Professional Documents
Culture Documents
Sub Station 1
Sub Station 1
For: By:
OBJECTIVE
1
CRITERIA FOR SELECTION OF
FEEDERS
EXISTING SYSTEM
Shorapur MUSS
2
Annexure − 1
Lightning CT CT
Wave Trap
Arrestor
10 MVA 10 MVA
110 / 33 kV Power Transformer 110 / 11 kV Power Transformer
CT
U. G Cable (XLPE)
Lightning Arrestor 2 x 300 Sq.mm
33 kV Isolator
CT CT
11 kV Bus
33 kV Isolator
11 kV V. C. B.
CT
33 kV Bus
33 kV Isolator
11 kV Isolator
33 kV
SF6 Circuit Breaker
Lightning Arrestor
Lightning Arrestor
110/11-kV 110/33-kV
F1 F2 F3 F4
33/11-kV Hunsgi 33/11-kV Kembhavi
12.4 10.2 7.7 15.29 MU
9.59 MU
From R. Kollur
0.73 MU
F1 F2 F3 F4 F1 F2 F3
4.0 4.24 7.04 5.2 1.02 3.37
3
Feeder wise IP-sets at Shorapur sub-station
1852
110/11-kV 110/33-kV
1009 843
F1 F2 F3 F4
33/11-kV Hunsgi 33/11-kV Kembhavi
660 61 178 110 555
288
From R. Kollur
0.73 MU
F1 F2 F3 F4 F1 F2 F3
117 37 201 200 46 31 211
TECHNICAL ANALYSIS
METHODOLOGY
4
TECHNICAL ANALYSIS (Cont’d)
110/33/11 kV
MUSS
Index
25 kVA DTC 100 kVA DTC
63 kVA DTC 250 kVA DTC
5
TECHNICAL ANALYSIS - HT Feeder
6
Single Line Diagram of Distribution under − 100 kVA Post Master DTC− Devapur
P
P 10 HP
10 HP
10 HP
P
P
7.5 HP
P
10 HP
7.5 HP
P
P 10 HP P 7.5 HP
Index Network Details DrgNo.: C7/VS−LT3/15
HT Line Pole P IP−Set Total Connected Load : 72.5 HP
7
TECHNICAL ANALYSIS - HT Feeders
CONCLUSION
DESIGN OF UP-GRADATION
Shorapur MUSS
8
DESIGN OF UP-GRADATION
METHODOLOGY
DESIGN OF UP-GRADATION
OPTIONS FOR HT FEEDERS
yBifurcation of feeders
- w.r.t load and line length
yRe-conductoring of feeders
- re-conductoring of major/trunk lines
9
DESIGN OF UP-GRADATION
OPTIONS FOR LT FEEDERS
110/33/11 kV
MUSS
Index
25 kVA DTC 100 kVA DTC Existing Conductor Replaced with Rabbit
63 kVA DTC 250 kVA DTC
Feeder Details
Drg. No. : Sld/Sho−Twn/03 (a)
25 kVA DTC : 03 Nos 100 kVA DTC : 21 Nos Ref : C7/VS 3EC
63 kVA DTC : 16 Nos. 250 kVA DTC: 05 Nos Note: All Dimensions are in kM
Line Length − HT : 46 kM
10
TECHNICAL ANALYSIS - HT Feeders, MODIFIED
CONCLUSION
11
Modified Single Line Diagram of Distribution under − 100 kVA Post Master DTC− Devapur
25 kVA DTC
(New)
P
A 10 HP
P
10 HP
10 HP
P
25 kVA DTC P
(New)
7.5 HP
Existing Transformer
to be removed E
P
10 HP
16 kVA DTC
7.5 HP (New)
10 HP
P P
16 kVA DTC 25 kVA DTC
(New) (New)
C D
P 7.5 HP
Index Proposed Modifications
HT Line Pole P IP−Set Existing 63 kVA DTC to be dismantled
Addition of New DTC (10,16&25 kVA)
DTC LT Line Reconductoring −section A−B−C−D−E
DrgNo.: C7/VS−LT3/15(a)
12
FINANCIAL ANALYSIS
Shorapur MUSS
13
PROJECTED SAVINGS & PAYBACK
(For network up-gradation only)
Present energy flow : 55.6 MU
Modified energy flow : 42.8 MU
Anticipated savings : 12.8 MU / annum
Estimated energy usage : 3600 hours / annum
Savings in Rs. Lakhs : 321.12
14
PROJECTED INVESTMENT & PAYBACK
(For Network up-gradation & IP-sets replacement )
CONCLUSION
yThe study reveals that a financially attractive
solution for loss reduction exists in this area
ythe avg. losses in the feeders is estimated
around 15.9 MU (27.4 %) & this can be
reduced to 4.73MU, for revised energy flow of
42.8 MU. The saved energy of 12.84 MU sold
to KPTCL at Rs. 2.50 will generate a revenue
of 321.12 Lakhs Per year
ythe investment for the project would be
about 1,394.4 Lakhs with a simple pay back
of 4.4 Years.
15
CONCLUSION (Cont’d)
16