LAPORAN KERJA HARI KE 25

Nama Pekerjaan : Perkuatan struktur gedung Trans Samudera


Lokasi : PT ELNUSA - TB SIMATUPANG
Pemberi Tugas : PT. ELNUSA - ETSA
Tahun : 2010

BOBOT 12 WAKTU PELAKSANAAN 25 Hari


NO. URAIAN PEKERJAAN KET
(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

10 98.9 99.9 100


I PEKERJAAN PERSIAPAN 3.39 1.70 1.70 96.9
93.9
1 Test Covid-19 88.9
85.9
2 Persiapan safety 82.5
8
77.5
3 Mob Demob
71.5
66.1
II Pekerjaan Sipil
6
1 4.05 2.03 2.03 58.1
Bongkar plafon/karpet / Meja
2 Pekerjaan galian fondasi P1,P2,P3,P4 2.83 0.71 0.71 0.71 0.71 48.1

3 Pekerjaan Pengecoran Fondasi P1,P2,P3,P4 12.40 4 4.13 4.13 4.13 40


4 Pekerjaan Pemasangan base plate/ tiang/balok/anak balok 57.45 6.38 6.38 33.3
6.38 6.38 6.38 6.38 6.38 6.38 6.38

III Pekerjaan Finishing 26.9

1 Pemasangan Plafon 13.79 2 19.8 3.45 3.45 3.45 3.45


15.7
2 Perapian balok , bungkus gypsum 6.09 10.1 11.6 1.52 1.52 1.52 1.52
8 8.7 9.4
5.9
2
-
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

JUMLAH 100.00

RENCANA PROGRES SESUAI TANGGAL (%)= 0.00 1.70 3.7 2.0 0.7 0.7 0.7 4.8 4.1 4.1 6.4 6.4 6.4 6.4 6.4 6.4 6.4 6.4 6.4 3.4 3.4 3.4 5.0 1.5 1.5 1.5

RENCANA PROGRES KOMULATIF(%)= 0.00 1.70 5.4 7 8 9 10 14 19 23 29 35 42 48 55 61 67 74 80 84 87 90 95 97 98 100

REALISASI PROGRES SESUAI TANGGAL (%) 0.00 2 3.9 2.1 0.7 0.7 0.7 1.5 4.1 4.1 7.1 6.4 6.7 8.1 10 8 5.4 6 5 3.4 3 5 3 2 1 0.1
REALISASI PROGRES KOMULATIF(%)= 0.00 2 5.9 8 8.7 9.4 10.1 11.6 15.7 19.8 26.9 33.3 40 48.1 58.1 66.1 71.5 77.5 82.5 85.9 88.9 93.9 96.9 98.9 99.9 100

SELISIH(DEVIASI ) SESUAI TANGGAL (%)= 0.00 0.3 0.2 0.1 - 0.0 - 0.0 - 0.0 - 3.3 - 0.0 - 0.0 0.7 0.0 0.3 1.7 3.6 1.6 - 1.0 - 0.4 - 1.4 - 0.0 - 0.4 1.6 - 2.0 0.5 - 0.5 - 1.4

SELISIH (DEVIASI) KOMULATIF(%)= 0.00 0.3 0.477 0.551 0.544 0.537 0.53 -2.81 -2.844 -2.877 -2.161 -2.145 -1.829 -0.112 3.504 5.12 4.136 3.752 2.369 2.322 1.876 3.429 1.461 1.94 1.419 0

jakarta , 12 April 2021

PT. Putra Karya Mandiri PT. Elnusa Trans Samudera

Suparnadi Ari Wibowo Dwi Binanda Putra


( Project Manager ) ( Procourement Manager )