S.N Location Dia. of Bar No. of Units No.S CUT Length #3 #3 #4 #6 #8
S.N Location Dia. of Bar No. of Units No.S CUT Length #3 #3 #4 #6 #8
S.N Location Dia. of Bar No. of Units No.S CUT Length #3 #3 #4 #6 #8
#3 2 3 14.00 84
#3 2 3 16.00 96
#3 2 3 15.00 90
#3 2 3 14.00 84
#3 2 3 8.00 48
#3 2 3 18.00 108
KOMAL ASSOCIATES
BAR BENDING SCHEDULE FOR GROUND FLOOR SLAB 2
#3 2 3 18.00 108
#3 2 3 17.00 102
#3 2 3 15.00 90
#3 2 3 18.00 108
#3 2 3 17.00 102
#3 2 3 10.00 60
BEAM
1 B4 #4 1 2 40.00 80
#6 1 3 40.00 120
KOMAL ASSOCIATES
BAR BENDING SCHEDULE FOR GROUND FLOOR SLAB 3
2 B5 #4 1 4 64.00 256
#6 1 5 64.00 320
3 B6 #6 1 2 46.00 92
#6 1 5 46.00 230
4 B7 #4 1 3 15.00 45
#6 1 4 15.00 60
5 B8 #6 1 2 33.00 66
#6 1 5 33.00 165
6 B9 #4 1 2 9.00 18
#6 1 2 9.00 18
#3* 1 18 3.00 54
7 B10 #4 1 2 14.00 28
#6 1 4 14.00 56
8 SEC 3 #4 1 2 27.00 54
#6 1 3 27.00 81
9 SEC2 #3 1 2 10.00 20
#3 1 2 10.00 20
#3* 1 20 3.50 70
KOMAL ASSOCIATES
BAR BENDING SCHEDULE FOR GROUND FLOOR SLAB 4
MATERIALS REQUIRED
CONCRETE 1:2:4
B4 1 40 0.75 0.25 8
2
B5 1 64 1.25 0.25 20
3
B6 1 46 0.75 1.25 43
4
B7 1 15 1 0.25 4
5
B8 1 33 0.75 0.75 19
6
B9 1 9 0.75 0.5 3
7
B10 1 14 0.75 0.75 8
8
1:2:4 TOTAL
KOMAL ASSOCIATES