Alcatel-Lucent 9130
BSC Evolution | B12
Change IP Extraction Mode
9YZ-03803-1256-RJZZA
Issue 1 | August 2012
Legal notice
Legal notice
Alcatel, Lucent, Alcatel-Lucent and the Alcatel-Lucent logo are trademarks of Alcatel-Lucent. All other trademarks are the property of their respective
owners.
The information presented is subject to change without notice. Alcatel-Lucent assumes no responsibility for inaccuracies contained herein.
Copyright © 2012 Alcatel-Lucent. All rights reserved.
Note:
Prerequisites ..................................................................................................................................................................................... xx
1 Overview
2 Scenario
....................................................................................................................................................................................................................................
GSM iii
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Contents
....................................................................................................................................................................................................................................
Before Going Onsite
Scenario Description
Verify Connection Between 9153 OMC-R and Cisco Router ............................................................................... 2-34
2-34
....................................................................................................................................................................................................................................
iv GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
List of tables
....................................................................................................................................................................................................................................
GSM v
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
List of tables
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
vi GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
List of figures
1-1 9153 OMC-R - 9130 BSC Evolution in the Same Network, O&M over Ethernet ........................... 1-3
1-2 9153 OMC-R - 9130 BSC Evolution in the Different Network, O&M over Ethernet .................... 1-4
1-3 9153 OMC-R - 9130 BSC Evolution, O&M over Ater, Extraction at MSC ....................................... 1-5
1-4 9153 OMC-R - 9130 BSC Evolution, O&M over Ater, Extraction at TC ............................................ 1-6
....................................................................................................................................................................................................................................
GSM vii
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
List of figures
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
viii GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
About this document
About this document
Purpose
This document describes how to change the O&M extraction point for an 9130 BSC
Evolution.
It is applicable to BSS at technical release level B12.
Intended audience
This document is intended for:
• Field service technicians
• Specialists
• Project managers
• Foremen.
Supported systems
This document applies to Release B12 of the BSS
...................................................................................................................................................................................................................................
GSM ix
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
About this document
....................................................................................................................................................................................................................................
How to use this document
No specific recommendation applies regarding the way readers should read this
document.
Prerequisites
You must have a basic understanding of the following:
• Planning
Including:
– Network architecture and reshuffling principles
– Scheduling.
• Implementation
Including:
– Alcatel-Lucent operations and maintenance (O&M) concepts for the BSS
– GPRS concepts
– 9153 OMC-R operation
– Basic Cisco router knowledge
– Basic UNIX knowledge.
Conventions used
This section gives information on conventions.
Vocabulary conventions
None.
Typographical conventions
The following typographical conventions are used in this document:
Appearance Description
Italicized text Emphasized information.
graphical user interface text Text that is displayed in a graphical user interface or in a
hardware label.
Document reference, reference Related document that is referenced in the document.
number
Related information
None.
....................................................................................................................................................................................................................................
x GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
About this document
....................................................................................................................................................................................................................................
Document support
For support in using this or any other Alcatel-Lucent document, contact Alcatel-Lucent at
one of the following telephone numbers:
• 1-888-582-3688 (for the United States)
• 1-317-377-8618 (for all other countries)
Technical support
For technical support, contact your local Alcatel-Lucent customer support team. See the
Alcatel-Lucent Support web site (http://www.alcatel-lucent.com/support/) for contact
information.
How to order
To order Alcatel-Lucent documents, contact your local sales representative or use Online
Customer Support (OLCS) (http://support.alcatel-lucent.com)
How to comment
To comment on this document, go to the Online Comment Form (http://infodoc.alcatel-
lucent.com/comments/) or e-mail your comments to the Comments Hotline
(comments@alcatel-lucent.com).
....................................................................................................................................................................................................................................
GSM xi
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
About this document
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
xii GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
1 Overview
1
Overview
Purpose
This Overview gives information needed by project managers and foremen, for
presentation to the customer and for site planning.
Contents
Presentation 1-1
Preparation 1-9
Scheduling 1-16
Telecom / Supervision Outage and Operating Impact 1-17
Resources 1-18
Presentation
Overview
Use this scenario to change the O&M extraction point for an 9130 BSC Evolution.
The BSCs can have O&M over Ethernet or O&M over Ater, but one BSC cannot be used
with both O&M over Ethernet and O&M over Ater connections at the same time.
The Atermux links used for O&M transport must be consecutive. A dedicated GPRS
Atermux link cannot be used to carry O&M flow. If O&M transport is needed on a
dedicated Ater mux, use Move Dedicated GPRS Link into Direct CS Link or Move
Dedicated GPRS Link into Mixed CS / GPRS Link before starting the procedure to
change the O&M extraction point.
In both the initial and final states, the 9153 OMC-R is connected to the Ethernet LAN
using one IP link.
...................................................................................................................................................................................................................................
GSM 1-1
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Presentation
....................................................................................................................................................................................................................................
Together with O&M over Ater, O&M extraction at the MSC site decreases the cost of the
9153 OMC-R / BSC connection by using the BSS's own transport network instead of an
external IP network for the O&M data flow between the 9153 OMC-R and the remote
9130 BSC Evolution. When O&M is routed over Ater, if the MSC does not support the
SPC function, O&M must be extracted at the TC side.
In the case of O&M over Ethernet, the 9130 BSC Evolution communicates with the 9153
OMC-R via the active OMCP board through Ethernet switches. When the link through
one switch is out of order, the communication continues through the second Ethernet
switch if a redundant link is provided between the BSC and LAN.
In the case of O&M extraction at the TC or at MSC side, the 9130 BSC Evolution
communicates with the 9153 OMC-R using O&M over Ater through a number of Ater
links. The default and recommended value is four Ater for one 9130 BSC Evolution, but
any value between 2 and 16 can be configured. The bandwidth is proportional with the
number of Ater mux links having O&M timeslots allocated for this purpose.
The following figures illustrate the main solutions for O&M extraction:
• Direct O&M
• O&M over Ater, MSC Routed
• O&M over Ater, TC Routed.
In order to change O&M extraction point for more than one 9130 BSC Evolution, apply
the complete scenario for each BSC, one after another.
....................................................................................................................................................................................................................................
1-2 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Presentation
....................................................................................................................................................................................................................................
Figure 1-1 9153 OMC-R - 9130 BSC Evolution in the Same Network, O&M over
Ethernet
....................................................................................................................................................................................................................................
GSM 1-3
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Presentation
....................................................................................................................................................................................................................................
Figure 1-2 9153 OMC-R - 9130 BSC Evolution in the Different Network, O&M over
Ethernet
....................................................................................................................................................................................................................................
1-4 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Presentation
....................................................................................................................................................................................................................................
Figure 1-3 9153 OMC-R - 9130 BSC Evolution, O&M over Ater, Extraction at MSC
....................................................................................................................................................................................................................................
GSM 1-5
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Presentation
....................................................................................................................................................................................................................................
Figure 1-4 9153 OMC-R - 9130 BSC Evolution, O&M over Ater, Extraction at TC
Cases
The following cases apply:
• C1: Direct O&M changed into MSC Routed O&M:
....................................................................................................................................................................................................................................
1-6 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Presentation
....................................................................................................................................................................................................................................
As follows:
– C1.1: Direct (1 LAN) O&M changed into MSC Routed O&M
– C1.2: Direct (2 LANs) O&M changed into MSC Routed O&M
• C2: Direct O&M changed into TC Routed O&M:
As follows:
– C2.1: Direct (1 LAN) O&M changed into TC Routed O&M
– C2.2:Direct (2 LANs) O&M changed into TC Routed O&M.
• C3: MSC Routed O&M changed into TC Routed O&M
• C4: MSC Routed O&M changed into Direct O&M
As follows:
– C4.1: MSC Routed O&M changed into Direct (1 LAN) O&M
– C4.2: MSC Routed O&M changed into Direct (2 LANs) O&M
• C5: TC Routed O&M changed into Direct O&M
As follows:
– C5.1: TC Routed O&M changed into Direct (1 LAN) O&M
– C5.2: TC Routed O&M changed into Direct (2 LAN) O&M
• C6: TC Routed O&M changed into MSC Routed O&M
Options
None.
Restrictions
None.
....................................................................................................................................................................................................................................
GSM 1-7
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Presentation
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
1-8 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Presentation
....................................................................................................................................................................................................................................
Applicable Documents
You must have the following documents or have electronic access to the following
documents:
• BSS Methods Handbook
• BSS O&M Routing Configurations
• BSS Configuration Handbook
• BSS Surveillance Handbook
• Network Reconfiguration Recommendations
The specific documents applicable to this scenario are:
• BSC Terminal User Guide
• Operator Hints.
Preparation
Prerequisites
The following prerequisites apply:
• No other configuration modification is allowed in the network
• The corresponding router must be installed and configured.
For more details about how to install and configure router refer to the document BSS
O&M Routing Configurations .
• For C1 or C6:
As follows:
– The MSC must be operational and ready for the change
– Ensure you have enough available timeslots on the existing PCM link between the
MSC and Cisco router. Otherwise, ensure you have one more available port.
• For C2 or C3:
As follows:
– The TC must be operational and ready for the change.
– Ensure you have enough serial ports to connect each X.21 Ater mux carrying
O&M.
• For C1 or C2, verify that for each 9130 BSC Evolution, the Ater mux links intended
to be used for O&M over Ater are connected and operational
• Availability of a local PC.
The following sections describe the reserved IP addresses assignments for 1LAN / 2
LANs solutions .
....................................................................................................................................................................................................................................
GSM 1-9
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Preparation
....................................................................................................................................................................................................................................
IP Assignment Rules in 9130 BSC Evolution with 2 LAN Solution
This section describes IP reserved addresses for the 2 LAN solution that must be taken
into account.
....................................................................................................................................................................................................................................
1-10 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Preparation
....................................................................................................................................................................................................................................
In 2 LAN configuration SubnetB +5 and SubnetC +5 are used as external router address.
IP Assignment Rules in 9130 BSC Evolution with 1 LAN Solution
This section describes IP reserved addresses for the 1 LAN Solution that must be taken
into account.
If the one-LAN solution is chosen, Subnets B and C are no more used.
The boards can be directly accessed through an IP address in Subnets A.
No MLPPP on Ater is used in case of one-LAN.
IP Assignment in 9130 BSC Evolution External Subnet A :
....................................................................................................................................................................................................................................
GSM 1-11
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Preparation
....................................................................................................................................................................................................................................
Table 1-4 IP Assignment in 9130 BSC Evolution External Subnet A (continued)
Note: The recommended connection for the External Alarm Box is direct to the edge
Switch / Router.
Ar-OAMx is an available IP Address in the same subnet configured as gateway when
1 LAN Solution is used.
IP Assignment in 9130 BSC Evolution ASig Subnet:
....................................................................................................................................................................................................................................
1-12 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Preparation
....................................................................................................................................................................................................................................
IP Assignment in 9130 BSC Evolution BSS Subnet:
....................................................................................................................................................................................................................................
GSM 1-13
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Preparation
....................................................................................................................................................................................................................................
Table 1-7 BSC IP Parameters Usage (continued)
....................................................................................................................................................................................................................................
1-14 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Preparation
....................................................................................................................................................................................................................................
Table 1-7 BSC IP Parameters Usage (continued)
....................................................................................................................................................................................................................................
GSM 1-15
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Preparation
....................................................................................................................................................................................................................................
Table 1-7 BSC IP Parameters Usage (continued)
External Tasks
None.
Scheduling
Time based on technical constraints
In the following table, the number of resources shown does not take into account
individual customer or safety requirements.
....................................................................................................................................................................................................................................
1-16 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Scheduling
....................................................................................................................................................................................................................................
Notes:
1. ope. OMC-R operator
2. * task to be performed only if necessary
....................................................................................................................................................................................................................................
GSM 1-17
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Telecom / Supervision Outage and Operating Impact
....................................................................................................................................................................................................................................
Resources
Tools
The following tables describe the necessary hardware tools, software tools, and forms.
Hardware Tools
Software Tools
Forms
None.
....................................................................................................................................................................................................................................
1-18 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Resources
....................................................................................................................................................................................................................................
Supplies
....................................................................................................................................................................................................................................
GSM 1-19
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Overview Resources
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
1-20 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
2 Scenario
2
Overview
Purpose
This Scenario presents all checks needed before beginning the scenario, and all detailed
tasks to be performed on each site.
Contents
...................................................................................................................................................................................................................................
GSM 2-1
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Overview
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-2 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Preparation Before Going Onsite
Before Going Onsite
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
GSM 2-3
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Preparation Before You Start
Before You Start
....................................................................................................................................................................................................................................
Required Knowledge
You must be familiar with the following:
• Safety Rules and Precautions
• “Telecom / Supervision Outage and Operating Impact” (p. 1-17)
• Reverse Procedure
• “Grouped Task Sequence” (p. 1-7)
• Operating Hints
• How to document Faults and Anomalies.
....................................................................................................................................................................................................................................
2-4 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Scenario Description Overview
Scenario Description
....................................................................................................................................................................................................................................
Scenario Description
....................................................................................................................................................................................................................................
GSM 2-5
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Initial Checks
Scenario Description
....................................................................................................................................................................................................................................
Initial Checks
Global Checks
Perform the following checks:
...................................................................................................................................................................................................
1 Perform an Audit Alarm State on the BSSs and analyze the results.
Case/Option None.
Site OMC-R
Time/Task 10 min.
Outage None.
...................................................................................................................................................................................................
2 View Status of Managed Objects and Alarms (BSCs and BTSs) and print them.
Case/Option CHECK
Site OMC-R
Time/Task 10 min.
Outage None.
E...................................................................................................................................................................................................
N D O F S T E P S
1 In the DCN window, select the BSS and check that the link between OMC-R and BSC is
green.
Case/Option None.
Site OMC-R
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................
2 Check the IP Link Status in order to ensure that the IP connection is up:
In the OMC-R Terminal window, type:
ssh -l <username> <ip_address_of_BSC>
....................................................................................................................................................................................................................................
2-6 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Initial Checks
Scenario Description
....................................................................................................................................................................................................................................
When a question appears, type yes. When requested, type the corresponding password.
Case/Option None.
Site OMC-R
Time/Task 2 min.
Outage None.
...................................................................................................................................................................................................
3 Check the connection between the 9153 OMC-R and Cisco router.
Refer to “Verify Connection Between 9153 OMC-R and Cisco Router” (p. 2-34).
E...................................................................................................................................................................................................
N D O F S T E P S
....................................................................................................................................................................................................................................
GSM 2-7
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Change Extraction Point
Scenario Description
....................................................................................................................................................................................................................................
1 Before modifying the extraction point or before adding ML-PPP links, you must remove
the GPRS from the impacted Ater mux links. Perform the following actions for all
impacted Ater mux links:
• If it is the last GSL of the GP in a Multi-GP, Lock GPRS on Cells from GP to stop
GPRS on all cells mapped on the GP
• If it is the last GSL on the BSC, Lock GPRS on BSS
• If one of the previous two operations was performed, then Lock NS-VC
• If GSL is activated on the Ater mux, Lock GSL
• If TC transparency is enabled and Gb is configured through TC, delete Gb resources:
Delete NS-VC and Delete NSE
• Unreserve Ater Timeslots for GPRS
• If TC transparency is enabled, change it to disabled (mandatory)
• If GSL is activated on the Ater mux, when a question appears, click on OK
• The configuration state in the BSC part of the Ater Supervision window becomes In
progress. Wait until Available appears in this window.
• If the Abis/Ater window is opened, during the audit, the following message appears:
Abis/Ater view is not up to date! It will be reloaded! Click on
OK
• Align GPRS Configuration on One TP.
(The MFS part of the Ater Supervision window is then updated).
• Unlock Released CS Timeslot on concerned Ater mux links and verify (see “Display
A Channels Synthesis Window” (p. 2-32)) if the previous GPRS timeslots are now CS
timeslots and unlocked.
Case/Option None.
Site OMC-R
Time/Task 40 min. + 40 sec./ TS
Outage STARTO (reduction)
Refer to “Telecom / Supervision Outage and Operating Impact” (p. 1-17).
Note: Write down the GPRS configuration for all impacted Ater mux links, as you
need to set the GPRS to the initial values after successfully changing the extraction
point.
....................................................................................................................................................................................................................................
2-8 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Change Extraction Point
Scenario Description
....................................................................................................................................................................................................................................
Note: During the Unreserve Ater Timeslots for GPRS action, if the GSL is activated
on an Ater mux, it is implicitly deleted and the BSC automatically resets the second
DTC of that Ater mux.
...................................................................................................................................................................................................
5 Disconnect the X.21 cable between the TC corresponding board's X12 port and the serial
interfaces of the Router
....................................................................................................................................................................................................................................
GSM 2-9
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Change Extraction Point
Scenario Description
....................................................................................................................................................................................................................................
Case/Option C5 C6
Site TC
Time/Task 5 min.
Outage Outage-S
Reduction-O
...................................................................................................................................................................................................
6 Modify IP Parameters.
Some alarms may occur.
Note: Fill the corresponding fields with the required values needed for desired
configuration. For more information, refer to the “BSC IP Parameters Usage”
(p. 1-13) .
Case/Option None.
Site BSC
Time/Task 2 min.
Outage Outage-S
Reduction-O
Reduction-O'
Note: Wait for the Declare BSC Peer Entities report. Check that the status is
successful.
Note: The "IP Ethernet Protocol" parameter must be E_2 LAN if "Extraction
point" parameter is changed to "MSC Routed" or "TC Routed"
...................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-10 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Change Extraction Point
Scenario Description
....................................................................................................................................................................................................................................
Case/Option C1.2 C2.2 C3 C4.2 C5.2 C6
Site BSC
Time/Task 2 min.
Outage Outage-S
Reduction-O
Reduction-O'
...................................................................................................................................................................................................
....................................................................................................................................................................................................................................
GSM 2-11
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Change Extraction Point
Scenario Description
....................................................................................................................................................................................................................................
Case/Option C4 C5
Site BSC
Time/Task 5 min.
Outage End-S
Reduction-O
...................................................................................................................................................................................................
12 Connect the X.21 cable between the TC related board and the serial interfaces of the
Router
Case/Option C2 C3
Site TC
Time/Task 5 min.
Outage End-S
Reduction-O
...................................................................................................................................................................................................
15 If the TC is a G2 TC, perform Disable SBLs, TC SBLs TC-ADAPT with number (4*i-2),
for i = 1 to n.
....................................................................................................................................................................................................................................
2-12 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Change Extraction Point
Scenario Description
....................................................................................................................................................................................................................................
Case/Option C1.2 C2.2 C3 C4.2 C5.2 C6
Site BSC
Time/Task 1 min.
Outage Outage-S
Reduction-O
...................................................................................................................................................................................................
16 If the TC is a G2 TC, Initialize SBLs, TC SBLs TC-ADAPT with number (4*i-2), for i =
1 to n.
Case/Option C1.2 C2.2 C3 C4.2 C5.2 C6
Site BSC
Time/Task 6 min.
Outage Outage-S
Reduction-O
...................................................................................................................................................................................................
18 Verify that the interfaces status is up for the interfaces used for O&M extraction (see
“Verify Router's Interfaces Status” (p. 2-32)).
If not, for DTC(4*i-2), with i = 1 to n, Reset SBLs.
If the protocol is still down, Disconnect GP Board and, after verifying that the interface
status is down for interfaces of all the n Ater mux (see “Verify Router's Interfaces Status”
(p. 2-32)),Cross-Connect GP Board. This last action implies a GPRS outage for all GPs to
which the Ater mux 1 to n belong.
....................................................................................................................................................................................................................................
GSM 2-13
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Change Extraction Point
Scenario Description
....................................................................................................................................................................................................................................
If the protocol is still down, Reset SBLs for CPR 3 and 4.
If the protocol is still down, even after this operation, Restart SBLs for the BSC SBL.
Case/Option None.
Site 9153 OMC-R, BSC
Time/Task 10 min.
Outage Reduction-O
...................................................................................................................................................................................................
20 If the TC is a G2 TC, verify the CRC4 and modify it if necessary, with Enable/Disable
ATBX CRC4 Process.
Case/Option None.
Site TC
Time/Task 1 min.
Outage Reduction-O
...................................................................................................................................................................................................
21 When the new O&M routing solution is operational, an automatic audit (Software, PM,
Trace and, if the interruption time is long enough, an Alarm State audit) is launched on
the BSS.
Otherwise, “Verify Connection Between Router and MSC / TC” (p. 2-36) and “Verify
Connection between BSC and Router” (p. 2-38).
If the tests are unsuccessfully, use the method with the appropriate case to get back to the
initial configuration.
....................................................................................................................................................................................................................................
2-14 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Change Extraction Point
Scenario Description
....................................................................................................................................................................................................................................
Case/Option None.
Site OMC-R
Time/Task 10-20 min.
Outage Reduction-O
...................................................................................................................................................................................................
23 For each Ater mux configured with GPRS, Align GPRS Configuration on One TP.
Case/Option None.
Site OMC-R
Time/Task 1 min.
Outage Reduction-O
...................................................................................................................................................................................................
24 Using the parameters noted when removing GPRS, for each Ater mux on which the
GPRS configuration was set to 0%, perform the following operations:
• Configure GPRS Granularity, setting the GPRS ratio, GSL activation and TC
transparency to initial values
• In the MFSUSM window, the configuration state in the BSC part of the Ater
Supervision window becomes "In progress". Wait until "Available" appears in this
window
• If the Abis/Ater window is open during the audit, the following message appears:
Abis/Ater view is not up to date! It will be reloaded! Click on
OK
• Align GPRS Configuration on One TP
(The MFS part of the Ater Supervision window is then updated).
....................................................................................................................................................................................................................................
GSM 2-15
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Change Extraction Point
Scenario Description
....................................................................................................................................................................................................................................
If the GSL is activated on the Ater mux, Unlock GSL.
If the NSE and NS-VC were deleted Create NSE and Create NS-VC
Unlock NS-VC, if needed.
Unlock GPRS on Cells from GP to start GPRS on all cells mapped on the GP. Otherwise
use Unlock GPRS Traffic on Cell to start GPRS on all cells which are mapped on the GP.
If GPRS is locked on the BSS, Unlock GPRS on BSS.
Case/Option None.
Site OMC-R
Time/Task 40 min.
Outage END-O
Refer to “Telecom / Supervision Outage and Operating Impact” (p. 1-17).
Note: During the GPRS granularity configuration action, if the GSL is created on
an Ater mux, the BSC automatically resets the second DTC on that Ater mux.
E...................................................................................................................................................................................................
N D O F S T E P S
....................................................................................................................................................................................................................................
2-16 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Add ML-PPP Links
Scenario Description
....................................................................................................................................................................................................................................
E...................................................................................................................................................................................................
N D O F S T E P S
1 Launch the Windows 9130 BSC Evolution Terminal application from the desktop.
...................................................................................................................................................................................................
2 Type the floating IP address of the 9130 BSC Evolution, and click on OK.
...................................................................................................................................................................................................
3 In the bottom status bar, check that the User Mode status is Master.
...................................................................................................................................................................................................
....................................................................................................................................................................................................................................
GSM 2-17
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Add ML-PPP Links
Scenario Description
....................................................................................................................................................................................................................................
...................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-18 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Add ML-PPP Links
Scenario Description
....................................................................................................................................................................................................................................
Add ML-PPP Links on 9153 OMC-R
Add the required number of ML-PPP links on an 9153 OMC-R:
...................................................................................................................................................................................................
....................................................................................................................................................................................................................................
GSM 2-19
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Add ML-PPP Links
Scenario Description
....................................................................................................................................................................................................................................
ML-PPP# exit
E...................................................................................................................................................................................................
N D O F S T E P S
....................................................................................................................................................................................................................................
2-20 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Remove ML-PPP Links
Scenario Description
....................................................................................................................................................................................................................................
E...................................................................................................................................................................................................
N D O F S T E P S
1 Launch the Windows 9130 BSC Terminal application from the desktop.
...................................................................................................................................................................................................
2 Type the floating IP address of the 9130 BSC Evolution, and click on OK.
...................................................................................................................................................................................................
3 In the bottom status bar, check that the User Mode status is Master.
...................................................................................................................................................................................................
....................................................................................................................................................................................................................................
GSM 2-21
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Remove ML-PPP Links
Scenario Description
....................................................................................................................................................................................................................................
...................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-22 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Remove ML-PPP Links
Scenario Description
....................................................................................................................................................................................................................................
Remove ML-PPP Links from 9153 OMC-R
Remove ML-PPP links from an 9153 OMC-R:
...................................................................................................................................................................................................
E...................................................................................................................................................................................................
N D O F S T E P S
....................................................................................................................................................................................................................................
GSM 2-23
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario ML-PPP Post Activities Tasks
Scenario Description
....................................................................................................................................................................................................................................
2 If the TC is a G2 TC, Disable SBLs, TC SBLs TC-ADAPT with number (4*i-2), for i = 1
to n.
Case/Option None.
Site BSC
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................
3 If the TC is a G2 TC, Initialize SBLs, TC SBLs TC-ADAPT with number (4*i-2), for i =
1 to n.
....................................................................................................................................................................................................................................
2-24 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario ML-PPP Post Activities Tasks
Scenario Description
....................................................................................................................................................................................................................................
Case/Option None.
Site BSC
Time/Task 6 min.
Outage None.
...................................................................................................................................................................................................
4 If necessary (if they are not in traffic in 10 minutes), Disable SBLs of BSC
(ATER_HWAYTP/1 to ATER_HWAYTP/n, ATR/(4*i-2) for i = 1 to n) and of TC
(A_PCM_TP/(4*i-2) for i = 1 to n, ATER_HWAYTP/1 to ATER_HWAYTP/n) and then
Initialize SBLs of BSC (ATER_HWAYTP/1 to ATER_HWAYTP/n, ATR/(4*i-2) for i = 1
to n) and of TC (A_PCM_TP/(4*i-2) for i = 1 to n, ATER_HWAYTP/1 to
ATER_HWAYTP/n).
Case/Option None.
Site BSC
Time/Task 40 min.
Outage None.
...................................................................................................................................................................................................
5 Verify that the interface status is up for the interfaces used for O&M extraction (see
“Verify Router's Interfaces Status” (p. 2-32)).
If not, for DTC(4*i-2), with i = 1 to n, Reset SBLs.
If the protocol is still down, Disconnect GP Board and, after verifying that the interface
status is down for timeslots 31 of all the n Ater mux, (see “Verify Router's Interfaces
Status” (p. 2-32)), Cross-Connect GP Board.
This last action implies a GPRS outage for all GPs where Ater mux 1 to n belong.
If the protocol is still down, Reset SBLs for CPR 3 and 4.
If the protocol is still down, even after this operation, Restart SBLs for the BSC SBL.
Case/Option None.
Site OMC-R, BSC
Time/Task 10 min.
Outage None.
...................................................................................................................................................................................................
6 If the TC is a G2 TC, verify the CRC4 and modify it if necessary, with Enable/Disable
ATBX CRC4 Process.
....................................................................................................................................................................................................................................
GSM 2-25
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario ML-PPP Post Activities Tasks
Scenario Description
....................................................................................................................................................................................................................................
Case/Option None.
Site TC
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-26 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Verify ML-PPP Configuration
Scenario Description
....................................................................................................................................................................................................................................
1 In the case of O&M over Ater with extraction at the MSC side or O&M over Ater with
extraction at the TC side with only one router, connect to the Cisco router and type the
password when requested:
telnet <Router IP address>
<hostname> >en
<hostname> > Password:
Type the appropriate password.
Case/Option None.
Site BSC
Time/Task 1 min.
Outage None.
...................................................................................................................................................................................................
2 In the case of O&M over Ater with extraction at the TC side with two routers, connect to
the router nearest to the 9153 OMC-R:
telnet <IP address of the router near OMC-R>
<hostname> > en
<hostname> > Password:
Type the appropriate password.
From this router, connect to the router near the TC:
telnet <IP address of the router near TC>
<hostname> > en
<hostname> > Password:
Type the appropriate password.
...................................................................................................................................................................................................
....................................................................................................................................................................................................................................
GSM 2-27
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Verify ML-PPP Configuration
Scenario Description
....................................................................................................................................................................................................................................
All member links (already existing and newly created) are not allowed not be shown as
inactive.
E...................................................................................................................................................................................................
N D O F S T E P S
....................................................................................................................................................................................................................................
2-28 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Verify O&M over Ater Link on BSC
Scenario Description
....................................................................................................................................................................................................................................
File Transfer
To verify proper operation of FTP, perform a file transfer. To test the file transfer, copy a
single BSS file from a specific BSS to the 9153 OMC-R.
Test the file transfer:
...................................................................................................................................................................................................
3 In the right panel of the gFTP window, designated for the remote BSC File List, select a
BSS file.
....................................................................................................................................................................................................................................
GSM 2-29
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Verify O&M over Ater Link on BSC
Scenario Description
....................................................................................................................................................................................................................................
...................................................................................................................................................................................................
4 In the left panel of the gFTP window, designated for the OMC (local) File List, select a
target directory.
...................................................................................................................................................................................................
5 To copy the BSS File, press the key with a left pointing arrow.
...................................................................................................................................................................................................
6 In the left panel with the OMC (local) File List, check if the file copy was successful.
...................................................................................................................................................................................................
7 In the left panel with the OMC (local) File List, select the file you have just copied and
delete it by selecting Local->Delete. Confirm the delete with Yes.
...................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-30 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Final Checks
Scenario Description
....................................................................................................................................................................................................................................
Final Checks
Procedure
Perform the final checks:
...................................................................................................................................................................................................
....................................................................................................................................................................................................................................
GSM 2-31
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Display A Channels Synthesis Window
Scenario Specific Tasks
....................................................................................................................................................................................................................................
1 In the Functional Alarm Synthesis View of the BSSUSM Main View, click on the BSS
field.
...................................................................................................................................................................................................
2 In the GSM Functional View, select the BSS with the left mouse button.
...................................................................................................................................................................................................
4 Click and hold down the right mouse button and select ACH Synthesis.
Result: The A Channels Panel window appears.
...................................................................................................................................................................................................
5 For i = 1 to n (where n is the number of Ater links intended to be used for O&M in the
BSC), in the Tp Id field, type the number corresponding to (4*i-2) to see the timeslot
allocation on the related A Channel for Ater mux i. Click on Display Ts.
E...................................................................................................................................................................................................
N D O F S T E P S
....................................................................................................................................................................................................................................
2-32 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Verify Router's Interfaces Status
Scenario Specific Tasks
....................................................................................................................................................................................................................................
Now you can see if the port and protocol status related to the serial
Interfaces/multilink/ethernet interfaces used is up.
....................................................................................................................................................................................................................................
GSM 2-33
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Verify Connection Between 9153 OMC-R and Cisco Router
Scenario Specific Tasks
....................................................................................................................................................................................................................................
2 Type the password when asked. If the password is not requested, refer to BSS O&M
Routing Configurations to check the physical connections between the 9153 OMC-R
LAN and the Cisco router, and the firewall settings for 9153 OMC-R LAN gateway.
...................................................................................................................................................................................................
4 If the success rate is 0 %, refer to BSS O&M Routing Configurations and check the Cisco
router setup and the firewall settings for the router.
E...................................................................................................................................................................................................
N D O F S T E P S
2 Type the password when asked. If the password is not requested, refer to BSS O&M
Routing Configurations to check the physical connections between the 9153 OMC-R
LAN and Cisco router, and the firewall settings for the 9153 OMC-R LAN gateway.
...................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-34 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Verify Connection Between 9153 OMC-R and Cisco Router
Scenario Specific Tasks
....................................................................................................................................................................................................................................
...................................................................................................................................................................................................
4 If the success rate is 0 %, refer to BSS O&M Routing Configurations and check the Cisco
router setup and the firewall settings for this router.
...................................................................................................................................................................................................
5 Run the following commands on the Cisco router near the OMC-R:
<hostname> > en
<hostname> > Password:
Type the appropriate password.
<hostname> > show ppp multilink
Identify the interface name of the PPP multilink which connects the two Cisco routers and
the name of the member links.
<hostname> > show interface <PPP Multilink Interface towards the Cisco
router near TC>
Verify that the interface is up-up.
<hostname> > show ip interface brief
Verify that all member link parts of the ML-PPP are up-up.
If any of the above two checks does not provide the correct result, refer to BSS O&M
Routing Configurations and check the setup of the two routers and the physical PCM
connection between them.
E...................................................................................................................................................................................................
N D O F S T E P S
....................................................................................................................................................................................................................................
GSM 2-35
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Verify Connection Between Router and MSC / TC
Scenario Specific Tasks
....................................................................................................................................................................................................................................
1 Connect to the Cisco router and type the password when requested:
telnet <Cisco Router IP address>
<hostname> > en
<hostname> > Password: <type the appropriate password>
<hostname> > show ppp multilink
...................................................................................................................................................................................................
2 Identify the interface name of the PPP multilink which connects the router to the MSC /
TC, and the name of the member links.
<hostname> > show interface <PPP Multilink Interface towards MSC/TC>
Verify that the interface is up-up.
<hostname> > show ip interface brief
Verify that all member link parts of the ML-PPP are up-up.
E...................................................................................................................................................................................................
N D O F S T E P S
1 Connect to the Cisco router near TC and type the password when requested:
telnet <IP address of Router near TC>
<hostname> > en
....................................................................................................................................................................................................................................
2-36 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Verify Connection Between Router and MSC / TC
Scenario Specific Tasks
....................................................................................................................................................................................................................................
<hostname> > Password: <type the appropriate password>
<hostname> > show ppp multilink
...................................................................................................................................................................................................
2 Identify the interface name of the PPP multilink which connects the Cisco router near the
TC and the TC, and the name of the member links.
<hostname> > show interface <PPP Multilink Interface towards TC>
Verify that the interface is up-up.
<hostname> > show ip interface brief
Verify that all member link parts of the ML-PPP are up-up.
E...................................................................................................................................................................................................
N D O F S T E P S
....................................................................................................................................................................................................................................
GSM 2-37
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012
Scenario Verify Connection between BSC and Router
Scenario Specific Tasks
....................................................................................................................................................................................................................................
1 From the local BSC terminal, connect to the active OMCP and type the password when
requested:
telnet <active OMCP IP address>
telnet <IP address of Cisco router>
Type the appropriate password when required.
...................................................................................................................................................................................................
....................................................................................................................................................................................................................................
2-38 GSM
9YZ-03803-1256-RJZZA B12
Issue 1 August 2012