Professional Documents
Culture Documents
The Concept
The Concept
The Concept
heritage square
to Arundel/
railway station
wetland centre
87
Waterfront planning
88
Hydroscape
59
89
Water and energy infrastructure
90
Aquatecture
91
92
Lessons learned
Located in the estuarine lower catchment of the defences to cope with future sea level rise.
the River Arun, Littlehampton is susceptible Structural resilience of buildings was necessary
to a range of flood risks; the greatest risk to cope with residual flood risk behind
is from storm surges from the sea. Flood defences. The lower catchment was found
volumes are too great to accommodate to be windy and tidal, providing abundant
on the development site. Land raising and sources of renewable energy for a zero-carbon
flood defences were needed to provide the development. Consideration of regional
necessary standard of protection. Space was strategies was found to help resolve local
needed to accommodate improvements to site-specific issues.
93
Findings > cost analysis of the LifE approach
The costs of delivering the LifE objectives of The cost increase was due to far higher public transport connections, car clubs and
making space for water, living with water and environmental design standards being reducing car parking provision reduced costs
eco-design were found to add to traditional met.11 The cost of the eco-design measures by 10% to 38% and provided more space for
development costs. However, it was found that accounted for 25% of the increase; it should landscaping and flood storage.
integrating measures could reduce the costs be noted that as the base traditional standards
and provide more extensive environmental have since risen, the cost difference would Summary
benefits. The renewable energy required for have decreased. The cost of making space for water/providing
the eco-design was the most significant cost ecological flood mitigation is achievable. A
and therefore locations where more efficient In contrast, the cost of providing ‘space for landscape-led approach to planning can help
technology could be used helped to reduce water’ was found to be marginally cheaper to reduce capital costs of transport, drainage
the capital cost. than providing flood defences. The cost of and energy infrastructure. It reduces hard
flood-risk management was found to increase surfaces and enables sustainable drainage on
To raise development from UK Building the lower down the river catchment the site the site. By providing space for medium and
Regulations 2006 to the LifE standards could was located. However, the range of renewable large wind turbines, which would otherwise
result in a capital cost increase of between 21% energy sources on site increased; therefore be too close to the development, helps to use
and 37%, indicated in Figure 2.68. It was found achieving a zero-carbon development became more efficient renewable energy technologies.
to be possible to reduce this cost increase to more feasible and the overall cost reduced.12
between 11% and 34% on the LifE case study
sites by integrating functions. It is expected that the cost of renewable
energy will fall in the future through increased
The cost to improve the development to LifE production and technological advances. This
standards for each site was: should then enable more cost-effective use of
technologies such as PV, GSHP and tidal.
• Site 1: Hackbridge (urban, upper
catchment) – 34% increase over traditional. The cost of ‘living with water’ by improving
• Site 2: Peterborough (suburban, middle certain buildings to make them flood-resilient
catchment) – 32% increase over traditional. and decrease flood risk increased the
• Site 3: Littlehampton (coastal, lower development cost by between 2% and 11%,
catchment) – 11% increase over traditional. depending on the location. Providing better
94
LifE time costs
95
LifE lessons region, due to the extent of flood defences the suitability of proposals. For each of the
required relative to the site area. sites a transferable message was created
as follows:
Integrated spatial planning requires
simultaneous assessment of multiple issues Upper catchment > Let rain slow
and criteria. The main drivers for change in The key was to slow the flow of rainwater to
The LifE project demonstrated the potential the way development in the UK is planned reduce the risk of surface water flooding and
of integrated planning to manage flood risk in the 21st century are sustainability and reduce peak river flows downstream.
and deliver more sustainable development. climate change. These are manifest in the
It showed that sustainable development need to make developments zero carbon, Middle catchment > Let river flow
requires space: for water, energy and amenity. conserve water, reduce unsustainable The key was to allow flood water to flow
It also illustrated that when considering transport use (namely cars, including electric through the site in a predetermined way,
core elements such as recreational space or or biodiesel cars unless powered from without risk to lives or property and without
renewable power, the spatial requirements renewable sources), reduce overheating increasing flood risk downstream.
could individually exceed the footprint of and manage flood risk. There are potential
the site. The spatial needs of each of the benefits from measures introduced to Lower catchment > Let tides go
three sites are illustrated opposite. It was respond to these issues but understanding The key was to avoid storms and let peak
only when synergies between these uses which to prioritise is fundamental to good tides go around development sites, and to
and programmes overlapped that the LifE planning. Of these issues flooding is the attenuate rainwater on site.
objectives of making space for water, living main risk to life and therefore should be the
with water, and eco-design were possible. priority. Space for water needs to be integrated
with sustainable design, so that the means
Although any site may be developed As the population expands and our resources of managing flood risk become an asset to
independently, the LifE case studies dwindle, the pressure on our land to provide the development and the wider community.
demonstrated the benefit of cross-scale more with less intensifies. The need to Multifunctional land use that makes space for
proposals. By developing a flood risk strategy use spatial and physical resources wisely water, energy and play within developments
across multiple development sites, it was becomes imperative and the need for must be fundamental to sustainable
possible to find the best solution for the whole multifunctionality intensifies. With the added development in the 21st century if we are to
Hackbridge neighbourhood. By considering pressures of rising frequency, intensity and adapt to the challenges of climate change.
various riverside sites, it was possible to extent of extreme events we need to provide
allocate the best uses according to flood more space for water and have a greater In the following chapters we further explore
risk and vulnerability, as well as the needs of respect for natural processes. Consideration designing with water, through waterfront
the surrounding city. The cost to redevelop of the wider context, particularly the location planning, aqua(archi)tecture, hydro(land)
the harbour site in Littlehampton would be of the sites within the river catchment, was scapes and water and energy infrastructure.
prohibitive without considering the wider essential to understanding the flood risk and
96