Professional Documents
Culture Documents
The Optimum Selection of Power Cable For ESP System, Emad Ebsis - Faraj, 2016, 16 PG
The Optimum Selection of Power Cable For ESP System, Emad Ebsis - Faraj, 2016, 16 PG
By Emad Ebsis.Faraj
MSc Petroleum and Gas Engineering
Falcon_1979m@yahoo.com
Abstract
This paper discusses the method of power cable design for electrical submersible
pumps, a method which can result in a more optimal design that means solving the
problem of short operating life and more economically efficient ESP system. A
procedure is developed for estimating the maximum expected operating temperature
of the conductor for each cable size. Cable length, type and size selection was done
with the aim of minimizing the operating cost along with accomplishing the optimum
performance. An accurate selection of power cable insulation type can be made for
each cable size based upon the maximum operating conductor temperature. Total
cable investment cost can then be determined for each cable size. Power loss
calculations are also provided to predict the power cost of the cable. The final cable
selection can be determined by economic analysis.
Introduction
Electric submersible pump system is a major form of artificial lift in secondary
recovery operations. The optimum production conditions must be provided for an ESP
well to produce at its greatest potential and achieve a successful run life; therefore
ESP downhole and surface equipment must be designated and operated properly.
The ESP power cable is responsible for transmitting the required power to the motor
in the downhole. The ESP power cable is an important part of the system and its right
selection is vital technically and economically. The cable length, type and size must
be considered when designing ESP system.
It has been the practice to choose the smallest conductor size possible, in this manner
reducing the initial cost for the installation. This practice, in many cases, led to
incorrect economic judgement which costs the operator of the equipment a great deal
as well as reducing the life of the selected system.
Once the factors effecting the proper cable selection are recognized, then a computer
program can be effectively used to calculate and to print necessary data for optimum
power cable size.
2
Emad E. Faraj
The selected power cable length is shorter which will have an effect on the total
operating cost .The total monthly cost will be reduced to approximately 50% for the
new cable as shown in table 6.
The selection of cable size depends on technical and economic considerations. The
technical approach is mainly the physical dimensions (the cable fits in the annulus
between the casing string and the ESP unit), the motor current and the voltage drop
along the length of the cable.
The choice of cable size must be based on that the total voltage drop is less
than 30V/1000 ft of cable (rule of thumb).
And on the cable of total voltage drop less than 5% of the nameplate voltage of
the motor.
The voltage drop along the cable can be obtained from:
At motor current of 61.7 and the voltage drop value per 1000ft from chart in figure A-2
in appendix A is equal to:
3
Emad E. Faraj
AWG#1 , AWG#2 and AWG#4 total voltage drop are 8% ,10 % and 15%
respectively of the nameplate voltage of the motor (891 V). AWG#1 and AWG#2
which are closer to the standard value.
AWG#6 will be excluded as its total voltage drop at the motor nameplate current is
beyond the voltage drop limit of 30V/1000ft.
The calculations of the cost for selecting the optimum size of ESP cable are described
in the following part. An assumption which is illustrated in table 1 was made in order
to perform the cost calculations for selecting the power cable.
Cable Expected
60
life (Months)
Prime Interest Rate
12
%/year
Electricity Cost
5
C/KWh
4
Emad E. Faraj
Different power cables conductors specifications and prices are shown in table 3.
Table 2: Properties of Different Cable Sizes
Cable Resistance
Cable Size Price per length $/ft
Ohms/1000ft
AWG 1 0.139 11.92
AWG 2 0.170 10.46
AWG 4 0.271 8.71
The monthly operating cost is equal to the power consumed along the cable length per
month.
5
Emad E. Faraj
It is obvious from the table above that AWG# 2 is the best choice in term of cost, but
additional factor should be considered before taking final decision about the size of
the cable, which is the motor start-up voltage check.
6
Emad E. Faraj
The ratio of start-up voltage to motor nameplate voltage should be greater than 50%
of the nameplate voltage at the motor terminal to avoid possible start-up problems.
The ratios of start-up voltage to motor nameplate voltage for several cable conductors
are shown in table 4.
Based on the table above AWG#1, 2 and 4 provide sufficient voltage to the motor
terminal for successful start-up.
Since the main factor in selecting the power cable size is based on the total monthly
cost AWG# 2 is selected as it gives the most economical solution.
7
Emad E. Faraj
8
Emad E. Faraj
Table 7 presents a summary to the result of proposed ESP cable parameters obtained
both by simple calculations and Software simulation.
9
Emad E. Faraj
Conclusions
The challenge for any ESP system is to increase the profitability as well as reduce the
operating cost which is mainly the electricity bill and the workover operations.
Several types and sizes of cables may be acceptable in a certain well from a material
viewpoint. However, the final decision of which cable is the optimum choice should
be an economic one established on investment costs against operating costs.
The Outcome revealed that no much difference between the results obtained from
software simulation and hand calculations.
The proposed power cable is shorter than the existing one due to that the setting of the
proposed pump is at 4000ft instead of 5900ft this will reduce the power cable length
and the monthly cost from 2451$ to 1251 $ consequently, there will be an amount of
72,000$ saved over the expected life of the cable. Minimising the pump setting will
result in reducing the number of pump stages required to lift the liquid to the surface
and in turn less motor horse power. Also less voltage drop will result from decreasing
the cable length.
Acknowledgement
The author wishes to thank the many members of the Division of ESP in Gailo 59E
field who helped make this paper possible.
10
Emad E. Faraj
Nomenclature
A = Amperage
ESP = Electric Submersible Pump
F = Degree Fahrenheit
KV = Kilovolt
KVA = Kilowatts- Volts- Amperage
L = Cable Length ft
Mint = Monthly Interest Rate
MLE = Motor Lead Extension
n = Expected Life for Cable
PB = Monthly Pay Back
Pint = Prime Interest Rate
PL = Power Loss in the Cable
PSI = Pound per Square Inch
RT = Total Cable Resistance
V = Voltage
11
Emad E. Faraj
References
6. Vandevier, J. E.: "Optimum Power Cable Sizing for Electric Submersible Pumps",
SPE 1#16195.
12
Emad E. Faraj
Appendix
Figure A-1: Redahot Round Cable ampacity chart (amperage carrying capacity)
13
Emad E. Faraj
14
Emad E. Faraj
Design Data
===========
Pump Data
=========
Pump Intake Liquid Rate = 3708.61 STB/d
Pump Intake Free Gas Fraction = 4.06 %
Selected Pump = Reda : SN3600
Number of Stages = 32
Pump Efficiency = 69.46 %
Pump Power = 55.79 hp
Pump Intake Pressure = 998.97 psia
Pump Discharge Pressure = 1602.02 psia
Pump Head Required = 1496.97 ft
Liquid Density = 58.96 lb/ft3
Free Gas Fraction at Inlet = 0.04
15
Emad E. Faraj
Motor Data
==========
Selected Motor = Reda : 540_Series_S : Single
NP Power at 60 Hz = 62.50 hp
NP Voltage at 60 Hz = 825.00 volts
NP Current at 60 Hz = 46.00 amps
NP Power at Design Speed = 62.50 hp
NP Voltage at Design Speed = 825.00 volts
NP Current at Design Speed = 46.00 amps
Cable Data
==========
Cable Length = 4100.00 ft
Voltage Drop = 96.36 volts
Downhole Voltage = 825.00 volts
Surface Voltage = 921.36 volts
Total System KVA = 73.32
16