Professional Documents
Culture Documents
Monitoring Project Performance With Earned Value Management: Prepared By: Yves Tyrone R. Rosales
Monitoring Project Performance With Earned Value Management: Prepared By: Yves Tyrone R. Rosales
Value Management
You can determine the cost variance percentage (CVP) and the
schedule variance percentage (SVP) using the following
formulas:
CVP = CV ÷ EV x 100
SVP = SV ÷ PV x 100
Table 19-1 illustrates that a positive variance indicates something desirable (that is,
you’re either under budget or ahead of schedule) and a negative variance indicates
something undesirable (you’re either over budget or behind schedule)
Estimate at Completion
To determine the Estimate at Completion (EAC), your
estimate of the total expenditures for completing a WBS
element based on the expenditure history to date as
follows:
The milestone method is the most conservative and the least accurate. You
expect to spend some money while you’re working on the task.
However, this method doesn’t allow you to declare EV greater than $0 until
you’ve completed the entire activity. Therefore, you’ll always appear over
budget while you perform the activity.
Approaches to Estimate EV
50/50 method
EV is zero before you start the activity, 50 percent of the total
activity budget after you start it, and 100 percent of the activity
budget after you finish the activity.