Using the AIA documents, what can the contractor expect to recover on his claim?
A. $2,700 but no extra time
B. $2,700 plus additional time and overhead
C. $700 but no extra time
D. $2,700 plus additional time, overhead and profit
Using the AIA documents, what can the contractor expect to recover on his claim?
A. $2,700 but no extra time
B. $2,700 plus additional time and overhead
C. $700 but no extra time
D. $2,700 plus additional time, overhead and profit (AIA 201 10.4 and AIA 201 7.3.7).