Professional Documents
Culture Documents
Presentation-4 - Flexibility of Thermal Power Plants - v2 - FPE - V2
Presentation-4 - Flexibility of Thermal Power Plants - v2 - FPE - V2
Presentation-4 - Flexibility of Thermal Power Plants - v2 - FPE - V2
power plants
Flexible coal power generation as a key to
incorporate larger shares of renewable
power
Frank Peter
14.11.2018, JAKARTA
From a pragmatic point of view, existing coal power plants are
likely to continue to play a role in several countries during the
transition period towards renewable energy systems.
China (72%)
921
United States (39%)
287
145 65
0
Japan (34%)
UK (30%)
44 4 3
13 0.4
Korea (43%)
Poland (81%) 6 2.5
33
27 4
Vietnam (24%)
Germany (45%) 13 15 12
53 Turkey (30%)
0.6
16 3 22 Indonesia (53%)
(X%) : Share of coal in India (75%) 26
211 27 8
power production South Africa (87%)
Australia (61%)
plants
Operating (GW)
Coal
40 8 2.3 48
Construction (GW) 39
26 1.3 1.2
Announced (GW)
Making conventional power plants more flexible can be a key
strategy to integrate large shares of renewables.
Renewable and conventional power production during two examplary days
In several countries, the development of renewables is
in a system with 60% RES in 2030 often hampered after reaching a certain level, because of
the claim that the existing power system cannot cope with
the weather dependent electricity generation of wind and
solar plants.
→ What are current technical parameters regarding the flexibility of thermal power plants?
→ What retrofit measures could increase the flexibility of coal power plants?
→ What are the technical and economic parameters of flexible coal (retrofit)?
→ What are the impact of flexible coal on costs, lifetime and CO2 emissions?
→ What regulatory framework and market design could incentivize flexibility of thermal power plants
without locking the respective power system into a high-carbon dependency?
Effects of Expanded
Renewables on
Conventional
Generation
Increasing requirements for flexible operation arise from
increasing shares of renewable generation.
Flexibility requirements with high share of renewables. Example load curves for two weeks during the winter in Germany
Prognos
Renewables also impact the operation pattern of thermal
power plants of vertical integrated electricity suppliers
Decreasing utilisation of conventional plants due to increasing shares of
renewable energy production (Merit-Order Effect) In vertically integrated power markets power
generators usually rely on long-term supply
contracts. Typically, the contracts cover the full
costs of the expected electricity supply. However
supplier use a marginal costs approach to optimize
the operation of their fleet of plants.
In contrast to thermal power stations, wind and PV
have low or zero marginal costs. Therefore,
renewable energies integrate at the beginning of
the merit order, pushing conventional technologies
further out on the merit order.
This has two effects: Firstly, the utilisation rate of
power plants tends to decrease — especially
during times of high renewable energy production
and low demand. Secondly, the average
generation costs of conventional plants increase
due to lower utilization. Both effects decrease the
Prognos profitability of thermal power plants.
Congestion management and renewables curtailment
Relationship between monthly wind generation and monthly redispatch volumes
in Germany (Jan. 2013–Oct. 2016) → Even in Germany, higher wind generation is
causing higher curtailment rates
→ Flexibility needs of the power markets are
required when introducing larger shares of
variable renewable generation
→ Flexibility can be derived from various
resources:
✓ Generation technologies
✓ Grid interconnections
✓ Storage technologies
✓ Demand side measures
Fichtner (2017)
Overview of thermal generation technologies
Overview of thermal generation technologies by fuel type
Fichtner (2017)
What are current
technical parameters
regarding the
flexibility of thermal
power plants?
Flexibility of a power plant is the ability to adjust the net
power fed into the grid, its overall bandwidth of operation
and the time required to attain stable operation when starting
Qualitative representation of key flexibility parameters of a power plant The 3 key parameters of operational flexibility are :
1/ minimal load Advantage : The lower the minimal
load, the larger the range of generation output.
Disadvantages : at minimum load the power plant
operate at low efficiency. Limitations : at low load, it
is difficult to ensure a stable combustion.
2/ start-up time Advantage : The shorter the start-
up time, the quicker a power plant can reach
minimum load. Disadvantages : faster start-up
times put greater thermal stress on components.
Limitations : thermal gradient for components.
3/ ramp rate Advantage : A higher ramp rate allows
a power plant operator to adjust net output more
rapidly. Disadvantage : rapid change in firing
temperature results in thermal stress. Limitations :
allowable thermal stress and unsymmetrical
deformations, storage behavior of the steam
generator, quality of fuel used, time lag between
Fichtner (2016) coal milling and turbine response.
Comparison of power plants with most commonly used
technologies and power plants with state-of-the-art
technologies for each generation type
Comparison on minimum load Comparison on ramp rate
Comparison of most commonly used power plants and state-
of-the-art technologies for each generation type with regard to
start-up time
Hot start-up time (interrupted < 8h) Cold start-up time (interrupted >48h)
Example
Comparison of three state-of-the-art coal-fired power plants in Poland and Germany
Fichtner (2017); * The values in italics represent the average values for state-of-the-art power plants
State-of-the-art-design improves significantly the flexibility
characteristics of fossil-fuel power plants
Minimum load of different hard coal power plants (as a percentage Ramp rates of hard coal power plants in South Africa compared to
of nominal capacity) most-commonly used and state-of-the-art designs
60% 7%
40%
minute
4%
30%
3%
20%
2%
10% 1%
0% 0%
Typical hard coal Most-commonly used Example of retrofit in hard coal power most-commonly state-of-the-art
power plants in China and state-of the art Germany (Bexbach plants in South used hard coal coal power
and India hard coal power Unit)
Africa power plants plants
plants
Fichtner, 2017
Option 1: Indirect Firing
Net grid feed-in for indirect (IF) and direct firing (DF) configurations → The decoupling has the following effects:
▪ Stable fire at low load due to faster response to
fire instabilities
▪ Reducing net power fed into the grid by
maintaining nominal coal mill operation during
low load (e.g. at night)
▪ Improving milling efficiency (operation closer to
the design point)
▪ Reduced time lag between mills and burners
allows for a higher ramp rate during operation
Fichtner, 2017
Option 1: Indirect Firing
Result:
→ implementing indirect firing in combination with a staged vortex burner retrofit, led to a decrease in
minimum stable firing rate from 25-30% down to 10%. This leads to a similar reduction of
minimum load.
→ Another advantage of reaching such a low stable fire is that the need for ignition fuels, such as oil
or gas, was reduced by 95%
Option 2: Switching from two-mill to single-mill operation
Coal mill and burner arrangement of a boiler in tangential firing configuration
with four burner stages (single-mill operation) →Key idea: Operating with only one instead of
two mills in combination with a single burner
stage can reduce minimum load by achieving a
lower stable firing rate.
→During nominal power plant operation all of
the typically 4-6 coal mills are operating at full
load.
→In direct firing configuration, reducing the net
power of a power plant requires the burners and
the coal mills to both run in part load.
→Result:
→ At Bexbach (780 MW PNom ): 170 MW to 90
MW (12.5% PNom)
→ At Heilbronn unit 7 (800 MW PNom ) : 200 MW
Fichtner (2017) based on Heinzel, et al. (2012) to 100 MW (12.5% PNom)
Option 3: Upgrade of control system in combination with plant
engineering upgrades
Load curves for pre-retrofit and post-retrofit of Unit G and H at Weisweiler →Key idea: An improved control system leads to
faster, more precise and more reliable
monitoring and control of processes, which can
reduce the minimum load.
Results
→ Unit E: The retrofit led to a decrease of
minimum load from 440 MW to 290 MW,
resulted in an increase of efficiency by 0.6%
and an improved ramp rate .
The total cost amounted to 70 million euros.
→ Unit D: The retrofit achieved a reduction of
minimum load from 440 MW to 260 MW and
an increased ramp rate. In addition, positive
and negative control power can be delivered to
the market. Unit D also gained prequalification
for 75 MW of secondary control power.
Source: RWE Power AG, 2011]) (in the image: Boiler retrofit at Neurath)
Options for reducing
start-up time
Current limitations for reducing start-up time
Start-up time
defined as the period from starting plant operation
until reaching minimum load.
Reasons to decrease start-up time
it enables a more rapid response to power
demand. Start-up procedures are complex and
expensive since they usually require
supplementary fuel, such as oil or gas, during the
ignition period.
Major limitations
▪ Allowable thermal stress in thick-walled
components
▪ Minimum required state in the boiler, before a
stable pulverized coal fire can be achieved
Fichtner, 2016
Option 1: Optimized control systems
Basic principle of BoilerMax application ▪ Predictive controller solutions are used for the
online-optimization of start-ups
▪ These controllers are based on dynamic
optimizations and beat the performance of
conventional control systems
▪ Several parameters of a real boiler are analyzed
and optimized for shortening start-up times (e.g.
fuel costs and thermal stress on thick-walled
components)
Option 1: Optimized control systems
Comparison of two start-ups at Zolling, one with BoilerMax and one without
BoilerMax
▪ Due to increased fuel supply and wider opening
of high pressure bypass station the power
station start-up time is shortened by 33% (15
minutes) (Franke & Weidmann, 2008).
▪ The quicker a start-up, the faster the ▪ utilization of high-value materials (e.g. ferritic
temperature of thick-walled components martensitic steel P92) that can cope with
rises thermal stress in a better way
▪ The allowed thermal stress on components ▪ special component design (e.g. Siemens
limits the temperature change rate that can SST5-6000 steam turbine)
be run by a power plant
▪ To realize quicker start-ups, the wall-
thickness of thick-walled components needs
to be reduced
Option 2: Thin-walled components/special turbine design
→ Highest possible efficiency is only achieved with steam at very high pressure and temperature. To
withstand this, components need to be designed rather thick-walled. However, the thicker the
components are the less flexible they are with regard to load and temperature changes.
→ Choosing between thin- or thick-walled components means a consideration if a power plant operator
▪ wants the power plant to be more flexible → rather thin-walled components
▪ wants to have the highest efficiency possible → rather thick-walled components
Option 2: Thin-walled components/special turbine design
Example for reduced wall thickness: Siemens SST5-6000 steam turbine → By redesigning the steam turbine, it was
possible to reduce wall-thickness of the outer
casing and thus enabling a faster heat-up. As
a result, starting performance is improved
(Alstom, 2013).
Fichtner, 2016
Option 1: Repowering
Effect of repowering on ramp rate →Key idea: Using the thermal energy of a gas
turbine exhaust to pre-heat the feed water of the
water-steam circuit to achieve a shorter start-up
time and an improved ramp rate.
→Repowering is a retrofit measure, in which a
gas turbine is implemented into a coal-fired
power plant upstream of the water-steam circuit.
The thermal energy in the exhaust stream of the
gas turbine is transferred to the feed water via
heat exchangers.
→ Gas turbines can start-up significantly faster
than coal-fired power plants.
→With repowering, a second heat source can be
used to pre-heat the feed water. It is therefore
possible to achieve a greater change in heat
input per time, which translates into a faster
ramp rate.
Option 2: Upgrading control systems and plant engineering
Result
→According to (Frohne, 2012), the ramp rate was increased by 10 MW/min as part of the total retrofit
cost of 60 million euros at unit G at Wesweiler.
→According to (Schulze & Hoffmann, 2013), the ramp rate was increased by 6 MW/min as part of the
retrofit at unit D at Neurath.
Option 3: Reducing the wall thickness of key component
Influence of relative pressure on allowable temperature change rate in K/min for
a high pressure header designed with two different materials →Key idea: Reducing the wall thickness of
components, such as headers or separators
increases the allowable temperature change
rate. This allows for faster ramping.
→Reduction of wall thickness can either result
from using superior materials or by increasing
the number of the specific components, e.g.
switching from a 2 line to a 4 line design.
→A reduction of wall thickness by 23% leads to an
increase of allowable temperature change rate
of 60%. This in turn translates into an increase
of ramp rate by 3% (Jeschke, et al., 2012).
Fichtner (2016)
Trade-off between flexibility and efficiency
Illustrative power production of one coal power plant in a day with high share of
renewables (comparison of a flexible and inflexible power plant) → The flexible operation of coal power plants can
700 60 have a negative impact on CO2 emissions at
600 in-feed (right minimum load prevent the power plant to shut-
50 axis) down during some period
500
40 inflexible coal
output (left
400 axis, minimal
30 load 240 MW)
300 flexible coal
20 output (left
200 axis, minimal
load 150 MW)
100 10 inflexible coal
plant (left axis,
switch off)
0 0
1 3 5 7 9 11 13 15 17 19 21 23
hours of the day
Prognos (2017)
The revenue effects for inflexible generation
Hard coal power plant in must-run operation in a 48 hour example period → Due to its limited flexibility in “must run”
operation, the plant has to stay in the market
and experiences losses during times with low
or negative prices.
→ Because the minimum load of the plant is
limited to 40 percent:
36.70 EUR/MWh.
Prognos (2017)
The revenue effects for higher operational flexibility with must-
run condition
Hard coal plant with lowered minimum load to 25% of its nominal capacity and
increased ramp rates in must-run operation in a 48 hour example period → Furthermore, some conventional plants have to
stay in operation because of their relevance for
system services or heat supply (“must-run”
conditions). In this situation, reducing the
minimum load is a key solution for optimising
power plant earnings while limiting losses.
→ The plant is able to generate additional
earnings during some hours after the price
drop:
36.70 EUR/MWh.
Prognos (2017)
The revenue effects for no must-run but limited flexibility
Hard coal power plant with temporary shut-down in a 48 hour example period → If the plant is able to shift to a more flexible
mode of operation, the first possible approach
would be to avoid negative prices and shut
down temporarily during times with negative
prices. However, the plant loses part of its
earnings due to shut-down and start-up times.
→ Because losses during times of negative prices
can be avoided:
42.5 EUR/MWh.
Prognos (2017)
The revenue effects for flexible operation without must-run
Hard coal power plant with lowered minimum load and increased ramp rates
and shorter start-up time in a 48 hour example period → The reduced minimum load mitigates losses
during times of negative prices. The increased
ramp rate and the reduced start-up time leads
to more flexible operation compared to a plant
with weaker flexibility characteristics.
41.5 EUR/MWh.
Prognos (2017)
Enhancing the flexibility parameters of coal power plants can
improve significantly their economic situation within a proper
market environment
Illustrative profit margin of a coal power plant in a short-term market with high Flexible operation of coal power plants can
shares of renewables under different flexibility and must-run conditions. increase operating costs but it minimizes the
losses coming from the increasing shares of
Illustraitve profit margin of a
Prognos (2017)
Flexible coal power plants emit more CO2 per electricity output
than flexible gas power plants, even when taking into account
the overall lifecycle emissions of the fuels.
Efficiency of hard coal and CCGT gas power plants (600 MW nominal power) at CO2 emissions of CCGT and hard coal power plants under similar dispatch
different operating points (up, illustrative) and specific ranges of CO2 emissions for conditions but with different flexibility features during 2 exemplary days
different fuels.(down) 20 ktCO2
60% 18
40% 14
40%
40% 12
35% 31 % 30%
10
20%
8
Min. load Min. load 6
nominal 10%
before after 4
load
retrofit retrofit
0% 2
600 500 400 300 200 100 hard coal gas
0
operating point of a 600 MW power plant (MW)
inflexible "inflexible flexible flexible CCGT CCGT with
Fuel Natural gas Hard coal Lignite coal power coal" coal with coal without must-run
Range of specific 202-300 325-350 340-410
plant with without lower without must-run
emissions gCO2/kWhth] high must- must-run must-run must-run
Specification lower limit Pipeline gas Bituminous coal
Pulverized run
lignite
Fichtner &
Specification upper limit Shale gas Anthracite Raw lignite
Prognos (2017) Agora Energiewende (2017)
In order to fully tap the technical potential for increased
flexibility, it is crucial to adapt the power market conditions.
Power generation from nuclear, hard coal and lignite power plants and demand in
Germany, 23 to 30 March 2016 Economics of flexible coal (retrofit) is significantly
influenced by the availability of remuneration
options for flexibility. A market design which
hampers the investment in flexibility is constraining
the realization of retrofit in coal power plants, as
well as alternative flexibility options.
Existing thermal power plants can provide much more flexibility than often assumed, as experience
1. in Germany and Denmark shows.
Numerous technical possibilities exist to increase the flexibility of existing coal power plants.
2. Improving the technical flexibility usually does not impair the efficiency of a plant, but it puts more
strain on components, reducing their lifetime.
Flexible coal is not clean, but making existing coal plants more flexible enables the integration of
3. more wind and solar power in the system and therefore reduces the overall CO2 emissions.
In order to fully tap the flexibility potential of coal and gas power plants, it is crucial to adapt power
4. markets.
Flexible operation of coal power plants is an interim solution in power systems characterized by very
5. high shares of coal generation.
Agora Energiewende T +49 (0)30 284 49 01-00 Please subscribe to our newsletter via
Rosenstraße 2 F +49 (0)30 284 49 01-29 www.agora-energiewende.de
10178 Berlin @ info@agora-energiewende.de www.twitter.com/AgoraEW
▪ Pump
▪ Boiler
▪ Turbine (coupled with generator)
▪ Condenser
Process steps:
→ Step 1: Pressure increase
→ Step 2: Heat addition through coal combustion
→ Step 3: Expansion in the turbine
→ Step 4: Condensation
Fichtner
The qualitative state changes of water in a water-steam cycle
Simplified representation of the state changes of water in a water-steam circuit Differentiation of subcritical, supercritical and ultra-
supercritical water-steam circuits:
Water-steam circuits can be operated below or
above the critical point of water specified by its
critical pressure and temperature (pc=221,2 bar;
Tc=374,15°C).
Three types of water-steam circuits exist and are
differentiated based on their live steam
parameters:
→ subcritical: 160 bar/535°C
→ supercritical: 240 bar/540°C
→ ultra-supercritical: 285 bar/600°C
The small rectangles represent the water in a liquid state; the large rectangles, the water in steam state;
the blue represents a state at lower temperature and the red a state at high temperature. Fichtner (2017)
Basic working principle of gas-fired power plants
Schematic of a gas turbine in open cycle configurations Joule cycle is the underlying working principle of a gas-fired
power plant. One distinguishes between the open cycle and the
combined cycle configuration.
Basic components:
▪ Compressor
▪ Combustion chamber
▪ Turbine (coupled with generator)
Compressor, gas turbine and generator are mounted on a
common shaft.
Process steps:
→ Step 1: Compression
→ Step 2: Heat addition
→ Step 3: Expansion
Fichtner (2017)
Basic working principle of gas-fired power plants
Schematic view of a combined cycle gas turbine configuration Combined cycle gas turbines contain both the Joule, as well as
the Rankine cycle.
Basic components:
Process steps:
Fichtner (2017)
Comparison of flexibility parameters in different generation
technologies
Comparison of flexibility parameters in different generation technologies
Fichtner (2017); Original sources: (VDE, 2012), (Steck & Mauch, 2008) and (Balling, 2010). The technical data is from OEMs
Option 2: Switching from two-mill to single-mill operation
Operation of four burner stages (left) in comparison to a single burner stage in
single-mill mode (right) →At a certain net power output it is common to
turn off some of the typically 4-6 mills
completely and have the remaining mills operate
closer to their design point.
▪ Steam temperature has to be higher than ▪ Allowing “cold” steam to enter the steam
the metal temperature turbine at an earliest possible point
▪ Plant is kept in bypass operation until boiler ▪ Turbine is enabled to start with the boiler
outlet temperature meets steam turbine which is still ramping-up in load
conditions
▪ Used to be based on static performance
curves of the boiler and did not take any
possible ramp rates into account
50 Hertz
Option 1: Repowering
Simplified illustration of a coal-fired power plant with a gas turbine employed for
feed water pre-heating → Key idea: Using the thermal energy of a gas
turbine to pre-heat the feed water of the water-
steam circuit to achieve a shorter start-up time
and to improve ramp rates.