Analisa Pekerjaan Waterproofing

PEKERJAAN WATER
VIIPROOFING

M
1Screeding tebal 3 cm 2 semen 0.288zak
pasir beton 0.039m3
tukang batu 0.1org/hr
kepala tukang batu 0.01org/hr
pekerja 0.2org/hr
mandor 0.01org/hr

M
2Screeding tebal 2 cm 2 semen 0.2zak
pasir beton 0.026m3
tukang batu 0.1org/hr
kepala tukang batu 0.01org/hr
pekerja 0.2org/hr
mandor 0.01org/hr

Pekerjaan water proofing M


3(coating) 2 pre treatment/ cleaning 1m2
curbing sudut 0.4m'
bahan waterproofting
coating 2.5kg
sewa mixer 0.02bh
kuas 0.2unit
tukang batu 0.2org/hr
kepala tukang batu 0.02org/hr
pekerja 0.1org/hr
mandor 0.01org/hr

4Pekerjaan water proofing M material primer 0.3kg


(membrance) 2
water proofing membrnce 1.05m2
tukang batu 0.5org/hr
kepala tukang batu 0.05org/hr
pekerja 0.25org/hr
0.012
mandor 5org/hr

M
5Pekerjaan Floor Hardener 2 Material natural non metalic 6kg
Curing compound 0.125ltr
tukang batu 0.15org/hr
kepala tukang batu 0.015org/hr
pekerja 0.075org/hr
0.007
mandor 5org/hr