterfall method structures the project lifecycle and the development into 4 distinct
phases, each of which have the following typical focus for the project team:
Start-up
Proof of Concept & Design
Rollout in multiple batches & per technology
Closure
Each of these phases by definition has a pre-defined set of objectives and evaluation
criteria, for the project to meet. This process is managed through the use of the Quality
Management procedures as provided in Section 16. Risk is assessed and mitigating
actions defined as the project progresses, to provide sound foundations of the solution
being built.
The following tables have been added as a guide and show the common phases that
apply depending upon the methodology used. Select the table which is appropriate to
the methodology being used and modify the naming of the phases as appropriate.
i) Waterfall:
Phase Activity
Start-up Project Preparation, PGP, Schedule, Planning
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Phase Activity
Requirements gathering, startup of procurement process
Preparation of the POC test cases
Creation of HLD, setup of the test environment, determine
POC & Design
exact number of servers per technology
Exploring and testing IBM BigFix Functionality (eg. Determine
hardware firmware detection), POs
Creation of Detailed Designs, Lessons learned, rollout plan
Installing and monitoring Patch management roll out SCCM /
Rollout
Wintel
Installing and monitoring Patch management roll out BigFix /
Linux & Unix
Progress and compliance reports
Issue resolving, Transition /handover to operations
Close Down Lessons learned
Run - system live
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
4 PROJECT GOVERNANCE
4.1 Project Management Method
Capgemini will manage Capgemini’s work on the project using Capgemini's UK Project
Management method Unified Project Management (UK UPM).
4.2 Organisation
The Governance organisation structure is defined in the following diagram, for more
details please see section §Error: Reference source not found.
Exec Steering Committee
Pieter Schoehuijs (Sponsor)
Steve Wanklin
Chella Namasivayam M (Shivam)
Sudhir Ramarao
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
4.3 Governance Roles and Responsibilities
The Capgemini Group IT key roles and their responsibilities within the governance
structure are defined below. The allocation of the responsibilities for the Capgemini
project management team roles at a more detailed level are also defined in the table
below.
The table below shows a RACI for the key Capgemini roles and responsibilities. By
Capgemini this means Group IT. The Business involvement by role is shown where
applicable annotated by a ‘Y’ within the table.
R (Responsible); Those who do the work to achieve the task. There is at least
one role with a participation type of responsible, although others can be
delegated to assist in the work required
A (Accountable); The one ultimately answerable for the correct and thorough
completion of the deliverable or task, and the one who delegates the work to
those responsible. There is only one person accountable.
C (Consulted); Those whose opinions are sought, typically subject matter
experts; and with whom there is two-way communication
I (Informed); Those who are kept up-to-date on progress, often only on
completion of the task or deliverable; and with whom there is just one-way
communication
Activity Business Project Project Group IT Project
Lead / Manager Sponsor Steering Team
Domain Committ members
Manager ee
Preparation & maintenance of C/I A/R I I C
PGP
Sign Off PGP R A/R I C
Appropriate Capgemini R A/R C
resourcing
Planning & control of work C/I A/R C C
Iteration planning and control I A/R C C
Management issues and risks R A/R I C C
Status & Progress reporting I A/R I I C
Manage budget R A/R I
Negotiation with Capgemini A/R C C
Suppliers
Implementation of Supplier A C C/R
deliverables
Overall delivery & quality of R A/R I R
work
Change Management & C A/R I I R
Communication
Configuration Management I A/R R
Sign Off Change Requests R A/R I I I
End of project archiving I A/R I R
Maintenance of the live system A
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Where a Capgemini person is absent though e.g. sickness or holidays, a deputy may be
nominated to undertake some or all of that person’s activities.
4.5 Meetings
The table below sets out key meetings that will take place:
Steering Domain Project Capgemini
Board Meeting Manager/ Management Project Team
Regional CIO Meeting Meeting
Objective Review Review Review Co-ordinate
progress and progress and progress and team, review
make make policy make tactical progress,
policy/strategy decisions decisions issues/actions,
decisions work for next
period
Frequency Monthly Monthly Weekly Weekly –
Monday
Reports for input to Monthly Project M-Review Pack Verbal EMI Project
Meeting Status Report Progress Progress Report
Report from
team
Suggested Agenda
Agree previous minutes Y Y Y Y
Outstanding actions Y Y Y Y
Review Progress this Y Y Y Y
Period
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Steering Domain Project Capgemini
Board Meeting Manager/ Management Project Team
Regional CIO Meeting Meeting
Issues arising/foreseen Y Y Y Y
Plans for next period Y Y Y Y
Financial Status N Y N N
Any Other Business Y Y Y Y
Date of next meeting Y Y Y Y
4.6 Acceptance
The procedures for accepting document and software deliverables are defined below.
The Business shall within five (5) working days of the Deliverable being submitted for
acceptance notify the Engagement Manager of acceptance or any questions of non-
conformity in a consolidated list and the parties shall work together to address the
concern and/or produce a new version of the particular Deliverable. If no questions of
non-conformity are received from the Company within five (5) working days of
submission, then the Engagement Manager shall escalate the matter to the Business
Project Manager for resolution.
4.8 Handover
A Handover Plan to the ongoing support organisation, Group IT Global Infra, will be
written. The ongoing support will be provided through already established Group IT
processes & Group IT Global Infra organisation.
4.9 Warranty
No Warranty applies.
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
5 PLANNING AND FINANCIAL MANAGEMENT
5.1 Estimating
The initial estimation of effort and duration for this project has been completed by the
project team. As the project progresses the estimates will be revisited and reviewed at
the end of each project phase by the Capgemini Engagement Manager.
An estimate may also be carried out by the Capgemini Engagement Manager at an
intermediate stage where there has been a change in scope, where further information is
known which is likely to impact the overall estimate or where there are variances against
the project forecasts.
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
5.4 Invoicing
5.4.1 Supplier Invoices
Supplier invoices received by the project are checked by the Capgemini Engagement
Manager. Valid invoices are passed for payment authorisation and payment within
Capgemini.
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
6 RESOURCE MANAGEMENT
The Capgemini Engagement Manager will liaise with Capgemini’s Resource
Management Team to obtain resources to deliver the project. The Business will be
advised, at project meetings, of planned project joiners/leavers.
Mahanthesha Tuppada,
Arvind Singh
Maruti Kumbhar
De La Monneraye, Aubin
Sagar Sawant
Data Center Define and execute POC, Producing implementation
Operations / Unix / approach, Coordinate the installation batches, Report issues
Linux / AIX as observed, Apply Solutions/workarounds, Provide Updates
for Status/dashboards
--
Jesan T (L3)
Prakash Periyasamy
M S, Ramajanarthanan
Chinnasamy, Ramya
Muthyala, Hema Varun
Narhe, Sunil
Sarade, Tejas
Data Center Define and execute POC, Producing implementation
Operations / approach, Coordinate the installation batches, Report issues
Virtualization / Cloud as observed, Apply Solutions/workarounds, Provide Updates
for Status/dashboards
--
Raphael Demange
Gurjit Dhilion
tbd
Global PPT / SCCM Producing implementation approach, Coordinate the
installation batches, Report issues as observed, Apply
Solutions/workarounds1, Provide Updates for
Status/dashboards
--
Umesh Tambe (L3)
Vasu Miriyala
Naba Das
1
During migration and after moving into production stage, SCCM team is responsible for
SCCM Server and/or Client level issues while Wintel Team takes care of Server OS level
issues concerning patching or Software Distribution due to fact that many OS, core OS
components can play vital role in patching or SWD. Access rights, in case of issues, will
be aligned between both teams.
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Area Responsibilities / Team
VinodKumar Devaragatla
Service Management Audit on Patch management process, Report issues as
Office / Infra Risk & observed, Provide Updates for Status/dashboards,
Compliance Assessment and advice on the reports produced by Patch
Management / Global Management Tools (SCCM and BigFx)
Security
--
Rakshit Dhamija
Abhayeet, Kumar
6.3 On Boarding
New Capgemini team members are on boarded using the projects Onboarding Pack.
They will be given an overview of the project by the Capgemini Engagement Manager
and the appropriate project team lead for technical aspects of the project. Training on
standard project tools will be given as needed.
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
7 SCOPE AND REQUIREMENTS MANAGEMENT
7.1 Scope Baseline
The scope of this project is as detailed in Section 2.4 Project Scope of this PGP.
Any deviation from that scope, inclusions or exclusions, will require a formal Change
Request (CR) which is duly approved by the project owner.
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
8 CHANGE CONTROL
The Change Control process for the project is described in DELIVER Project
Management Method.
The responsibilities / timescales for affecting these procedures are:
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
9 RISK MANAGEMENT
The Risk Register will be maintained using EMI. In summary, risk assessment and
monitoring will take place at regular intervals throughout the project. These are normally:
Where necessary, the Project Plan will be updated to reflect the impact of any agreed
containment actions, and Change Control will be invoked if appropriate.
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
10 ISSUE MANAGEMENT
The Issue Register will be maintained using EMI. Issues are situations that could affect
project performance or quality.
In summary, issue assessment and monitoring will take place at regular intervals
throughout the project. These are normally:
Task Timescale Responsibility
Raise Issue Report As they occur Any person working on or related
to the project
Assessment/ Periodically Project Manager / PMO
management of problems
Reporting Periodically Project Manager / PMO
The Project Manager and the Project Team will assess the impact of each issue on the
project and identify the actions/responsibilities to resolve the issue, with input from the
Business where required. The impact on the costs and timescales may also be
assessed.
The Issue Register will be maintained using EMI and the following will be documented:
Reference Consecutive number
Issue Description of Issue that has occurred
Action Action to be taken to resolve issue
Responsibility Person responsible for carrying out resolution actions
By When Timescale for resolution action to be carried out
Where necessary, the Project Plan will be updated by the Project Manager to reflect the
impact of the issue and the resolution actions, Change Control will be invoked where
there is any impact on project timescales, Capgemini’s services, resources or costs or
the Business obligations.
The Issue escalation route is defined below.
Escalation within the Project Project Manager to
Team Domain Manager to
Project Board to
Steering Board to
Executive Steering Board
Escalation within Group IT Project Resources to
Project Manager to
Domain Manager / Regional CIO to
Capgemini Group IT CIO
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
11 CLIENT RELATIONSHIP MANAGEMENT
11.1 Business Steering Board Description
The Group IT steering board and all related activities are described in §Error: Reference
source not found
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
12 SUPPLIER AND PROCUREMENT MANAGEMENT
Procurement Management will be carried out by Capgemini using Capgemini’s standard
procurement tool, GPS. The information in this section refers to both Capgemini
suppliers and sub-contractors involved in delivering the Project.
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
13 COMMUNICATION MANAGEMENT
Communication Management will establish and implement effective communication to
the Business, End Users and Support Teams in the progress and overall outcome of the
project.
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_V0.9) Version: (v0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Global Patch Management Tool / Project Governance Plan Page 32 of 46
14 INFRASTRUCTURE MANAGEMENT
14.1 Project Management Environment
The project management environment will support the Program Manager in running and
managing the project. It will be set up using the standard Capgemini project
management tools of Open Work Bench for Planning and Troom for the project
repository.
The project repository which will hold all management and delivery documents produced
during the project's lifetime. In addition the project will have use a Troom for work in
progress.
The project management environment will be managed by the PMO / Project Manager
with support from the PMO Managed Service.
14.4.2 Data
No Capgemini customer data is involved.
14.4.4 Confidentiality
Not applicable
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_v0.9) Version: (V0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Global Patch Management Tool / Project Governance Plan Page 33 of 46
14.5.2 Archiving
TRoom will be used for Archiving of project related documents
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_v0.9) Version: (V0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Global Patch Management Tool / Project Governance Plan Page 34 of 46
15 CONFIGURATION MANAGEMENT
For Configuration Management the ITSM records will be updated where needed.
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_v0.9) Version: (V0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Global Patch Management Tool / Project Governance Plan Page 35 of 46
16 QUALITY MANAGEMENT
Capgemini Quality Management (QM) within the project is provided by a number of
Capgemini roles operating independently of the project team, and each providing a
different perspective to the overall QM role.
The Capgemini roles involved in providing QA within the project are:
Domain Manager / Regional CIO – Responsible for the project’s delivery within
Capgemini, and providing QM in the areas of commercial and financial management,
together with overall mentoring of the Engagement Manager.
Independent Quality Advisor (IQA) –Responsible for providing independent quality
assurance and coaching.
Technical Quality Advisor (TQA) - Responsible for providing independent quality
assurance for the software development of the project.
Each of these roles will initially report findings and recommended actions to the
Capgemini Engagement Manager to be implemented. The quality status of findings is
also reported to the Group IT leadership team. Non-compliance with QM requirements is
escalated to the Capgemini Domain Manager / Regional CIO.
All information and reporting from the Capgemini QM process is internal and confidential
to Capgemini.
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_v0.9) Version: (V0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Global Patch Management Tool / Project Governance Plan Page 36 of 46
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_v0.9) Version: (V0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Global Patch Management Tool / Project Governance Plan Page 37 of 46
17 KNOWLEDGE MANAGEMENT
17.1 Knowledge Object Reuse
Capgemini has a policy of re-using best practices gained in its projects. Each project
has access to a range of functional descriptions, system designs, frameworks,
components, and code.
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_v0.9) Version: (V0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
_______________________________
APPENDICES
_______________________________
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_v0.9) Version: (V0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Appendix A: Document Control
Version History
Version Date Comments
0.1 29 Sep. 2017 First draft of PGP
0.2 6 Oct. 2017 Processed initial feedback teams
0.3 10 Oct. 2017 Processed feedback Sandeep H.
0.4 13 Oct. 2017 Processed feedback Team members
0.8 17 Oct. 2017 Processed comments and feedback Team Leaders
0.9 19 Oct. 2017 Processed comments and feedback Program & Project
Office - Sonika Sharma and from Domain manager /
Senior Director, Global Datacenter Ops - Sudhir
Ramarao
0.91 21 Oct. 2017 Processed comments of PMO CoE, updated and aligned
on the dates regarding the dependencies.
1.0
Document Sign Off
Name Capgemini Responsibility PGP Signature
Role Section
Sudhir Domain Review to confirm the ALL See email
Ramaro Manager / PGP meets and does Wed
Regional CIO not exceed the needs 10/18/2017
of the Group IT
commitments
RE Patch
Management Tool Review of the Proje
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_v0.9) Version: (V0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Document Distribution
Name Location Responsibility PGP Action/
Sectio
Information
n
Sudhir Capgemi Capgemini Domain ALL Action
Ramarao ni Manager / Regional CIO
tbd Capgemi Capgemini Group IT ALL Information
ni PMO
Sandeep H Capgemi Data Center ALL Action
ni Technologies / Tools &
Technologies
Jesan T Capgemi Data Center Operations / ALL Action
ni Unix / Linux / AIX
Amol Capgemi Data Center Operations / ALL Action
Belhekar ni WinTel
Umesh Capgemi Global PPT / SCCM ALL Action
Tambe ni
Dennis Capgemi Capgemini Project ALL Action
Gebbink ni Manager
Key Capgemi Team member Global ALL Information
stakeholders ni Patch Management Tool
Project team
Project Capgemi ALL Information
Repository ni
Source File Location – Office 365\ Group IT \ Infra \ DC Global \ Tools& Technologie \
Patchmanagement
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_v0.9) Version: (V0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Appendix B: Reference and Applicable Documents
B1 Reference Documents
The following table lists documents which are referenced within this Project Governance
Plan. They are for supplementary information.
B2 Applicable Documents
The following table lists all documents, which may not be explicitly referenced within this
Project Governance Plan, but provides background or supplementary information to the
project.
B3 Global Datacenters
This appendix defines key abbreviations and acronyms contained in this document.
S. Datacenter Site City Cou Region
N Name ntry
o
1 IN-MAA-PCT Chenn India East
ai
2 Hyderabad H07 Hydera India East
(phoenix) bad
3 IN-BLR- Bangal India East
BELLANDUR1 (6B) ore
4 IN-BOM- Mumb India East
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_v0.9) Version: (V0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
MINDSPACE (Airoli) ai
5 Mumbai IKP Mumb India East
ai
6 AU-MEL- Melbou Austr East
COLLINSS rne alia
7 AU-SYD- Sydne Austr East
KINGSTRE y alia
8 Chennai DLF Chenn India East
ai
9 Pune Hinjewadi Pune India East
1 IN-HYD- Hydera India East
0 HYDERABAD bad
(campus)
1 IN-KOL- Kolkat India East
1 UNITECHA2 a
1 Bangalore Campus Bangal India East
2 (whitefield) ore
1 Mumbai CKP Mumb India East
3 ai
1 IN-PNQ- Pune India East
4 TECHNOA1
(Talwade)
1 DE-FRA- Frankf Ger North EU
5 DCTAUBENST urt man
(FR1) y
1 Luxembourg Luxem Luxe North EU
6 bourg mbo
urg
1 NL-ALM-KPN Almere Neth North EU
7 (DC3) erlan
ds
1 NL-AMS-AMSDC Amster Neth North EU
8 dam erlan
(DCA) ds
1 GB-LDN-LONCITY Londo UK North EU
9 n
2 DE-FRA- Frankf Ger North EU
0 DCKRUPP urt man
(FR2) y
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_v0.9) Version: (V0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
4 BR-BAR- Sao Brazi West
3 ALPHA1930 Paulo l
4 CA-MIS- Toront Can West
4 MILLCREEK o ada
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_v0.9) Version: (V0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
Appendix C: Glossary
This appendix defines key abbreviations and acronyms contained in this document.
C1 Terms
Term Meaning
Review (e.g. of a deliverable prior to A formal documented review by one or more
delivery to the Business people, either from within or outside the
project team
Walkthrough (e.g. of a deliverable A peer group review of any deliverable
prior to delivery to the Business conducted by the project team members.
This should normally include the originator of
the deliverable
Inspection (e.g. of a deliverable prior A semi-formal check that the deliverable
to delivery to Business meets the specifications and conforms to
standards. This may not include the originator
of the deliverable
Formal Inspection (e.g. of a A formal methodical inspection (e.g. Gilb
deliverable prior to delivery to the Inspection)
Business
Testing (e.g. of a deliverable prior to A series of formal tests against a set of
delivery to the Business documented expected results. The types and
level of testing will depend on the stage of the
project
________________________________________________________________________________________________
Reference: (DGe\PGP-GPMT_v0.9) Version: (V0.9) Date: (October 19, 2017)
The information contained in this document is proprietary and confidential. It is for Capgemini internal use only. Copyright
2014 by Capgemini. All rights reserved.
________________________________________________________________________________________________